NATIONAL GREEN TRIBUNAL NEW DELHI (PRINCIPAL BENCH)
PRAKASH SHRIVASTAVA, CJ, SUDHIR AGARWAL, J, DR. A. SENTHIL VEL, ACJ
Purab Premium Apartments Allottees Association – Appellant
Versus
Greater Mohali Area Development Authority – Respondent
Original Application No. 493/2023 | Original Application No. 572/2023
| Table of Content |
|---|
| 1. allegations of environmental violations by gmada affecting resident safety. (Para 1 , 2) |
| 2. gmada's noncompliance with environmental clearances leading to multiple issues. (Para 3 , 4 , 5 , 6) |
| 3. the tribunal's findings on gmada's responsibilities and required compliance. (Para 7 , 8 , 9 , 10 , 11 , 12) |
| 4. final directives and responsibilities for compliance established by the tribunal. (Para 13 , 14) |
ORDER
1. In OA No. 493/2023, the applicant which is a registered society, has raised a grievance against violation of environmental norms and clearance conditions in the construction and operationalization of a group housing project by the respondent no. 1, Greater Mohali Area Development Authority (GMADA) by the name "Purab Premium Apartments" in sector 88, Sahibzada Ajit Singh Nagar, Mohali, Punjab having environmental clearance for construction of 6360 flats (Type I-1080, Type II-2520 and Type III-2760 flats) in an area of 117.118 acres. The allegation of the applicant is that the environmental clearance (EC) conditions have been violated, and no Sewage Treatment Plant (STP) has been installed. The applicants were compelled to take possession of uninhabitable apartments based on an allotment letter and offer of possession containing the condition to take possession within 30 days or the allottee shall not be entitled to take benefit of any rebate or refund on any ground whatsoever.
2. It is further alleged that only 1620 flats in 37 acres have been constructed and the residents are deprived of fresh drinking water and the Respondent No. 1 has even failed to comply with the most important safety protocol, which includes fire safety certificate and several other conditions of EC have been violated by the Respondent No. 1 such as submission of the six-monthly report. It has also been alleged that Respondent No. 1 had failed to obtain NOC from the Ministry of Defence requiring the installation of a Garbage Treatment Plant to avoid birds’ activity.
3. OA No. 572/2023 was registered based on a letter petition making a complaint in respect of the same project and complaining that the families residing in the flats were facing dust and noise pollution on account of incomplete construction projects. They were getting contaminated water due to lack of STP and instead of constructing 4500 flats only 1620 flats on 37 acres have been constructed, which require a fresh appraisal by State Environment Impact Assessment Authority (SEIAA), Punjab and the EC has expired, and the project is still incomplete, and the life of the residents has been put to risk.
4. Respondent No. 1, Project Proponent was issued the EC dated 14.03.2013 by the SEIAA, Punjab, providing for as many as 17 specific conditions to be complied with during the construction phase and as many as 14 conditions to be complied with in the operational phase. The EC also had 16 general conditions. This EC has undisputedly expired on 13.02.2020 and has not been reviewed thereafter. Specific Conditions for the construction phase and specific conditions for the operational phase mentioned in the EC were as under:-
“PART A- Specific conditions:
I. Construction Phase i) “Consent to Establish” shall be obtained from Punjab Pollution Control Board under Air (Prevention & Control of Pollution) Act, 1981 and the Water (Prevention & Control of Pollution) Act, 1974 and a copy of the same shall be submitted to the Ministry of Environment & Forest/State Level Environment Impact Assessment Authority before the start of any construction work at site.
ii) All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained throughout the construction phase.
iii) A first aid room will be provided in the project both during construction and operation phase of the project.
iv) All the topsoil excavated during construction activities should be stored for use in horticulture/landscape development within the project site.
v) Disposal of muck dur
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.