NATIONAL GREEN TRIBUNAL CHENNAI (SOUTHERN ZONE BENCH)
Pushpa Sathyanarayana, Judicial Member, Satyagopal Korlapat, Expert Member
Shoukkath Ali – Appellant
Versus
Ministry of Environment, Forests and Climate Change – Respondent
Appeal No.43 of 2024 (SZ)|I.A. Nos.115 & 124 of 2024 (SZ)
| Table of Content |
|---|
| 1. appeal challenges ec for quarry due to violations. (Para 1 , 2 , 3) |
| 2. appellant alleges procedural lapses and environmental risks. (Para 4 , 5 , 6 , 7) |
| 3. seiaa defends appraisal process and site inspections. (Para 8 , 9 , 10 , 11) |
| 4. proponent denies violations, cites compliance measures. (Para 12 , 13 , 14 , 15) |
| 5. high court directed seiaa consideration; prior rejection noted. (Para 17 , 18 , 19 , 20 , 22 , 23 , 24) |
| 6. cpcb guidelines mandate 200m distance for blasting. (Para 25 , 26 , 27 , 28 , 40 , 41) |
| 7. fresh application; 2016 dsr acceptable per high court. (Para 29 , 30 , 31) |
| 8. hydrogeological conditions imposed; channel needs scrutiny. (Para 32 , 33 , 34 , 35) |
| 9. biodiversity and mitigation conditions examined. (Para 36 , 37 , 38) |
| 10. distance shortfall violates cpcb norms. (Para 39 , 42 , 43) |
| 11. ec kept in abeyance; remit for re-evaluation. (Para 44 , 45) |
JUDGMENT
Delivered by Smt. Justice Pushpa Sathyanarayana, Judicial Member
1. The appeal is challenging the Environmental Clearance dated 01.07.2023 granted to the 5th Respondent for quarrying operations in Pulamanthole Village, Malappuram District, alleging procedural violations, environmental risks and impact on livelihoods due to the project.
2. The 5th Respondent originally had submitted an application for Environmental Clearance before the District Level Environmental Impact Assessment Authority (DEIAA) - Malappuram for the granite building stone quarry project for an extent of 1.8227 Hectares at Sy. No. 85 (pt).
3. The appellant herein filed a Writ Petition No.41905 of 2017 before the Hon’ble High Court of Kerala, in which, the Hon’ble High Court vide its Judgement dated 11.04.2018 directed the State Environmental Impact Assessment Authority (SEIAA) - Kerala to consider the application and pass orders, therein, and to submit a copy before the Hon’ble High Court within 03 months from the date of receipt of files from the DEIAA. Accordingly, after the papers were forwarded from the DEIAA, the SEIAA – Kerala had considered the proposal and passed the impugned order.
4. According to the appellant, the application for Environmental Clearance applied by the 5th Respondent was beyond the time stipulated in S.O. 804 (E) dated 14.03.2017 and O.M. dated 30.05.2018. It is stated that pursuant to the interim order of the Hon’ble High Court on 11.04.2018, the Environmental Clearance was granted on 03.11.2021. The SEIAA – Kerala was aware of the complaints raised by the appellant against the project. However, the issues raised even in the Writ Petition were not considered by the SEIAA – Kerala before issuing Environmental Clearance. The SEIAA - Kerala has not considered the fact that no District Survey Report (DSR) was approved or prepared by the 2nd Respondent for the Malappuram District. There is no separate DSR for granite/building stone made or considered by the SEIAA – Kerala before granting Environmental Clearance. The impugned Environmental Clearance is in violation of EIA Notification, 2006 and its amendments.
5. It is alleged further that in the absence of the hydrogeological study and appraisal of the same by the SEAC – Kerala, the proposed project would affect water table in the appellant area once the mining operation commenced. Without the hydrogeological study being conducted, the Environmental Clearance ought not to have been issued. Thus, the appellant has alleged that SEAC – Kerala and SEIAA – Kerala failed to conduct a meaningful appraisal of the project. It is ascertained by the appellant that the authorities acted mechanically relying solely on the documents submitted by the Project Proponent without individual application of mind regarding the validity or comprehensiveness of the same.
6. It is also alleged that there was no public hearing thus depriving the stakeholders of the opportunity to voice their concerns. Specific concerns like ground water depletion, structural damage to nearby residences due to blasting and the likelihood of landslides owi
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.