NATIONAL GREEN TRIBUNAL CHENNAI (SOUTHERN ZONE BENCH)
Pushpa Sathyanarayana, Judicial Member, Satyagopal Korlapati, Expert Member
Jesu Rethinam – Appellant
Versus
Tamil Nadu Coastal Zone Management Authority – Respondent
Original Application No.101 of 2023 (SZ)



Advocates:
For Applicant(s): Mr. A. Yogeshwaran
For Respondent(s): Mr. P.S. Raman, Mr. S. Sai Sathya Jith, Dr. D. Shanmuganathan, Mr. AR. L. Sundaresan, Mr. S. Janarthanam

Draft CZMP maps must include all mandated features, undergo ground truthing for omissions, and enable meaningful public consultation per CRZ Notification 2019.

Headnote:(A) CRZ Notification, 2019 - Annexure IV - Preparation of CZMP maps - Mandatory components including fishing zones, village boundaries, breeding grounds, common properties, long-term housing plans, ecologically sensitive areas (sand dunes, turtle nesting grounds, seagrass beds, mangroves), erosion zones, and hazard line land use planning must be marked; 1:25000 scale for draft public consultation, 1:4000 scale for local-level post-approval; ground truthing required for specific omissions noticed; public consultation must be meaningful with complete draft maps. (Paras 3, 4, 17, 18, 21, 36, 42)

(B) Environmental Law - Public participation - Draft CZMP must be near-final to enable informed objections; authorities to incorporate stakeholder inputs, district collector suggestions before final publication; no general unsubstantiated claims to delay process. (Paras 24, 30, 41)

Facts of the case:
Applicants challenged draft CZMP maps (TN 01 to TN 105) for 12 Tamil Nadu districts as incomplete, lacking key fisherman community features, ecologically sensitive areas, erosion zones, written plans, proper scale, and comparison with prior maps; prior Tribunal/High Court orders on similar deficiencies not fully complied.

Findings of Court:
Draft maps incomplete; directed ground truthing for specified ecologically sensitive areas, incorporation of district collector inputs and fisheries data, corrections per CRZ 2019 Annexure IV before republication and public hearing.

Issues: Compliance of draft CZMP with CRZ Notification 2019 requirements; adequacy of marked features, scale, public accessibility, and prior judicial directions.

Ratio Decidendi: CZMP preparation demands comprehensive inclusion of all mandated features via satellite imagery and ground truthing where omissions specifically identified; meaningful public consultation requires substantially complete drafts to protect coastal ecosystems and community livelihoods.

Result: OA disposed with directions.

Table of Content
1. challenge to incomplete draft czmp maps lacking key features. (Para 1 , 2 , 3 , 4 , 14)
2. history of crz notifications and prior judicial interventions. (Para 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13)
3. responses on inclusion of fisherman features and dynamic updates. (Para 17 , 24)
4. marking of ecologically sensitive areas in crz-ia. (Para 18)
5. compliance with judicial orders, scale, consultation process. (Para 19 , 20 , 21 , 22 , 23)
6. necessity of ground truthing and complete drafts for consultation. (Para 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41)
7. directions for corrections, ground truthing, and republication. (Para 42 , 43)

JUDGEMENT

Delivered by Smt. Justice Pushpa Sathyanarayana, Judicial Member

1. The fishermen community represented by the first applicant and the second applicant himself being a member of the fishermen community have challenged the draft Coastal Zone Management Plan (CZMP) Maps uploaded by the respondent authority on the website of the Department of Environment.

2. It is alleged that the 105 Maps uploaded for the districts of Chengalpattu, Cuddalore, Kanyakumari, Mayiladuthurai, Nagapattinam, Pudukkottai, Ramanathapuram, Thanjavur, Thiruvaur, Thoothukudi, Tirunelveli and Villupuram are incomplete, as they do not even have all the necessary components marked in the maps.

3. It is alleged further that the fundamental components like fishing zone in the water bodies and fishing village boundaries, breeding and spawning grounds of fish, common properties of the fishermen community, and detailed plans for long-term housing needs of coastal fishing community are not earmarked on any of the 105 CZMP map sheets uploaded. The map also had not marked the existing authorized developments on the seaward side which would result in frustrating the identification of future violations. The ecologically sensitive features like sand dunes, turtle nesting grounds, seagrass beds, sanctuaries, and reserve forests have also not been marked.

4. It is further alleged that no written plan has been published and only a generic document stating the contents of the CRZ Notification is published. There is also no specific long- term housing plan for coastal fishermen which is an essential component considering the threat of climate change induced sea level rise. The difference between the previous map and the present map is not distinctly marked for easy understanding. Though 1:4000 scale maps have to be uploaded for scrutiny, only 1:25000 scale maps have been prepared and uploaded for comments. Finally, erosion zones have not been marked despite directions from this Tribunal in O.A. No.04 of 2013 (SZ).

5. This is not the first occasion or litigation relating to the preparation of the CZMP. There were challenges earlier before this Tribunal as well as before the Hon’ble High Court.

6. The Central Government, with a view to ensure the livelihood, and security of the fishermen communities and other local communities living in the coastal areas, to conserve and protect the coastal stretches, its unique environment and its marine area and to promote development through sustainable manner based on the scientific principle taking into account the dangerous of the natural hazards in the coastal area, sea level rise due to global warming, issued the CRZ Notification, 1991 vide S.O. 114 (E) dated 19.02.1991. These regulations are issued to strike a balance between economic growth and environmental conservation.

7. By implementing these regulations, the countries can safeguard fragile ecosystems. The first CZMP was prepared based on the 1991 Notification in the year 1996 and the same was approved on 27.09.1996. Subsequently, the CRZ Notification, 1991 was superseded by CRZ Notification, 2011 in S.O. No.19 (E) dated 06.01.2011. Clause (5) of the CRZ Notification, 2011 provides for the preparation of the CZMP. Thereafter, the said CRZ Notification, 2011 issued in S.O. 19 (E) dated 06.01.2011 was

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top