NATIONAL GREEN TRIBUNAL BHOPAL (CENTRAL ZONE BENCH)
HON’BLE MR. JUSTICE SHEO KUMAR SINGH, J
Dheeraj Tiwari – Appellant
Versus
MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE – Respondent
JUDGMENT
1. This Application has been filed by the Applicant with the following prayers:-
“(a) Quash and set aside the Consent to Operate dated 23 August 2024 and/or any other consent to operate being issued to Respondent No. 6 during the pendency of the instant application;
(b) Directions be passed for the immediate closure of the Respondent No. 6’s Unit at Plot No. 17/N, Heavy Industrial Area, Hathkhoj, Bhilai, District – Durg, Chhattisgarh;
(c) Directions be passed for the stay of the operation of the Respondent No. 6’s Unit at Plot No. 17/N, Heavy Industrial Area, Hathkhoj, Bhilai, District – Durg, Chhattisgarh till disposal of this application;
(d) Directions be passed upon the Respondent No. 3 not to issue any consent to operate to the Respondent No. 6 till the pendency of this application;
(e) Direct the Respondent No. 5 and 7 to stay the grant of Environmental Clearance to the Respondent No. 6 till the disposal of this application;
(f) Injunction restraining the operation of the Unit of the Respondent No. 6 at Plot No. 17/N, Heavy Industrial Area, Hathkhoj, Bhilai, District – Durg, Chhattisgarh, till the Respondent No. 6 is granted the Environment Clearance as per the EIA 2006 dat
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.