Important Points
Subject
Environmental Law - Industrial Pollution and Regulatory Compliance
Act Referred
Headnote
(B) Administrative Law - Doctrine of exhaustion of alternative remedies - Jurisdiction of tribunal - Availability of statutory remedy under relevant acts - Requirement to approach competent authorities before approaching judicial forums - Limitation period under tribunal act. (Paras 15, 16, 22, 23, 24)
Facts of the case:
The application alleged that various mineral grinding and stone processing units were discharging untreated water, hazardous dust, and silica particles into open spaces without remedial measures. It was claimed that these units violated pollution control guidelines, particularly concerning proximity to habitation and unauthorized groundwater extraction, causing health hazards and environmental degradation. The Respondents argued that the application was time-barred, that statutory remedies were not exhausted, and that they had valid consents and were implementing necessary pollution control mechanisms.
Findings of Court:
The joint committee inspection revealed that units possessed valid consents and were taking steps to manage waste through designated dumping yards. Although initial deficiencies in plantation, record-keeping, and groundwater extraction were noted, the relevant authorities had initiated show-cause processes, and units had since obtained requisite permissions or initiated compliance. The tribunal found no evidence of violation of water bodies and affirmed that revenue-related disputes regarding encroachments fall outside its jurisdiction.
Issues: The main issues were whether the industrial units were causing environmental degradation through unauthorized discharge and extraction, whether the application was barred by limitation and the doctrine of exhaustion of alternative remedies, and whether the tribunal should intervene in matters pending before executive/revenue authorities.
Ratio Decidendi: The tribunal maintains that where statutory mechanisms and competent authorities are already exercising oversight and enforcement powers regarding pollution control, the tribunal will not interfere unless there is a failure to exercise such power or persistent non-compliance. The applicant must exhaust administrative remedies provided under the prevailing environmental and revenue statutes.
Result: Original Application dismissed, with directions to the authorities to monitor compliance periodically.
For the Appellants/Petitioners: Seema Roj, Kamlesh Roj
For the Respondents: Shantanoo Saxena, Ashwin Rastogi, Kartik Bhatia, Om Shrivastava, Rohit Sharma, Om Shankar Shrivastava, Dharam Vir Sharma, Gigi George
| Table of Content |
|---|
| 1. allegations of environmental pollution and violation of industrial guidelines. (Para 1 , 2 , 3 , 4) |
| 2. factual assessment of industrial compliance and pollution control status. (Para 5 , 6 , 7 , 8 , 9 , 10 , 11) |
| 3. standards for pollution control in mineral grinding industries. (Para 12 , 13 , 14) |
| 4. procedural objections regarding limitation periods and exhaustion of remedies. (Para 15 , 16 , 17 , 18) |
| 5. requirement to exhaust statutory remedies before tribunal intervention. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30) |
| 6. final adjudication on regulatory oversight and compliance monitoring. (Para 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42) |
JUDGMENT
1. Issue raised in this application is discharge of untreated water into the open space, violation of environmental rules, discharging hazardous dust and silica particles into the open space without any remedial measures causing severe air and water pollution.
2. Respondents Nos. 5 to 20 are engaged in both quartz manufacturing and natural stone processing. The quartz manufacturing process involves crushing raw quartz into powder, which, along with additives, is used to create slabs. This process generates significant amounts of dust and fine silica particles, contributing to air pollution. Approximately 15% to 25% of the raw material becomes waste, which is released into the atmosphere, creating severe environmental and health issues. Additionally, Respondents Nos. 15 to 20, involved in large-scale stone cutting, discharge contaminated water and dust onto open lands without authorization, further exacerbating environmental degradation.
3. The Respondents have violated several regulations, including the "Guidelines for Abatement of Pollution in Mineral Grinding Industry" and specific conditions outlined in their Consents to Establish (CTE) and Operate (CTO). Despite the mandate to maintain zero discharge status and adhere to pollution control guidelines, these units have been found discharging waste into open lands and water bodies. The guidelines also require plantation of trees within the plot area, which the Respondents have failed to implement. Furthermore, they have ignored the prohibition on groundwater use without authorization, leading to groundwater depletion.
4. The matter was taken up by the Tribunal and a Committee consisting the Representative of the Secretary Environment, Jaipur, Secretary Forest Jaipur and one representative from Member Secretary Rajasthan State Pollution Control Board, was constituted with direction to submit the factual and Action Taken Report. Respondents are directed to submit their reply.
5. The Members of the committee visited the site and submitted the report. Objection of the response on the report has been filed.
6. Respondents have filed the reply which is on record. We have heard learned counsel for the parties and perused the records.
7. The submission of the learned counsel for the Application are that Respondents Nos. 5 to 20 are discharging substantial quantities of powder waste and contaminated water in the vicinity of their respective units.
8. This practice has resulted in the creation of unauthorized open dump yards. The establishment and maintenance of these open dump yards have been carried out without obtaining the necessary permissions or approvals from the relevant authorities, Respondents Nos. 5 to 20 are discharging substantial quantities of powder waste and contaminated water in the vicinity of their respective units. This practice has resulted in the creation of unauthorized open dump yards. The establishment and maintenance of these open dump yards have been carried out without obtaining the necessary permissions or approvals from the relevant authorities, there constituting an illegal act and exacerbating environmental degradation.