2023 Supreme(Online)(ORI) 3468
ORISSA HIGH COURT
B.R.SARANGI, Biraja Prasanna Satapathy, J
M/S.RAJLAXMI CONSTRUCTION LTD. CUTTACK – Appellant
Versus
STATE OF ODISHA – Respondent
WP(C)/2334/2023
Page 1 of 6
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P (C) No. 2334 of 2023
M/s. Rajlaxmi Construction Ltd.,
Cuttack
…..
Petitioner
Mr. P.C. Nayak, Adv.
Vs.
State of Odisha and others
…..
Opposite Parties
Mr. P.P. Mohanty, AGA
CORAM:
DR. JUSTICE B.R. SARANGI
MR. JUSTICE B.P. SATAPATHY
ORDER
27.01.2023
Order No.
01.
This matter is taken up through hybrid mode.
2.
Heard Mr. P.C. Nayak, learned counsel appearing for
the petitioner and Mr. P.P. Mohanty, learned Addl.
Government Advocate appearing for the State-opposite
parties.
3.
Mr. P.C. Nayak, learned counsel appearing for the
petitioner contended that this matter is covered by the order
dated 17.08.2022 passed by this Court in W.P.(C) No. 20632
of 2022. Copy of the said having been served on learned State
Counsel in Court today and he acknowledged the same.
Therefore, on the agreement of the parties, this order is being
passed.
4.
The petitioner has filed this writ petition seeking to
quash the order dated 06.03.2018 under Annexure-1 and in
imposition of penalty @ 0.50% of the agreement value and
not approving the price escalation amount for the extended
period and further to issue direction to the opposite parties to
release the price escalation amount in terms of agreement and
Page 2 of 6
in terms of the judgment of this court in Raghunath Sahu v.
State of Odisha, AIR 2022 Orissa 37 for the work
“Construction of H.L. Bridge over river Koel and approaches
at Jhirpani in the district of Sundargarh under NABARD
Assistance RIDF-XIII.
5.
Mr. P.C. Nayak, learned counsel appearing for the
petitioner contended that imposition of penalty and rejection
of claim of the petitioner by the authority vide order dated
06.03.2018 under Annexures-1 cannot sustain in the eye of
law, in view of the fact that no opportunity of hearing was
given to the petitioner. Had the opportunity been given, the
petitioner would have brought to the notice of the authority
with regard to the judgment rendered by this Court in
Raghunath Sahu (supra). Thereby, gross illegality and
irregularity has been committed by the authority in passing
the order impugned, which is liable to be quashed.
6.
Mr. P.P. Mohanty, learned Addl. Government Advocate
appearing for the State-Opposite Parties contended that since this
question has already been decided by this Court in Raghunath
Sahu (supra), while considering the case of the Petitioner, the
Authority could have considered the same and passed appropriate
order in accordance with law. As the said benefit has not been
given to the Petitioner, the Order so passed by the Authority
cannot have any justification.
7.
Though the matter was listed under the heading ‘fresh
admission’, but with the consent of learned counsel for the
parties, this writ petition is being disposed of at the stage of
Page 3 of 6
admission.
8.
Having heard learned counsel for the parties and after
going through the records, it appears that similar matter had
come up for consideration before this court in Raghunath
Sahu (supra) and this Court in paragraphs-20, 21, 22 and 25
held as follows:
“20. Therefore, taking into consideration the meaning
attached to the word ‘escalation’, as per terms and
conditions of the agreement, the petitioner is entitled to get
escalation cost but not the compensation, for which the
blockage of the escalation benefit has been made. Needless
to say, an ‘undertaking’ is nothing but a standard form,
which every contractor has to sign and submit to the effect
that he shall not claim for compensation for delay in work
and extend the period of work. This is submitted whenever
extension of time is granted for completion of work or else
extension will not be granted. This document is signed,
without adjudicating the merits of the claim of the
petitioner, and is done under duress or else the contract
would be liable to be terminated with penalty, even though
the petitioner may not