IN THE HIGH COURT OF ORISSA AT CUTTACK
CONTC No. 5482 of 2025
Krupasindhu Gahan
…..
Petitioner
Mr. Milan Kanungo, Senior Advocate
-versus-
1.Shri Digbijay Biswal
2.The Superintendent of Police,
…..
Opp. Parties
Economic Offence Wing (EOW),
Bhubaneswar
Mr. Dolagobinda Mohapatra, Advocate
Mr. Sarathijyoti Mohanty, Additional Standing Counsel (for O.P. No.2)
CORAM:
HON’BLE MISS JUSTICE SAVITRI RATHO
08.04.2026
ORDER
Order No. 12.
(Through hybrid Mode)
1. Perused the compliance affidavit dated 04.09.2025 filed by the Opposite Party No. 1 - contemnor Shri Digbijay Biswal in paragraph 4, 5, 6 and 7 of the affidavit are extracted below;
“4. That the petitioner filed the abovementioned Criminal Misc. Case for a direction to quash the impugned order dated 05.10.2024 passed by the Learned S.D.J.M Talcher in G.R. Case No. 1198/24 and to transfer investigation of the case to Economic Offences Wing, Police Station, Bhubaneswar and this Hon'ble Court vide judgment dated 19.06.2025 disposed of the aforesaid Criminal Misc. Case with a direction to hand over the case diary and other relevant records to the Superintendent of Police, EOW, Bhubaneswar within a period of ten days for assigning the investigation to a competent officer.
5. That it is humbly submitted that after disposal of the aforesaid Criminal Misc. Case, the petitioner has not produced the certified copy of the judgment dated 19.06.2025 before the office of the deponent. Further, no communication has been received by the Office of the deponent regarding passing of judgment dated 19.06.2025 in CRLMC No.201/25.
6. That it is humbly submitted that the deponent while checking the present status of the aforesaid Criminal Misc. Case on 02.08.2025 came to know that the aforesaid Criminal Misc. Case has been disposed of by this Hon'ble Court vide judgment dated 19.06.2025. Thereafter, the deponent immediately intimated the aforesaid fact to the Superintendent of Police, Angul vide D.R. No.2625/Talcher PS, dated 02.08.2025, copy of which is filed herewith as Annexure-A/1.
7. That on the basis of letter under Annexure-A/1, the Superintendent of Police, Angul vide Letter No.5109/DCRB, dated 07.08.2025 requested the Superintendent of Police, EOW, Bhubaneswar for taking charge of investigation of Talcher P.S. Case No.641/24 and also vide Letter No.3098/DCRB, dated 07.08.2025 directed the deponent to depute one Special Messenger to hand over the charge of investigation of the aforesaid case to EOW, Bhubaneswar in compliance to the judgment passed by this Hon'ble Court. Copies of Letter No.5109/DCRB, dated 07.08.2025 and Letter No.3098/DCRB, dated 07.08.2025 are filed herewith as Annexure-B/1 and Annexure-C/1 respectively.”
2. From reading of these paragraphs, it is apparent that on 19.06.2025, direction had been issued for handing over the case diary to the EOW within a period of 10 days. It is apparent from a perusal of the order sheet in CRLMC No. 201 of 2025 that on 15.05.2025, the Opposite Party No. 1 - contemnor was present on virtual mode. On the said date, after hearing the learned counsel for the parties the matter was posted to 18.06.2025 for delivery of judgment. Since, this order was passed in his presence, he was aware of the date when the case was fixed for judgment. On 18.06.2025, as the judgment was not ready the matter was directed to be listed on 19.06.2025 for delivery of judgment and judgment was delivered on 19.06.2025. The contemnor was aware of the date and when the matter was initially posted for judgment. He should therefore have checked the order on 18.06.2025. Hence, it is not known as to why he waited for 2 months, i.e. till 02.08.2025 to check the website for the order.
3. As the direction had been issued for handing over investigation to the EOW, as it was found that investigation was not being conducted in a proper way and the direction dated 05.10.2024 of the learned SDJM, Talcher directing the IO to conduct a fair and proper investigation had not been complied in spite of the case being registered on 06.08.2024 and during the pendency of the investigation, withdrawals have been made from the demat account.
4. Mr. Kanungo, learned Senior counsel for the petitioner submits that in paragraph 10 of his affidavit, the contemnor has begged unconditional apology for the delay stating that the delay in compliance of the orders of this Court was