2024 Supreme(Online)(Pat) 1769

PATNA HIGH COURT
M/s Rathore and Bishwajeet Infra Developers Pvt. Ltd. – Appellant
Versus
The State of Bihar – Respondent


ORAL JUDGMENT

(Per: HONOURABLE THE CHIEF JUSTICE)

Date : 24-01-2024 Petitioner has approached this Court for quashing of an order dated 20.11.2021 passed under Section 73 of the Bihar Goods and Services Tax Act, 2017 (for brevity ‘BGST Act’). There was an appeal provided under the BGST Act’. As per Section 107(4), an appeal would be maintainable within three months of the order or with a delay condonation application within a further period of one month. No such appeal has been filed. The writ petition is itself delayed for almost one year.

2. This Court and the Hon’ble Supreme Court have held that when there is a specific period provided in the statute, within which period a delayed appeal could be filed; then neither the Appellate Authority nor this Court under Article 226 of the Constitution of India could condone the delay beyond the period provided.

3. The Central Board of Indirect Taxes and Customs has by Notification No. 53 of 2023- Central Tax, dated 02.11.2023 (S.O. 4767(E)) extended the time for filing appeal against an order passed by the Proper Officer on or before 31.03.2023 under Sections 73 and 74 of the ‘BGST Act’. This in fact extends the period for filing a delayed ap

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top