2025 Supreme(Online)(Pat) 1830

PATNA HIGH COURT
MR. RAJIV ROY, J
The Union of India through Assistant General Manager Engineer (Civil) Airports Authority of India Gaya Airport, Gaya-923004 (Bihar) – Appellant
Versus
Brajesh Kumar Sinha son of Sri Bharat Sinha, Resident of behind H/150, Veer Kunwar Singh Colony, Hinoo, Ranchi, P.O.-Hinoo, P.S.-Doranda, District-Ranchi-834002 – Respondent
Miscellaneous Appeal No.449 of 2025 | Arbitration Case No 18/2024



Advocates:
For the Appellant/s: Mr. Dr. Pankaj
For the Respondent/s: Mr. Saurabh Bishwambhar

The court ruled that an application to set aside an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is strict in nature with a non-extendable time limit, and appeals filed beyond this limit are time barred.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Appeal against arbitral award - Application for setting aside the award filed after delay of 197 days - No sufficient cause established for delay - Award passed by the Sole Arbitrator became enforceable post expiration of the time limit prescribed under Section 34(3) - Thus, the appeal was dismissed for being time barred. (Paras 17-18)

(B) Limitation - The interpretation of Section 34(3) of the Act indicates that an application to set aside an arbitral award cannot be made after three months from the date of receipt of the award or disposal of a Section 33 request - The court cannot entertain the application beyond prescribed time frame even with sufficient cause. (Paras 47-50)

(C) Judicial Review - Emphasis on minimizing judicial intervention in arbitral proceedings as per the Arbitration and Conciliation Act, 1996. (Paras 36-50)

Facts of the case:
The appellants contested an arbitral award passed in favor of the claimant-respondent regarding a construction contract with the Airports Authority of India. Following disruptions and a delay in construction due to local unrest, the case went to arbitration, resulting in an award that the appellants sought to challenge.

Findings of Court:
The court concluded that the application under Section 34 was dismissed as it was filed beyond the permissible period, with no sufficient reasons to warrant the delay being acknowledged.

Issues: Whether the application under Section 34 of the Act was barred by limitation and whether the case merited judicial intervention despite the delay.

Ratio Decidendi: Section 34(3) establishes strict timelines for filing applications for setting aside an arbitral award, which cannot be extended, emphasizing the significance of adhering to statutory limitations.

Result: Appeal dismissed.

Table of Content
1. introduction of the parties involved. (Para 1 , 2 , 3)
2. tendering process and contract signing. (Para 4 , 5 , 6 , 7 , 8 , 9)
3. commencement of construction and disruption. (Para 10 , 11 , 12 , 13 , 14 , 15 , 16)
4. claimant's demand for payments and resolution. (Para 18 , 19 , 20 , 21 , 22 , 28)
5. arbitration and award process. (Para 30 , 32 , 35)
6. timing and conditions for applications under arbitration act. (Para 38 , 39 , 40 , 46 , 47)
7. final conclusion and dismissal. (Para 54 , 55 , 56)

ORAL JUDGMENT

Date : 11-12-2025

Heard the parties.

2. The present application has been preferred against the judgment dated 07/04/2025 passed by the learned Principal District and Sessions Judge, Patna in Arbitration Case No 18/2024. [The Union of India Through Assistant General Manager, Engineer (Civil), Airports Authority of India, Gaya Airport, Gaya- 923004 Bihar vs. Brajesh Kumar Sinha] as also Award dated 31.05.2023 passed by the sole Arbitrator by which the case of the sole claimant-respondent was allowed and the appellants were directed to pay the Award amount within 90 days.

3. The matrix of facts giving rise to the present appeal is/are as follows:

4. Tenders were invited through the e-tendering portal by the Assistant G.M. (E-C), AAI, Gaya Airport (Bid Manager) on behalf of Chairman, Airports Authority of India (henceforth for short ‘the AAI’), on 07.11.2016 from the eligible contractors for the Construction of the Property Boundary Wall of ‘the AAI’ land situated at Gaya Airport, Gaya at an estimated cost of Rs.2,12,07,560.00 with the completion period of six months. The scope of work included RCC footing, RCC column, RCC Plinth beam, brick work etc. The last date and time of sale of tender document was 07.11.2016 while the last date for submission of e-bid was 17.12.2016.

5. The claimant-respondent thereafter submitted his application form along with other candidates within the stipulated period and time i.e. 02.12.2016 and after completion of paraphernalia, the claimant respondent was selected for the above captioned work.

6. This followed the issuance of the Letter of Appointment on 04.01.2017 for the work mentioned above at the item rates quoted by him totaling to Rs.1,25,77,245/- (Rs. One Crore Twenty Five Lakhs Seventy Seven thousand Two hundred & Forty Five only) which was 40.69% below the estimated cost of tender of Rs. 2,12,07,560/- (Rupees Two Crores Twelve Lacs Seven Thousand Five Hundred & Sixty only). The claimant respondent was acknowledged about conversion of Earnest Money Amount of Rs. 4,24,152/- (Rupees Four Lakhs Twenty Four Thousand One Hundred Fifty Two only) into SECURITY DEPOSIT, as per condition number 15 of the contract document.

7. The further direction to the claimant respondent was to deposit the remaining amount of Security Deposit i.e. Rs. 8,33,573/- (Rupees Eight Lakhs Thirty Three Thousand Five Hundred & Seventy Three only) within ten days from the date of issue of the letter, failing which, the same will be deducted as per condition 13(iii) of the tender/contract document.

8. The claimant respondent was further asked to be present before the Assistant General Manager (E-C), of ‘the AAO’ Gaya Airport, Gaya, the in-charge of the contract, to sign and complete the contract agreement on 15.01.2017.

9. Thereafter, the Contract Agreement No- AAI/GAYA/AGM/Engg(c) 03/2016-17 dated 19.01.2017 signed and executed between ‘the AAI’ and Brajesh Kumar Sinha, the claimant-respondent.

10. The contention is that there was no dispute on the proposed property regarding title and possession of said property of the Gaya Airport and the State Agencies demarcated the said property/premises which was proposed to be boundary walled.

11. The claimant respondent accordingly started construction work without any hindrance and being satisfied with the performance of the claimant-respondent, the appellants cleared the 1st Running Account Bill(R/A Bill) without any dispute for the work done up to 31.03.2017.

12. On 03.04

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top