SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Pat) 4126

PATNA HIGH COURT
Purnendu Singh, J
Kakolat Road Muawza Samiti – Appellant
Versus
The State of Bihar – Respondent
Civil Writ Jurisdiction Case No.1701 of 2026



Advocates:
For the Appellants/Petitioners: Mr.Rashid Izhar, Mr. Syed Md. Ibrahim Quli
For the Respondents: Mr. Ravi Kumar, Mr. Akshay Lal Prasad

Court emphasized the necessity for proper assessment under the Land Acquisition Act based on current market value.

Headnote:The petitioners sought reliefs to quash an award notice prepared without mandatory reports as per section 37(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. They claimed the award calculation was erroneous and sought a proper reassessment of compensation based on current market value. The court directed the authority to recalculate the award, recognizing the petitioners’ claims. The writ petition was disposed of.

Table of Content
1. relief sought for quashing an award notice based on procedural non-compliance. (Para 2 , 3)
2. reassessment of compensation based on current market value mandated. (Para 4)

CORAM: HONOURABLE MR. JUSTICE PURNENDU SINGH ORAL ORDER

2 03-02-2026 Heard learned counsel appearing on behalf of the petitioners and learned counsel for the State.

2. The petitioners in paragraph no. 1 of the present writ petition have sought, inter alia, following relief(s), which is reproduced hereinafter:-

“(I) Issuance of Writ or Writs in the nature of certiorari quashing the Award Notice dated 17-18.07.2025, which is prepared without submission or availability of the mandatory Report for determination of nature and category of land under section 37(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and in conflict with the direction issued in this context by the Government of Bihar which is prepared in haste even when the District Land Valuation Committee was constituted on 19.05.2025 (II) Issuance of Writ or Writs in the nature of mandamus commanding the Respondents to act upon the Order of Government of Bihar dated 22.04.2025 and only after assessment of the nature and category of the land in terms of action, vide Order dated 19.05.2025, as directed by the Respondent District Magistrate -cum-Collector to take further course to prepare the respective Awards in favour of the Title Holders of the land under acquisition and the wrongful and contrary action of the Respondent is causing wide spread grievance among the citizens resulting into huge future pendency of litigation in Courts and before administration.

(III) For issuance of Writ or Writs in the nature of mandamus commanding the Respondent Collector cum- District Magistrate to reassess and prepare a new Award in favour of the Petitioners towards the proposed acquisition of land for SH 103 Manjve Govindpur Path Project and direct for strict compliance of section 26 and 28 of the Act by the District Land Acquisition Authorities.

(IV) Grant any other relief or reliefs to which the Petitioners may be found entitled to in the facts and circumstances of this case.”

3. The petitioners are aggrieved by the action of the District Magistrate cum Collector who allegedly without following the procedure as prescribed under Section 26 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation And Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”) with regard to determination of nature and category of land and in spite of the representation filed by the similarly situated persons and the petitioners on 31.05.2025, has erroneously calculated the Award without giving opportunity to the petitioners and has also issued Award notice under Section 37 (2) of the Act, 2013 along with a detailed Award in favour of the petitioner nos. 2 to 5 on 17.07.2025. Petitioners are aggrieved by the illegal fixation of the Award on the basis of the nature of the land as mentioned in Khatiyan and the sale deed of the petitioners and similarly situated persons. Learned counsel submitted that in course of time, the nature of land has changed. The petitioner has purchased the said land for amount of Rs. 20 lacs by depositing required stamp duty to the government. The petitioners have claimed that they are entitled for higher compensation at the existing MVR in the area. Petitioners have been able to bring on record the value of the land by way of registered sale deed and on the basis of the MVR determined by the State Government, they have made payment of required stamp duty.

4. In view of the recorded evidence and the established MVR of the area, in which vicinity, petitioners’ land has been acquired, I find it proper that the concerned authority must give due regard to the same and recalculate the amount of Award at the current rate of MVR so that the petitioners should not be made to suffer financially in any manne

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top