SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Pat) 4811

IN THE HIGH COURT OF JUDICATURE AT PATNA
Sudhir Singh, Rajesh Kumar Verma, JJ
M/s Star Construction
Civil Writ Jurisdiction Case No.15018 of 2025



Advocates:
For the Appellants/Petitioners: Ranjeet Kumar, Rajnish Prakash, Lakshmi Kumari
For the Respondents:Addl. Advocate General (04)

An authority can legally cancel a tender process prior to the award of the contract if the Notice Inviting Tender (NIT) contains a clause reserving such a right, and the bidder is bound by the terms they voluntarily accepted upon participation.

Headnote:The petitioner challenged the cancellation of a tender for item Serial No. 17 of N.I.T. No. MR-3051-07/2024-25, where they were declared the L1 bidder. The departmental tender committee cancelled the bid on 05.07.2025 on the grounds that the petitioner lacked sufficient bid capacity due to existing commitments in other works divisions. The petitioner contended that they had sufficient capacity and that the cancellation violated the principles of natural justice as no show cause notice was issued. The primary issue was whether the respondent authorities could unilaterally cancel the tender process after the financial bid was opened. The court observed that Clause 29 of the N.I.T. explicitly reserves the right of the Engineer in Chief to accept or reject any bid or cancel the bidding process at any time prior to the award of the contract without assigning any reason. The court held that the provisions of the N.I.T. are binding on both parties, and the petitioner had voluntarily participated with full knowledge of these terms. Accordingly, the present application stands disposed of.

Table of Content
1. dispute regarding the cancellation of a tender based on the bidder's lack of bid capacity despite being the l1 bidder. (Para 1 , 2 , 3 , 4)
2. the validity of tender cancellation based on explicit reservation clauses in the notice inviting tender (nit). (Para 5 , 6 , 7)
3. absence of prejudice in floating a fresh tender and the resulting dismissal of the writ application. (Para 8 , 9 , 10 , 11)

ORAL ORDER

(Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)

4 04-02-2026 Following is the relief sought for in the present writ application:-

“I. For setting aside the minutes of the departmental tender committee Dated 05.07.2025 headed by the Additional Chief Secretary, Rural Works Department, whereby the financial bid already opened on 03.06.2025 and decided in favour of the petitioner with respect to item Serial No.- 17 of N.I.T. No. MR-3051-07/2024-25 Dated 05.11.2024 has been resolved to be cancelled unilaterall on the ground that the petitioner did not have bid capacity on the date of opening of financial bid and finally it has been cancelled.

II. For setting aside the fresh N.I.T. issued vide N.I.T. Re-tender No. MR-3054-02/2025- 26 Dated 11.07.2025 to the extent of item Serial No. 1, which has been issued for the same work in which the petitioner had already been declared as L1.

III. For issuance of direction to the respondents authorities to execute agreement with the petitioner on the basis of financial bid Dated 03.06.2025 relating to Item Serial No. 17 of N.I.T. No. MR-3054-07/2024-25 Dated 05.11.2024.

IV. For that any other relief/reliefs for which the petitioner may be deemed entitled to.”

2. The brief facts of the present case are that the petitioner had participated in the NIT No. – MR-3054-07/2024- 25 published by the respondent department dated 05.11.2024. The petitioner was declared technically qualified in the same vide decision of the technical evaluation committee dated 02.06.2025. Thereafter, the financial bids were opened on 03.06.2025, wherein the petitioner was declared to be L1. However, the tender evaluation committee after opening of the financial bids reconsidered the matter on 05.07.2025 and it was found that petitioner did not have sufficient bid capacity. The respondent department in view of this finding, cancelled the tender in question and issued directions for a fresh tender.

3. The learned counsel for the petitioner submits that the petitioner had sufficient bid capacity for the work in question on the date of submitting his bid. The learned counsel for the petitioner also submits that the impugned order was issued without giving any show cause notice to the petitioner, and as such the principles of natural justice has been violated. The learned counsel further submits that the impugned order is highly arbitrary, illegal, malicious and a result of colorable exercise of power.

4. A counter affidavit has been filed on behalf of Respondent nos. – 2 to 6. From the perusal of the said counter affidavit, it is apparent that the bid capacity of the petitioner is less than the quoted rate. The relevant paragraphs of the counter affidavit is reproduced as under:-

“11. That pursuant to aforesaid recommendation the Financial Bid of the tender in question was opened on 03.07.2025 and the Bidder M/S Star Construction was declared Lowest Quoted Bidder (L1) for the tender in question.

12. That thereafter the Bid Capacity of the petitioner was calculated during which it came to the notice regarding existing commitments petitioner in of various works divisions prior to award of Tender ID. 137506 which are as follows:-

i. Work Allotment of Total Value Rs.168.61302 Lakhs in Works Division Pakridayal (MR-N/24-25 Pakaridayal/01 Tender Id-137499) vide Chief Engineer 5 letter no 562 dated 21.02.2025.

ii. Letter of Acceptance (LOA) for the execution of Package No. RRSMP/24-25 Pakridayal/-04 under 4515 MMGSUY (RRSMP for Contract Price of Rs. 160.28463 Lakhs vide Executive Engineer, Works

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top