SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Pat) 14212

IN THE HIGH COURT OF JUDICATURE AT PATNA
Sudhir Singh, Ranjan Kumar Jha, JJ
Vijay Raj Mewar Construction Co. (P) Ltd. – Appellant
Versus
State of Bihar – Respondent
Civil Writ Jurisdiction Case No.19748 of 2025



Advocates:
For the Appellants/Petitioners: Prabhat Ranjan
For the Respondents: Rakesh Kumar Ranjan

An order of debarment, involving serious civil consequences, must be passed in accordance with the principles of natural justice. A show cause notice issued prior to the execution of a formal agreement cannot be considered a valid notice for a subsequent debarment order.

Headnote:The petitioner challenged an ex parte debarment order issued by the respondent authorities on the grounds of insufficient progress in a construction project. The petitioner contended that the order was passed without a show cause notice, violating the principles of natural justice, and noted that site encroachments had delayed the commencement of work. The primary issue was whether a valid show cause notice was issued to the petitioner prior to the debarment order dated 27.06.2025. The court observed that while a notice was issued on 20.05.2025, the authorities subsequently entered into a formal agreement with the petitioner on 26.05.2025, rendering the previous notice invalid for the subsequent action. The court reasoned that debarment carries serious civil consequences and must strictly adhere to the rule of audi alteram partem. With the aforesaid observations and direction, the present writ application stands allowed.

Table of Content
1. challenge against ex parte debarment order due to alleged lack of progress in construction work. (Para 2 , 3)
2. contention regarding violation of natural justice versus claim of prior notice issuance. (Para 4 , 5)
3. debarment as a serious civil consequence requiring strict adherence to audi alteram partem. (Para 6 , 7 , 8 , 9)
4. invalidity of a show cause notice issued before the execution of a subsequent agreement. (Para 10 , 11 , 12)
5. setting aside of the debarment order for violation of natural justice. (Para 13 , 14 , 15)

ORAL JUDGMENT

(Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)

Heard learned counsel for the petitioner and learned counsel for the respondents.

2. The following reliefs have been sought by the petitioner in the present writ application.

“1 (i) Quashing of the ex parte order as contained in Letter No. 769 dated 27.06.2025 (Annexure P/7) by which, the Respondent No. 4, without issuing any Show Cause Notice and absolutely without jurisdiction has debarred the petitioner from participating in any further tender till the time desired progress in the work/project is not achieved;

(ii) Restraining the Respondent from taking any coercive and giving effect to the order of debarment as contained in Letter No. 769 dated 27.06.2025 (Annexure P/7) during the pendency of the present writ application and/or the without the leave of this Hon’ble Court.”

3. The brief facts of the case are that the petitioner participated in a tender floated by the respondent authorities, and was declared successful. Pursuant thereto, a Letter of Acceptance was issued in favour of the petitioner dated 05.02.2025, and a provisional work order was issued dated 19.02.2025. The work/construction was to be started from 19.02.2025 itself, and was to be completed by 18.02.2026. Thereafter, an agreement was also executed between the parties dated 26.05.2025. Subsequently, on 27.06.2025 the authorities issued a debarment order against the petitioner on the ground that desired progress in the work has not been achieved. It was further alleged by the authorities that the petitioner has not shown any interest in completion of the said work and therefore, the order of debarment is being passed which will be effective till the desired progress in work is not achieved. By way of filing the present writ application, the petitioner has challenged the debarment order dated 27.06.2025.

4. Learned counsel for the petitioner submits that no show cause notice was issued to the petitioner before the impugned action of debarment was taken against him. It is submitted that the action of debarment being in nature of serious civil consequence requires an issuance of show cause notice, and therefore, the impugned order passed by authorities is in grave violation of principles of natural justice. It is further submitted that even after the issuance of work order, there was an encroachment existing on the site of construction. It is submitted that after the concerned circle officer submitted the measurement/demarcation of the construction site dated 05.05.2025, the petitioner and respondent authorities entered into an agreement dated 26.05.2025 whereafter, the petitioner commenced the work.

5. Learned counsel for the respondent-state submits that a work order was issued to the petitioner on 19.02.2025, and the petitioner was supposed to start the work from 19.02.2025 itself. It is further submitted that the site for the work was also made available to the petitioner on 18.02.2025. It is submitted that despite several reminders given to the petitioner to start and complete the said work, the petitioner failed to do so, and the desired progress in the work was not achieved. It is further submitted that the petitioner had already been issued a show cause notice dated 20.05.2025 (Annexure – R/C to the counter-affidavit), contemplating the action of the debarment against the petitioner. It is thus submitted that the impugned order

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top