NIDHI GUPTA, J.
Present Civil Revision Petition has been filed by the plaintiff under Article 227 of Constitution of India seeking setting aside of the Impugned Order dated 08.11.2024 (Annexure P-10) passed by learned Additional District Judge, Gurugram whereby the order dated 01.04.2019 (Annexure P8), passed by learned Civil Judge (Junior Division), Gurugram dismissing the petitioner’s application seeking ad-
interim injunction in Civil Suit bearing No. 991/2019, has been upheld.
2. Brief facts of the case in chronological order are as follows: -
01.03.2019: The petitioner was served with Show Cause Notice dated 01.03.2019 (Annexure P1) by the respondent as to why illegal construction raised by the petitioner should not be demolished.
DIVYANSHI
07.03.2019: In response to above said Show Cause Notice, petitioner had filed reply dated 07.03.2019 (Annexure P2) stating that he is only repairing old structure; and that it was not new construction.
22.03.2019: The respondent passed a Demolition Order dated 22.03.2019 (Annexure P3) under Section 26
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.