IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CORPORATION – Appellant
Versus
GAWAR CONSTRUCTION PVT. LTD. – Respondent
IN THE HIGH COURT OF PUNJAB & HARYANA AT CHANDIGARH ***
CR-1578-2026 (O&M)
Date of Decision: 18.02.2026 Haryana State Industrial & Infrastructure Development Corporation Limited and another .... Petitioner Versus Gawar Construction Private Limited ..... Respondent CORAM: HON'BLE MR. JUSTICE JASGURPREET SINGH PURI Present: Mr. Vishal Garg, Advocate, for the petitioner.
****
JASGURPREET SINGH PURI , J . (ORAL)
1. The present petition has been filed under Article 227 of the Constitution of India for setting aside the order dated 17.01.2026 (Annexure P- 1) whereby learned Executing Court is proceeding to execute the decree in favour of the respondent-decree holder.
2. Learned counsel for the petitioner submitted that the petitioners are the judgment debtors and had filed objections under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’) before learned Additional District Judge, Panchkula. The said objections were dismissed for non-prosecution. Thereafter, the petitioners filed an application for restoration of the aforesaid objections, in which notice has been issued. He further submitted that since the notice in the restoration application is pe
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.