SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(P&H) 6051

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Alka Sarin, J
SAHAB SINGH – Appellant
Versus
DILBAG SINGH AND OTHERS – Respondent
CR-94-2024 (O&M)



Advocates:
For the Appellants/Petitioners: Amit Kashyap
For the Respondents:

A claim for an injunction regarding an electricity connection must be supported by credible documentary evidence of ownership and must be consistent with the physical location reported by a Local Commissioner.

Headnote:The petitioner filed a revision petition under Art. 227 of the Constitution of India challenging the dismissal of an application under O. 39 R. 1 and 2 of the Code of Civil Procedure. The petitioner sought a permanent injunction to restrain respondents from interfering with an electricity connection, claiming the connection was purchased via an affidavit dated 22.11.2013. The court found that the petitioner failed to provide documentary evidence regarding the shifting of the connection and the Local Commissioner's report contradicted the petitioner's claims regarding the location of the connection. The primary issue was whether the petitioner established a prima facie case for the grant of an injunction. The court reasoned that the Local Commissioner's report indicated the connection existed in a different location than claimed, and the fact that electricity bills remained in another person's name meant that mere production of bills did not prove payment or ownership by the petitioner. In view of the above, I do not find any merit in the present revision petition and the same is accordingly dismissed.

Table of Content
1. challenge to lower court orders dismissing an application for temporary injunction. (Para 1 , 2)
2. claim of ownership of utility connection based on an affidavit of sale. (Para 3)
3. requirement of physical verification and documentary proof to establish prima facie right to injunction. (Para 4 , 5)
4. dismissal of revision petition due to lack of merit. (Para 6)

ALKA SARIN, J. (ORAL)

1. The present revision petition has been filed under Article 227 of the Constitution of India challenging the order dated 17.03.2020 passed by the learned Trial Court and the order dated 12.09.2023 passed by the learned First Appellate Court dismissing the application filed by the plaintiff-petitioner under Order 39 Rules 1 and 2 CPC.

2. Brief facts relevant to the present lis are that the plaintiff-petitioner herein filed a suit for permanent injunction for restraining the defendant-respondents No.1 and 2 from interfering in the peaceful use of electricity connection bearing No.SL-61-1066 (earlier installed in Killa No.12 and now in Killa No.13) as fully described in the plaint. Along with the suit, an application was also filed by the plaintiff-petitioner under Order 39 Rules 1 and 2 CPC. Reply was filed to the said application. The Trial Court vide order dated 17.03.2020 dismissed the application under Order 39 Rules 1 and 2 CPC. Aggrieved by the same, an appeal was preferred by the plaintiff-petitioner which appeal was also dismissed by the learned First Appellate Court vide order dated 12.09.2023. Hence, the present revision petition.

3. Learned counsel for the plaintiff-petitioner would contend that it is an admitted case that the land was exchanged by the plaintiff-petitioner and the defendant-respondents No.1 and 2 and that the tubewell fell to the share of the plaintiff-petitioner. Learned counsel would further contend that an affidavit dated 22.11.2013 qua the sale of the tubewell connection was executed for a sale consideration of ₹60,000 by defendant-respondent No.1 wherein it was clearly stated that the connection was purchased by the plaintiff-petitioner from defendant-respondent No.1.

4. Heard.

5. In the present case the case set up by the plaintiff-petitioner is that he purchased the tubewell connection through an affidavit dated 22.11.2013. The said fact was denied by defendant-respondents No.1 and 2. A Local Commissioner had been appointed who had reported that the tubewell connection in question was existing in Killa No.18/2 of Square No.193 and is still in existence in the said Killa. Though the plaintiff-petitioner had taken a stand that the connection was shifted from Killa No.12 to 13 after completing all the formalities, however, no document was placed on the record qua the same. The report of the Local Commissioner dated 25.11.2019 also stated that there was no connection in Killa No.12 or 13. Both the Courts concerned observed that the bills were still being issued in the name of Vakil Singh and mere production of the same by the plaintiff-petitioner would not mean that the payment was being made by him.

6. In view of the above, I do not find any merit in the present revision petition and the same is accordingly dismissed. Pending applications, if any, also stand disposed off.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top