108 IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH DATE OF DECISION : 02.09.2025 NARESH KUMAR ... APPELLANT V/S HARPREET SINGH (SINCE DECEASED) THROUGH LR AND OTHERS ... RESPONDENTS CORAM: HON'BLE MR. JUSTICE PARMOD GOYAL Present: Mr. Mohit Jaggi, Advocate for the appellant.
* * *
PARMOD GOYAL , J. (ORAL)
Plaintiff-appellant is aggrieved by the impugned judgement dated 01.11.2019 passed by learned District Judge, Mohali whereby appeal preferred by defendants was allowed and suit of plaintiff was dismissed.
Parties were left to bear their own costs.
2. Admittedly, plaintiff-appellant had filed a suit for mandatory injunction seeking directions to defendants to remove unauthorised wall constructed over the wall ABC of the house of plaintiff and also to remove the iron garders and tin shed from said wall. Plaintiff had also sought permanent injunction seeking to restrain defendants from making any kind of extension/construction over the wall. The case of the plaintiff was that he had purchased house marked with letter ‘ABCDE’ measuring 2.5 Biswas from Gulshan Kumar who had constructed the house by purchasing vacant plot from defendant no.3 vide sale deed dated 05.03.2009 and since the date of purchase, plaintiff is owner in possession of suit property. It was asserted that at the time of purchase of house, there was no construction over the area adjoining/abutting the house. The plaintiff became exclusive owner of house purchased by him from Gulshan Kumar. However, taking benefit of his absence, defendants have raised construction over the existing wall and had put iron garders and tin shed thereupon and accordingly, plaintiff is seeking removal of the same. Upon notice, defendants appeared and filed detailed written statement, took number of preliminary objections regarding maintainability etc. It was asserted that it was defendant No.3 who was owner of the house in dispute and constructed the same in the year 1983. Defendant No.3 had sold the said house to Gulshan Kumar who further sold the same to plaintiff. Wall in dispute was stated to be jointly constructed by defendant No.3 and the father of defendant Nos.1 and 2 and that since its construction wall is joint and is being jointly used by both the parties since 1983. It was specifically asserted that neither plaintiff nor Gulshan Kumar has raised construction of the wall. The wall was stated to be joint and expenses for same were stated to be jointly borne by defendants. It was asserted that with the passage of time, defendants have raised the height of joint wall and it was never objected by the plaintiff. Plaintiff himself had suggested that a beam be placed on the wall. However, since defendants were not putting anything except tin sheds, they decided not to do that.
Dismissal of suit was prayed for.
3. Following issues were framed from the pleadings of the parties:-
“i) Whether plaintiff is entitled for the relief of Mandatory Injunction directing the defendant Nos. 1 and 2 to remove the unauthorized wall constructed by them and also to remove iron garder and tin-shed installed by them in suit property? OPP ii) Whether plaintiff is entitled for the relief of Permanent Injunction restraining the defendants from raising any kind of extension by way of construction in the suit property? OPP iii) Whether plaintiff has not approached the court with clean hands and has suppressed the material facts from the Court?
OPD iv) Whether suit is not maintainable in present form? OPD v) Relief.”
4. Learned Court of Civil Judge (Junior Division), Kharar vide judgement dated 29.11.2018 concluded that plaintiff has succeeded in proving his case and accordingly, defendants were directed to remove unauthorised wall constructed by them and also remove the iron garders as well as tin shed intstalled by defendants. However, on appeal, learned District Judge, Mohali vide impugned judgement and decree dated 01.11.2019 concluded that as no demarcation report was ever placed by plaintiff to prove t