Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(P&H) 21182

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
EMAAR INDIA LIMITED – Appellant
Versus
KUSUM BALI AND ANOTHER – Respondent



IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH Date of decision : 17.11.2025 Emaar India Limited ...... Appellant versus Kusum Bali and another ...... Respondents CORAM : HON'BLE MR. JUSTICE PANKAJ JAIN Present: Mr. Kunal Dawar, Senior Advocate with Ms. Shruti Mandhotra, Advocate Mr. Saurav Bajaj, Advocate Mr. Samarth Dwide, Advocate and Mr. Manish, Advocate for the appellant.

****

PANKAJ JAIN, J. (Oral)

1. Appellant is a developer aggrieved of the orders passed by the authorities under the Real Estate (Regulation and Development)

Act, 2016 (hereinafter referred to as ‘RERA Act’, 2016).

2. The appeal arises out of a complaint filed by allottee under Section 31 of 2016 Act read with Rule 28 of Haryana Real Estate (Regulation and Development) Rules, 2017 alleging violation of Section 11(4)(a) of 2016 Act. As per the complainant, the appellant- promoter agreed to handover possession of the building to the allotttes within 30 months of the execution of the agreement, i.e. 24.12.2010 with the further grace period of 120 days. Due date of possession was 24.06.2013. Occupation certificate was issued on 08.01.2018 and possession was offered on 09.03.2018.

3. The complaint was contested by promoter claiming that the conveyance deed already stands executed on 05.10.2018. The present complaint has been filed in March 2021 and the same having been filed after the execution of conveyance deed, is not maintainable.

4. There not being much dispute regarding the timelines, the authority vide order dated 13.12.2022 disposed off the complaint in the following terms:-

“34. Hence, the authority hereby passes this order and issues the following directions under section 37 of the Act to ensure compliance of obligations cast upon the promoter as per the function entrusted to the authority under section 34(f): i. The respondent is directed to pay the interest at the prescribed rate i.e. 10.35% per annum for every month of delay on the amount paid by the complainants from 24.06.2013 till 09.05.2018 i.e. expiry of 2 months from the date of offer of possession (09.03.2018). The arrears of interest accrued so far shall be paid to the complainants within 90 days from the date of this order as per rule 16(2) of the rules.

ii. The amount of compensation already paid to the complainants by the respondent as delay compensation in terms of the buyer’s agreement shall be adjusted towards delay possession charges payable by the promoter at the prescribed rate of interest to be paid by the respondent as per the proviso to section

18(1) of the Act.

iii. The respondent shall not levy/recover any charge from the complainants which is not the part of the buyer's agreement. The respondent is also not entitled to claim holding charges from the complainants/allottees at any point of time even after being part of the buyer's agreement as per law settled by hon'ble Supreme Court in civil appeal nos. 3864-

3889/2020 decided on 14.12.2020.”

5. Dissatisfied with the order passed by the authority, the promoter approached the Appellate Tribunal by way of Appeal No.397 of 2023. Vide impugned order, the Tribunal partly allowed the appeal preferred by the promoter granting four months grace period, i.e. 120 days in terms of the agreement.

6. Learned senior counsel appearing for the appellant- promoter has assailed the orders passed by the Tribunal primarily disputing the maintainability of the application. Mr. Dawar submits that the complaint having been filed after execution of conveyance deed and the rights of the parties having been finalized by the covenants contained in the conveyance deed, the complainant had no locus to prefer the complaint in terms of agreement of allotment. Complainant is estopped from raising any grievance in terms of concluded contract between the parties. Reliance is being placed upon Section 55 of the Indian Contract Act. He draws attention of this Court to the observation made by Tribunal in para 6 holding that there is no limitation prescribed in the Act.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top