IN THE HIGH COURT OF PUNJAB & HARYANA AT CHANDIGARH ***

CR-8476-2025 Date of Decision: 20.11.2025 Arvindera Electricals .... Petitioner Versus Greater Mohali Area Development Authority and others ..... Respondents CORAM: HON'BLE MR. JUSTICE JASGURPREET SINGH PURI Present: Mr. Sourabh Goel, Advocate, for the petitioner.

****

JASGURPREET SINGH PURI , J . (ORAL)

1. The present is a Civil Revision Petition filed under Article 227 of the Constitution of India seeking quashing of the order dated 14.11.2025 (Annexure P-20) passed by learned Sole Arbitrator vide which application of the respondent for filing counter-claim has been allowed.

2. Mr. Sourabh Goel, learned counsel for the petitioner while giving the facts of the case submitted that there was an Agreement between the petitioner and the respondent-Greater Mohali Area Development Authority (hereinafter referred to as ‘GMADA’) wherein there was an arbitration clause and in pursuance thereof a petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Arbitration Act’) was filed by the petitioner before this Court and a Co- ordinate Bench of this Court vide order dated 02.12.2024 (Annexure P-1) had allowed the aforesaid petition and a Sole Arbitrator was appointed. In pursuance thereof the arbitral proceedings commenced before learned Sole Arbitrator. The first date fixed before learned Sole Arbitrator was

##PAGE2##

30.12.2024. Thereafter, on 24.07.2025, the statement of defence was also filed and on 12.09.2025 the petitioner filed rejoinder and issues were also framed. Thereafter, on 30.09.2025, an affidavit was filed by the petitioner/claimant since the case was fixed for evidence. On 27.10.2025, an application was filed by the respondents by stating that the counter-claim is pending before the Chief Administrator, GMADA and the aforesaid application for filing counter-claim by the respondents was allowed on 14.11.2025 by learned Sole Arbitrator. This order dated 14.11.2025 (Annexure P-20) vide which learned Sole Arbitrator has allowed the application for filing of the counter-claim by the respondents is under challenge in the present Civil Revision under Article 227 of the Constitution of India.

3. Learned counsel further submitted that the arbitral proceedings started on 30.12.2024 and as per the provisions of Section 23(4) of the Arbitration Act, the statement of claim and defence is to be filed within a period of six months from the date the Sole Arbitrator or the Arbitral Tribunal, as the case may be, receives notice, in writing of their appointment. He submitted that the aforesaid dates would show that after about almost 11 months from the date when the arbitral proceedings first commenced, 6 months have lapsed and therefore, learned Sole Arbitrator could not have allowed the filing of the counter-claim by the respondents by way of the impugned order (Annexure P-20) since it was in violation of the provisions of Section 23(4) of the Arbitration Act. He also submitted that allowing the aforesaid application of the respondents for filing the counter- claim by learned Sole Arbitrator, has caused prejudice to the petitioner since it was allowed to be filed beyond the limitation period of 6 months as stipulated under Section 23(4) of the Arbitration Act.

##PAGE3##

4. While referring to the impugned order (Annexure P-20), he submitted that it was so observed by learned Sole Arbitrator that since the counter-claim is not a part of the original pleadings, the respondents are permitted to file their counter-claim and further submitted that the aforesaid finding of learned Sole Arbitrator is perverse because counter-claim is also a part of the original pleadings and also referred to Section 2(9) of the Arbitration Act in this regard. He also submitted that it was so observed by learned Sole Arbitrator that the respondent herein is a Corporate body and things do not move as fast as is expected and that also became a ground for all