2025 Supreme(Online)(P&H) 40145
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Reserved on:-05.09.2025
Date of Decision : 09.09.2025
1. RSA-2734-2024 (O&M)
RSA-2224-2025 (O&M)
M/s Modular Infratech Pvt. Ltd. ....Appellant VERSUS M/s Bitureks Fire Solutions and Another ....Respondents
Capital Vehicles Sales Ltd. ....Appellant VERSUS M/s Bitureks Fire Solutions and Another ....Respondents
CORAM : HON’BLE MS. JUSTICE MANDEEP PANNU
Present: Mr. Sudhir Aggarwal, Advocate and Mr. Ishan Aggarwal, Advocate for the appellant.
Mr. Vipin Pal Yadav, Advocate with Mr. J.S.Sohal, Advocate for respondent No.1.
Mr. Sarthak Gupta and Ms. Sanya Shangari, Advocates for respondent No.2.
-.-
September 09, 2025
(MANDEEP PANNU)
JUDGE
tripti
Whether speaking/non-speaking : Speaking Whether reportable : Yes/No.
T2Iin R0at 2 e I t P tg 5e T r .s0 i I tt 9 y S t. A o1 o I f 2t N h t 0I he9 i sa: 5cdc9 oucruamcye natnd
MANDEEP PANNU,J.
1. The above-mentioned two Regular Second Appeals i.e. RSA-2734-2024 and RSA-2224-2025 shall stand dispose of by this common judgment.
2. RSA-2734-2024 has been filed by the appellant/defendant No.1-M/s Modular Infratech Pvt. Ltd. against the respondents/plaintiff-M/s Bitureks Fire Solutions, a proprietary concern through its sole proprietor Jatinder Chauhan, and defendant No.2-M/s MGF Toyota Pvt. Ltd., and RSA-2224-2025 has been filed by the appellant/defendant No.2-Capital Vehicles Sales Ltd. (alleged to be wrongly mentioned as M/s MGF Toyota Showroom) against respondents/plaintiff-M/s Bitureks Fire Solutions, a proprietary concern through its sole proprietor Jatinder Chauhan, and defendant No.1-M/s Modular Infratech Pvt. Ltd., challenging the concurrent findings of the learned trial Court and the Lower Appellate Court whereby the suit of the plaintiff – M/s Bitureks Fire Solutions for mandatory injunction was decreed and the appeal preferred by M/s Modular Infratech Pvt. Ltd. was dismissed.
T2Iin R0at 2 e I t P tg 5e T r .s0 i I tt 9 y S t. A o1 o I f 2t N S h t 0I he9 o i sa: l 5cd u c9 ouc t ru i am o cye n na s tnd
Brief Facts
3. The case of the plaintiff, as set out in the plaint, is that defendant No.1, after mutual discussions, allotted job work to the plaintiff for installation of fire suppression systems and plumbing and sanitary works at the premises of defendant No.2 vide work order dated 26.05.2012. The value of the work was fixed at ₹37,35,404/- for fire suppression systems and ₹36,88,225/- for plumbing and sanitary works.
4. It was alleged that while the work was in progress, the defendants required certain changes, including installation of Jaguar make fixtures in place of Hindware and provision of additional flexible sprinkler drops which were not part of the original BOQ. After reminders, the revised rates for the changed items were approved through emails dated 10.12.2012 and 14.12.2012.
5. The plaintiff completed the work and raised a final bill dated 19.03.2013 for ₹82,05,964.28, comprising ₹51,99,988/- towards fire-fighting system and ₹30,05,975/- towards plumbing and sanitary works. Out of this, the
T2Iin R0at 2 e I t P tg 5e T r .s0 i I tt 9 y S t. A o1 o I f 2t N d h t 0I he e 9 i sa: f 5cd e c9 ou n crua d mcy a e na n tn t d s
paid a total of ₹58,34,000/-, leaving a balance of ₹27,71,964/- outstanding.
outstanding. The plaintiff further claimed ₹5,00,000/- as compensation for financial loss caused due to non-release of payment.
6. It was pleaded that despite repeated demands, including legal notice dated 19.07.2013, the defendants failed to pay. Instead, defendant No.1 issued a baseless penalty notice dated 28.03.2013 and thereafter proposed a “Memorandum of Final Bill Settlement” dated 16.04.2013, which was wholly unfair and unreasonable and was rejected. The delay in execution of the job, according to the plaintiff, was entirely attributable to the defendants, who had failed to hand over the premises in time, altered specifications midway, and took time in finalising new rates. The plaintiff, therefore, prayed for a decree of mandatory injunction directing the defendants to pay ₹28,71,964/- (balance plus compensation) with interest at 24% per annum from the date of submission of the final bill till realization.
7. Defendant no.1 filed written statement raising preliminary objections that the suit was not maintainable in the form of mandatory injunction and that the proper remedy was a suit for recovery. It was also contended that the plaint was liable to be rejected under Order 7 Rule 11 CPC for non-payment of proper court fee.
8. It was further pleaded that the plaintiff was negligent in execution, failed to complete the job within the stipulated 90 days, and caused heavy losses of about ₹98 lakhs to defendant no.1, including penalties imposed by defendant no.2. The plaintiff was alleged to have inadequate resources and manpower, failed to supply materials in time, and repeatedly