2025 Supreme(Online)(P&H) 42424
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
LABH SINGH TRANSPORT COMPANY – Appellant
Versus
HINDUSTAN PETROLEUM CORPORATION LTD AND ANR – Respondent
FAO_1322_2017
##PAGE1##
215 IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH FAO-1322-2017 (O&M)
Date of Decision:20.08.2025 (I)
M/s Labh Singh Transport Company ....Appellant(s)
Versus Hindustan Petroleum Corporation Ltd. and another .....Respondent(s)
FAO-1337-2017(O&M)
(II)
M/s Jai Maa Ambey Transport ....Appellant(s)
Versus Hindustan Petroleum Corporation Ltd. and another .....Respondent(s)
CORAM: HON’BLE MR. JUSTICE JASGURPREET SINGH PURI Present: Dr. Rau P.S. Girwar, Advocate, for the appellant(s).
Mr. Raman Sharma, Advocate, for the respondents.
****
JASGURPREET SINGH PURI , J. (Oral)
1. Both the appeals are taken up together for final disposal with the consent of learned counsel for the parties.
2. Learned counsel appearing on behalf of the appellant submitted that the appellant had filed objections under Section 34 of the Arbitration and Conciliation Act, 1996 before the learned Additional District Judge, Bathinda but an application which was filed under Section 5 of the Limitation Act, 1963 was dismissed and in this way, the objections under Section 34 of the Arbitration and Conciliation Act, 1996 have also been dismissed by way of the impugned order dated 13.05.2016.While giving the relevant dates which are undisputed, he submitted that the award was passed on 22.11.2010, copy of which was received by the appellant on 06.12.2010 and thereafter, the objections under Section 34 of the Arbitration and Conciliation Act, 1996 were filed on 17.05.2011 i.e. beyond the period of 3 months plus 30 days regarding which there is no dispute. He submitted that in view of the provisions of Section 5 of the Limitation Act, 1963, the application ought to have been considered as to whether it constituted sufficient cause or not for condonation of delay and the delay could have been condoned. In this regard, he referred to the judgments of Hon'ble Supreme Court in Government of Maharashtra (Water Resources Department) Versus M/s Borse Brothers Engineers & Contractors Pvt. Ltd. 2021(6) SCC 460 and Chintels India Ltd. Versus Bhayana Builders Pvt. Ltd., 2021(4) SCC 602.
##PAGE2##3. On the other hand, the learned counsel appearing on behalf of the respondent/HPCL submitted that provisions of Section 5 of the Limitation Act, 1963 do not apply to the objections filed under Section 34 of the Arbitration and Conciliation Act, 1996 and therefore, the learned Court has rightly dismissed the application for condonation of delay and the objections under Section 34 of the Arbitration and Conciliation Act, 1996.
4. After hearing the learned counsel for the parties, this Court is of the considered view that the aforesaid issue of law is no longer res integra.
##PAGE3##Hon’ble Supreme Court in Mahindra and Mahindra Financial Services Limited versus Maheshbhai Tinabhai Ra t hod and others, (2022) 4 SCC
162 held as under:-
“9. The scope available for condonation of delay being self contained in the proviso to Section 34(3) and Section 5 of Limitation Act not being applicable has been taken note by this Court in its earlier decisions, which we may note. In Union of India vs. Popular Construction Co.
(2001) 8 SCC 470 it has been held as hereunder:
“12. As far as the language of Section 34 of the 1996 Act is concerned, the crucial words are “but not thereafter” used in the proviso to subsection (3). In our opinion, this phrase would amount to an express exclusion within the meaning of Section 29(2) of the Limitation Act, and would therefore bar the application of Section 5 of that Act. Parliament did not need to go further. To hold that the court could entertain an application to set aside the award beyond the extended period under the proviso, would render the phrase “but not thereafter” wholly otiose. No principle of interpretation would justify such a result.
xxx-xxx-xxx-xxx
14. Here the history and scheme of the 1996 Act support the conclusion that the time-limit prescribed under Section 34 to challenge an award is absolute and unextendible by court under Section 5 of the Lim