2025 Supreme(Online)(P&H) 43178

IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
PUNJAB STATE WAREHOUSING CORPORATION LTD – Appellant
Versus
M/S GURU RAM DASS RICE MILLS AND ORS – Respondent
CR_5444_2022



##PAGE1##

224 IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH CR-5444-2022 Date of decision: 18.08.2025 PUNJAB STATE WAREHOUSING CORPORATION LTD.

...Petitioner(s)

VERSUS M/S GURU RAM DASS RICE MILLS AND ORS.

...Respondent(s)

CORAM: HON'BLE MR. JUSTICE JASGURPREET SINGH PURI Present:- Mr. Parambir Singh, Advocate for the petitioner.

****

JASGURPREET SINGH PURI, J. (Oral)

1. The present petition has been filed under Article 227 of the Constitution of India for setting aside the order dated 09.08.2022 (Annexure P-4), whereby the application filed by the petitioner under Section 5 of the Limitation Act for condonation of delay in filing the petition under Section 34 of the Arbitration and Conciliation Act, 1996 against the award dated 20.02.2017 has been dismissed by the learned Additional District Judge, Ferozepur.

2. Learned counsel for the petitioner submitted that in the present case, by way of the impugned order dated 09.08.2022 (Annexure P-4) passed by the learned Additional District Judge, Ferozepur, the objections filed by the petitioner under Section 34 of the Arbitration and Conciliation Act, 1996 have been dismissed on the ground of delay. He further submitted that the Award was passed on 20.02.2017 and the objections under Section 34 of the Arbitration and Conciliation Act, 1996 were filed on 08.11.2017 and although there was a delay of about 8½ months in filing the objections but the same was due to the counsel’s failure to file the objections on time and therefore, that constituted a sufficient cause for condoning the delay even beyond the prescribed period of 3 months plus 30 days. He also submitted that since there was no fault of the petitioner-Corporation, the aforesaid impugned order is liable to be set aside.

##PAGE2##

3. I have heard the learned counsel for the petitioner.

4. It is a case where the Award was passed on 20.02.2017 and the objections under Section 34 of the Arbitration and Conciliation Act, 1996 were filed on 08.11.2017 i.e. after a period of about 8½ months. The statutory period for filing the objections as contained in Section 34(3) of the Arbitration and Conciliation Act, 1996 is three months. However, by virtue of the proviso contained in aforesaid sub-section 3, another 30 days can be granted subject to explaining to the Court whether there exists any sufficient cause or not. However, there is no such provision for further extending the period of limitation beyond the further period of 30 days. In other words, the maximum period of limitation within which the objections can be filed is only 3 months plus 30 days, whereas in the present case, the petitioner filed the objections much beyond the aforesaid period of 3 months plus 30 days i.e. after a period of about 8½ months.

5. A perusal of the aforesaid impugned order would show that the petitioner did not mention any specific date when the copy of the Award was received by it and therefore, the date on which the Award was passed was taken as the starting point of the period of limitation. A further perusal of the aforesaid impugned order would show that rather the entire law pertaining to the applicability of Section 5 of the Limitation Act has been considered by the learned Additional District Judge, Ferozepur. Therefore, it is not understandable as to how even after knowing the legal position that there can be no condonation of delay after 3 months plus 30 days and the same has been so incorporated in the impugned order also, the petitioner-Corporation which is a Public Sector Undertaking has filed the present petition. The law with regard to the aforesaid applicability of Section 5 of the Limitation Act is no longer res intergra.

##PAGE3##

6. Hon’ble Supreme Court in Mahindra and Mahindra Financial Services Limited versus Maheshbhai Tinabhai Rathod and others, (2022) 4 SCC 162 held as under:-

“9. The scope available for condonation of delay being self contained in the proviso to Section 34(3) and Section 5 of Limitation Act not being applica

1
2
3
4
5
6
7
8
9
10
11