IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH RESERVED ON: 15.05.2025 PRONOUNCED ON: 26.05.2025 M3M India Private Limited …. Petitioner Versus MGF Developments Limited & Ors.

… Respondents CORAM: HON’BLE MR. JUSTICE DEEPAK GUPTA Argued By:- Mr. Ashish Chopra, Senior Advocate with Ms. Rupa Pathania, Advocate for the petitioner.

Mr. Amandeep Singh Talwar, Advocate for Respondents No.1 and 2.

Mr. Sumeet Jain, Advocate, Mrs. Ashima Mor, Advocate and Mr. Gyan Parkash Saini, Advocate for Respondent No.3.

Mr. Amit Jhanji, Sr. Advocate with Ms. Priyanka Kansal, Advocate and Mr. Harshit Joon, Advocate for Respondent No.4.

***

DEEPAK GUPTA, J.

Petitioner herein is the plaintiff in civil suit No. 4 of 2023 titled ‘M3M India Private Limited Vs. MGF Developments Limited & Ors.’, pending before learned Additional District Judge-cum-Presiding Officer, Exclusive Commercial Court at Gurugram exercising jurisdiction under Commercial Courts Act, 2015 [in short – ‘commercial court’]. The petitioner is aggrieved by the order dated 05.03.2025 (Annexure P-1), whereby Commercial Court has dismissed the application filed by the said petitioner under Order XI Rule 1 (5) CPC for producing certain additional documents.

##PAGE2##

2.1 Defendants No.1 and 2 (respondents N: 1 & 2 herein) were owner of the suit land. Collaboration agreement dated 23.11.2016 (Annexure P-2) was executed between the plaintiff and defendants No.1 & 2 regarding the said land; and an amount of ₹88 crores was paid by the plaintiff to the said defendants, which as per plaintiff’s case was a refundable security. Irrevocable power of attorney was executed by defendant No.1 & 2 in plaintiff’s favour on the same day i.e. 23.11.2016. The plaintiff was represented by one Mr. Ravi Khera. On 24.11.2016, a supplementary agreement is purported to have been executed between the parties, whereby refundable security deposit under the collaboration agreement was made non-refundable. Plaintiff claims that Ravi Khera had tendered his resignation on 25.05.2017. It is further the allegation that cancellation agreement dated 18.12.2017 was later on executed between the plaintiff through Ravi Khera and defendants No.1 & 2, thus, cancelling the collaboration agreement.

2.2 Later on, out of total 61 kanals 18 marlas of the suit land, defendants No.1 & 2 sold 60 kanals 7 marlas to defendant No.3 (respondents N: 3 herein) on 09.09.2021, who was granted license to develop the plotted colony by Director Town and Country Planning.

2.3 Cancellation agreement dated 18.12.2017 is alleged by the plaintiff to be a forged document, having been prepared by the defendants No.1 & 2 in collusion with its erstwhile employee Mr. Ravi Khera, who had already resigned in May 2017. On a complaint moved by the plaintiff on 30.12.2021, FIR No. 3 dated 03.01.2022 under Sections 120-B, 406, 409, 420, 467, 468, 471 IPC was registered against defendants No.1 and 3, its Directors and Mr. Ravi Khera. CRM-M 4263 of

2022 was filed by defendant No.1 to quash the FIR before this High Court.

2.4 Plaintiff then filed civil suit No. 2770 of 2022 on 07.06.2022 before the Court of learned Civil Judge (Jr. Divn.), Gurugram seeking decree of declaration of his rights under the collaboration agreement. Defendants No.1 and 3 filed separate applications under Order 7 Rule 11 CPC contending that suit was not maintainable being a commercial dispute and so, same should have been brought before Commercial Court. The objection of maintainability was also raised in the written statement filed by defendants No.1 and 2 in October, 2022. Defendant No.3 pleaded itself to be a bonafide purchaser.

##PAGE3##

2.5 The plaint of aforesaid suit was returned by the learned Civil Judge on 09.01.2023 and thereafter, plaintiff brought the present suit on 21.01.2023 seeking decree of declaration regarding validity of the collaboration agreement, contending that it was still subsisting and seeking cancellation of sale deeds executed by defendants No.1 and 2 in f