SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Raj) 12669

HIGH COURT OF RAJASTHAN (JODHPUR BENCH)
Mr. Justice Arun Monga, J
M/s Shri Raghav Developers And Construction – Appellant
Versus
Amit Bishnoi – Respondent
Arbitration Application No. 7/2024



Advocates:
For the Petitioner(s): Mr. Abhinav Jain
For the Respondent(s): Mr. Narendra Thanvi, Mr. Nishank Madhan

The court ruled that disputes must be resolved via arbitration as specified in the binding arbitration clause, despite prior civil litigation attempts.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11 - Appointment of Arbitrator - Dispute arising from Development Agreement regarding construction and obligations of parties - The applicant seeks appointment of an arbitrator due to the respondent's failure to fulfill obligations, despite an arbitration clause being present in the agreement. (Paras 1, 4, 11, 14)

(B) Jurisdiction - Disputes arising and clauses for resolution - The court emphasizes the need for parties to adhere to their mutually agreed arbitration clause to resolve disputes arising from the agreement rather than resorting to civil suits. (Paras 10, 13)

(C) Application Time Bar - Arguments regarding timeliness of the application are presented, yet the court finds that the arbitration clause remains a valid path for resolution, notwithstanding prior civil claims. (Paras 7, 13)

Facts of the case:
The applicant, a partnership firm, engages in land development but faces issues due to the respondent's failure to comply with the obligations of a Development Agreement dated 19.07.2013, leading the applicant to seek arbitration.

Findings of Court:
The court finds merit in the application for arbitration due to the undisputed clause and the existing dispute between the parties.

Issues: The main issue was which forum, arbitration or civil court, should primarily address the dispute per agreed terms of the Development Agreement.

Ratio Decidendi: The court ruled that since an undisputed arbitration clause exists within the agreement, the matter should be referred to arbitration as specified by the parties, thus binding them to the chosen forum for dispute resolution.

Result: Application stands disposed of.

Table of Content
1. dispute arises from obligations under a development agreement. (Para 1 , 2 , 3 , 4 , 5)
2. arguments presented regarding appropriate forum for dispute resolution. (Para 6 , 7)
3. court emphasizes the importance of adhering to the arbitration clause. (Para 8 , 9 , 10 , 11 , 12 , 13)
4. appointment of an arbitrator to resolve the dispute. (Para 14 , 15)

Order(Oral)

02/07/2025

1. Application herein is under Section 11 of the Arbitration & Conciliation Act, 1996 with the prayer to appoint a sole arbitrator to decide/ adjudicate upon the dispute between the parties arising out of the Development Agreement dated 19.07.2013 (registered on 30.07.2013).

2. The applicant is a registered partnership firm engaged in land development and construction. The non-applicant, who owns plots admeasuring 2,107 square yards at Patel Nagar, Bikaner, entered into a Development Agreement with the applicant on 19.07.2013, registered on 30.07.2013, for the construction of a multi-storey building.

3. As per the agreement, the applicant paid Rs. 1 crore to the non-applicant as refundable security—50% refundable after completion of RCC work, and the remaining after completion of construction.

4. It is stated in the application that the non-applicant allegedly failed to comply with key obligations, including submission of necessary applications to the Urban Improvement Trust (UIT) for depositing Floor Area Ratio (FAR)charges (challan dated 29.01.2014). This prevented the applicant from proceeding with the development. Dispute is that after receiving Rs. 1 crore, the non-applicant backed out of the agreement. He neither returned the amount nor reimbursed the applicant for costs incurred on registration, hiring engineers/architects, and other project-related expenses.

5. A legal notice was served on 25.09.2018, invoking the Arbitration Clause (Clause 17) of the Development Agreement but to no avail. Left with no choice, the applicant filed a civil suit (No. 58/2019) before the Commercial Court, Jodhpur. On 31.08.2022, the Court returned the plaint to the applicant to approach the Arbitrator in view of Clause 17 of the development agreement.

6. Learned counsel for the applicant submits that Clause 17 of the Development Agreement provides for resolution of disputes through arbitration. He further states that since the parties are not ad idem regarding the appointment of a Sole Arbitrator, the present application has been filed in terms of the said clause.

7. Learned counsel for the respondent argues that the applicant had earlier filed a civil suit for adjudication of the dispute between the parties which was not entertained by the learned court. Present application at this stage is now time barred, he would further contend.

8. I have gone through the record and heard the learned counsel for the parties.

9. The arbitration Clause-17 as contained in the agreement is reproduced herein below:-

"17. That all disputes in relation to the interpretation of the any terms and conditions of this agreement and rights and liabilities of both the parties or any dispute arising out of this agreement shall be referred to an arbitrator and whose decision shall be final and binding upon the parties and for all proceedings of arbitration, the jurisdiction shall be Bikaner only and all the provisions of the Arbitration and Conciliation Act, 1996 shall apply."

10. The applicant when earlier approached the civil Court, the respondent opposed the forum on the ground that it ought to invoke arbitration proceeding as per clause 17 ibid. Now that the instant application has been filed before this Court seeking arbitration proceeding the same is being opposed on the ground that the applicant had earlier approached the civil Court.

11. The aforesaid arbitration clause is not disputed. Moreover, there is no quibble about the fact that there is an existing dispute between the parties, but there is a dispute as to which forum should adjudicate the same. However, on a court query qua t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top