SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Raj) 15917

HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
Pushpendra Singh Bhati, Anuroop Singhi, JJ
RAJASTHAN STATE ROAD DEVELOPMENT AND CONSTRUCTION – Appellant
Versus
M/S PRAMAN CONSTRUCTION PVT. LTD. – Respondent
D.B. Civil Misc. Appeal No. 2338/2024



Advocates:
For the Appellants/Petitioners: Sunil Bhandari
For the Respondents: Harshit Bhurani

A contractual dispute resolution mechanism cannot override the statutory mandate of the Limitation Act; once a contract is rescinded and final measurements are taken, the cause of action crystallizes, and subsequent representations do not revive a time-barred claim.

Headnote:The appeal was preferred under S.13 of the Commercial Courts Act, 2015. A contractor was awarded a construction contract, which was rescinded on 23.09.2010, and final measurement was conducted on 06.10.2010. A suit for recovery of dues was filed on 10.12.2015, which was partly decreed by the trial court. The court found that the suit was barred by limitation as the cause of action had crystallized in 2010. The main issue was whether the suit was within the prescribed period of limitation. The court held that 'a contractual dispute resolution mechanism cannot override the statutory mandate of the Limitation Act, 1963' and that the invocation of a contractual dispute resolution clause after the expiry of the limitation period could not revive a time-barred claim. It further determined that withholding payment after contract termination does not constitute a 'continuing breach' under Art. 55 of the Limitation Act. The judgment and decree dated 05.06.2024 passed by the learned Commercial Court, Udaipur in Commercial Case No. 167/2018 (E.D.) is hereby quashed and set aside.

Table of Content
1. background of contract award, rescission, and suit filing. (Para 1 , 2)
2. rival contentions regarding limitation and breach of contract. (Para 3 , 4)
3. limitation crystallizes upon final measurement; contractual clauses cannot override statute. (Para 5 , 6)
4. suit held time-barred and lower court decree set aside. (Para 7 , 8 , 9)

Judgment

1. Date of conclusion of arguments 20.11.2025

2. Date on which judgment was reserved 20.11.2025

3. Whether the full judgment or only the operative part is pronounced: Full judgment

4. Date of pronouncement 19.12.2025

Per Dr. Pushpendra Singh Bhati, J:

1. The present D.B. Civil Misc. Appeal has been preferred under Section 13 of the Commercial Courts Act, 2015 claiming the following relief:

“It is, therefore, most humbly and respectfully prayed that the record of the case may kindly be called for and by an appropriate writ, order or direction:–

1. The present appeal may kindly be allowed and the judgment / decree dated 05.06.2024 passed by the Commercial Court, Udaipur in Case No. 167/2018 (E.D.) (C.I.S. No. 169/2018), holding the appellant jointly and severally liable for payment of Rs.27,66,879/- towards the final bill and Rs.13,56,864/- towards the refund of security deposit along with interest @ 9% p.a. and further quashing the order dated 23.09.2010 imposing penalty of Rs.13,00,000/- on the respondent plaintiff and further restraining the appellant from taking any action against the respondent plaintiff pursuant to order dated 23.09.2010, may kindly be quashed and set aside with costs.

2. Any other appropriate order or direction as may be deemed just and proper in the facts and circumstances of the case may kindly be passed in favour of the appellant.”

2. Brief facts out of which the instant controversy has emanated are that the respondent–company was awarded a contract by the appellant–Corporation for construction of Sajjangarh Biological Park, Udaipur, and a work order dated 01.09.2009 was issued for a contract value of Rs. 2,74,44,746.85/-.

2.1. As per the work order, the work was to commence on 16.09.2009 and was required to be completed within a stipulated period of 11 months, i.e., on or before 15.08.2010. A formal contract governing the execution of the work was entered into between the parties.

2.2. During execution of the contract, disputes arose between the parties with regard to execution of work, availability of drawings, progress of work, and compliance with contractual terms.

2.3. On 23.09.2010, the appellant–Corporation rescinded the contract and imposed a penalty upon the respondent in terms of the contract. The respondent was thereafter called upon to remain present for final measurement of the work done.

2.4. A committee was constituted for taking final measurement of the work, and final measurement was carried out on 06.10.2010, in which the respondent participated.

2.5. Thereafter, the respondent submitted claims in respect of the work executed and raised disputes regarding payment of alleged outstanding dues.

2.6. On 10.12.2015, the respondent instituted a civil suit before the competent court seeking recovery of an amount of Rs. 57,19,993/-, along with declaration and permanent injunction, which came to be transferred to the Commercial Court, Udaipur.

2.7. Upon consideration of the pleadings, evidence and submissions of the parties, the learned Commercial Court, Udaipur, vide judgment and decree dated 05.06.2024, partly decreed the suit, which has given rise to the present appeal.

3. Learned counsel for the appellants, at the outset, submitted that the impugned judgment and decree dated 05.06.2024 passed by the learned Commercial Court, Udaipur suffer from serious errors of law and jurisdiction and are liable to be set aside.

3.1. Learned counsel submitted that the suit instituted by the respondent on 10.12.2015 was ex facie barred by limitation. It was contended that the contract was rescinded on 23.09.2010 and final

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top