2026 Supreme(Online)(Raj) 1686
HIGH COURT OF RAJASTHAN (JODHPUR BENCH)
SUNIL BENIWAL
M/S CHAMPAT SINGH RAJU SINGH RAJPUROHIT – Appellant
Versus
STATE OF RAJASTHAN – Respondent
CW / 2337 / 2026
##PAGE1##
[2026:RJ-JD:5588]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Civil Writ Petition No. 2337/2026
M/s Champat Singh Raju Singh Rajpurohit, Proprietorship Form
Through Its Proprietor Shri Champat Singh S/o Shri Raju Singh,
Aged About 42 Years, Resident Of Safed Aakade Ke Pass, Gadan,
Mahabar Road, Barmer, Rajasthan.
----Petitioner
Versus
1. State Of Rajasthan, Through The Secretary, Public Works
Department, Government O Rajasthan, Jaipur, Rajasthan.
2. The Chief Engineer, Public Works Department, Jaipur.
3. The Superintending Engineer, Public Works Department,
Circle- Balotra, District Balotra.
4. The Executive Engineer, Public Works Department
Division- Balotra, District Balotra.
5. The Assistant Engineer, Public Works Department, Sub
Division- Samdari, District Balotra.
----Respondents
For Petitioner(s) : Mr. Uttam Singh
For Respondent(s) : --
HON'BLE MR. JUSTICE SUNIL BENIWAL
Order
30/01/2026
1. Learned counsel for the petitioner submits that the petitioner
was awarded a contract by the respondent Department for
construction of various missing link/non-patchable roads under
Package No. RJ-43-07/15 CR/State Fund/2025-26 in District
Balotra. He submits that pursuant to the issuance of the work
order, the petitioner commenced the work and approximately 50%
of the work was completed. However, the petitioner was informed
(Uploaded on 30/01/2026 at 06:27:37 PM)
(Downloaded on 31/01/2026 at 08:53:05 AM)
##PAGE2##[2026:RJ-JD:5588] (2 of 3) [CW-2337/2026]
via telephonic communication on 21.01.2026 that the contract of
the petitioner has been terminated.
2. Learned counsel for the petitioner contends that prior to
cancellation of the contract, no opportunity of hearing was
afforded to the petitioner and even the decision to terminate the
contract was not duly communicated. It is submitted that the
petitioner was ready and willing to complete the entire remaining
work within a period of one month, however, the respondents
have taken a decision to float a fresh tender.
3. Being aggrieved by the said action, the petitioner has
preferred the present writ petition.
4. Heard learned counsel for the petitioner.
5. This Court takes note of the fact that a work order was
issued in favour of the petitioner, wherein it was clearly stipulated
that the petitioner was required to commence the work from
08.10.2025 and complete the same by 07.02.2026. Vide
communication dated 06.11.2025, the petitioner was informed
that despite the stipulated date for commencement of work being
08.10.2025, the petitioner had failed to commence the work
within a period of one month.
6. After the aforesaid communication, the petitioner was served
with a notice dated 02.12.2025, informing him of the proposed
action of withdrawal/cancellation of the contract under Clauses 2
and 3 of the Contract Agreement. The said communication was
followed by a reminder dated 04.12.2025. As no satisfactory
response was received from the petitioner, the respondent
authorities invoked Clauses 2 and 3 of the Contract Agreement
and vide order dated 09.12.2025, proceeded to withdraw the
(Uploaded on 30/01/2026 at 06:27:37 PM)
(Downloaded on 31/01/2026 at 08:53:05 AM)
##PAGE3##[2026:RJ-JD:5588] (3 of 3) [CW-2337/2026]
subject tender work from the petitioner along with imposing a
penalty amount as well as an additional performance security
amount.
7. Learned counsel for the petitioner submits that the said
proceedings were undertaken without giving any notice. This
Court does not find the said submission to be an acceptable
ground for entertaining the present writ petition.
8. Considering the fact that the petitioner failed to commence
the work as stipulated in the work order and further failed to
submit any satisfactory response pursuant to the communications
dated 06.11.2025 and 25.11.2025, this Court is of the view that
the respondents were fully justified in passing the order dated
09.12.2025 (Annexure-9) and in taking a decision to float a fresh
tender.
9. In view of the aforesaid facts and circumstances, this Court
is not inclined to entertai