THE RAJASTHAN REAL ESTATE REGULATORY AUTHORITY, JAIPUR Comp. No. RAJ-RERA-C-2021-4388 Jagdish Chandra Sharma ...Complainant Versus SNG Real Estate Pvt. Ltd. ...Respondent Present Shri Shailendra Agarwal, Hon’ble Member (1) Adv Suruchi Kasliwal Multani, on behalf of the complainant through video conferencing CA Praneti Agarwal, on behalf of the respondent promoter through video conferencing Date of Order: 05.01.2022 ORDER The instant case pertains to a project by the name “Krishnangan” registered with this Authority with registration No. RAJ/P/2017/003 Promoted by the respondent promoter SNG Real Estate Pvt. Ltd. The complainant Lt. Col. Jagdish Chandra Sharma was represented by his Advocate Suruchi Kasliwal Multani. Arguing first in favour of the complainant, she argued that the residential project Krishnangan” was an incomplete and Page No.) of 10 Comp. No. 2021-4388 ]much delayed project which was to be completed by 30.09.2019 which has lapsed and the project has not been completed even after more than two years of the promised date of completion. She argued that the complainant was a landowner along with others and has been forced to continue to live in the rented accommodation because the project has not been completed in time by the respondent Promoter. She argued that the respondent had to pay a penalty of Rs. 1,00,000/- per month after the deadline for completion of the project had elapsed for a period of six months which was termed. as the grace period for completing the project. However, the respondent promoter neither completed the project nor paid the penalty. She argued that the complainant was an allottee as well in terms of provisions of section 2(3) of the Real Estate (Regulation and Development) Act, 2016 (hereinafter called ‘the Act’) and stated that the development and construction agreements entered into between the landowner and the respondent promoter dated 11.11.2012 and 28.06.2013 clearly stated that the complainant had no involvement whatsoever in raising the construction or completing the construction work. She vehemently argued that Page No.2 of 10 Comp. No. 2021-4388 ;her client, the complainant, was not a Promoter or a co-promoter in any sense of the word and the complainant along with his two other brothers own the land in question which they handed over to the respondent for completing the construction of the project in a time bound manner as per the clauses agreed to in the development and construction agreements. Citing the notification No. F.1(152)RJ/RERA/LAND/2020/1202 issued by this Authority on 30.06.2020 she stated that this notification further confirms that her client, the complainant, was not a Promoter or a co-promoter within the terms of this notification. She also argued that another Memorandum of Understanding (MOU) was signed ¥)\ between the complainant and the respondent which allowed JE reconstitution of the plots of land in question. However, even though the complainant had cooperated with the respondent in all possible terms the respondent has failed to complete the construction of the Project or pay the requisite penalty and the complainant is forced to reside in a rented accommodation and thereby Suffering financial loss apart from grave mental and physical agony at the old age of 89. She further alleged that the respondent had taken two extensions from the Authority without Page No.3 of 10 Comp. No. 2021-4388any information to the landowner and had also submitted wrong information to the Authority regarding the date of commencement of construction. The extension has been obtained without obtaining any permission from the allottee or the complainant. The MOU between the landowner and the respondent having been terminated wayback in 2019 and violation of the provisions of section 6 of the Act was being committed. Closing her argument she stated that as the complainant was neither a Promoter nor a co-promoter and was indeed an aggrieved person within the provision