2024 Supreme(Online)(SC) 10011

DIPANKAR DATTA, S. RAVINDRA BHAT, JJ
M/S UNIBROS – Appellant
Versus
ALL INDIA RADIO – Respondent
CIVIL APPEAL NO…………………/2023 | SLP (CIVIL) NO. 8791/2020



Advocates:
For the Appellants/Petitioners: Mr Sameer Rohatgi
For the Respondents: Mr Sanjay Jain

In claims for loss of profit due to contract delays, the claimant must provide credible evidence of potential profits missed, or the claim will be dismissed as lacking substantiation.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Appeal against suspension of arbitral award - Arbitral award setting aside loss of profit - Court confirms lower court's view that lack of evidentiary support for loss of profit renders award illegal and contrary to public policy. (Paras 11-21)

(B) Legal principles on claims for loss of profit established - Party seeking damages for delay in completion must substantiate delay and provide credible evidence of lost opportunities. (Paras 16-20)

Facts of the case:
The appellant claimed compensation for loss of profit from delays caused by the respondent in completing a contract for construction. Disputes arose leading to arbitration, where the appellant was initially awarded damages for loss of profit which was later challenged and set aside by higher courts due to lack of evidence.

Findings of Court:
The court finds the arbitral award to violate public policy due to inadequate evidence supporting the appellant’s claims.

Issues: Whether a contractor claiming loss of profit due to delay needs to substantiate with evidence that such profits could have been made elsewhere.

Ratio Decidendi: The court reaffirms that loss of profit claims must be founded on demonstrable evidence, with courts not permitted to guess damages in the absence of supporting facts.

Result: Appeal dismissed.

Judgement Key Points

In the context of claims for loss of profit due to delays in contract performance, such as the issue of idle charges, the legal principles outlined in the provided document emphasize the importance of credible and sufficient evidence to substantiate such claims (!) (!) . Specifically, the claimant must demonstrate that the delay caused by the respondent resulted in the contractor being unable to undertake other profitable work opportunities with their existing resources.

The courts have clarified that mere assertions or estimations are inadequate; instead, the claimant must produce concrete evidence—such as details of other potential projects, tender opportunities declined, or financial statements—that convincingly establish the existence of viable alternative profits that were foregone due to the delay (!) .

Furthermore, the use of formulas like Hudson’s may aid in estimating damages, but they cannot substitute for actual evidence of loss. The application of such formulas requires that the claimant first substantiate that the loss of profit was real and measurable, and not merely speculative (!) (!) .

In summary, for claims related to idle charges or loss of profit due to contract delays, the claimant must provide credible, tangible evidence demonstrating that the delay directly caused the loss of specific, identifiable profit opportunities. Without such evidence, claims for idle charges are unlikely to be upheld, and awards based solely on estimations or formulas without proper evidentiary support may be considered contrary to public policy and legally unsustainable (!) (!) .


Table of Content
1. claim for loss due to delay in contract performance. (Para 3)
2. arguments regarding evidence supporting profit claims. (Para 5)
3. court's observations on public policy and evidence requirements. (Para 7 , 8 , 10 , 11 , 14)
4. requirement for credible evidence in profit loss claims. (Para 20)
5. final dismissal due to lack of substantiation. (Para 21)

JUDGEMENT

DIPANKAR DATTA, J.

1. Leave granted.

2. This appeal, at the instance of M/s Unibros (“appellant”, hereafter), registers a challenge to the judgment and order dated 9th December, 2019 in FAO (OS) 229/2010 passed by the High Court of Delhi (“High Court”, hereafter) dismissing an appeal carried by the appellant under section 37 of the Arbitration and Conciliation Act, 1996 (“the Act”, hereafter). Vide the impugned judgment, a Division Bench affirmed the judgment and order of a learned Single Judge dated 25th February, 2010 whereby an objection of the All India Radio (“respondent”, hereafter) under section 34 of the Act was allowed resulting in setting aside of an arbitral Award dated 15th July, 2002 to the extent it awarded loss of profit to the appellant.

3. The relevant facts, discerned from the records, reveal that the appellant was awarded a work contract by the respondent to carry out Digitally signed by NEETA SAPRA Date: 2023.10.19 16:05:01 IST Reason:

    Signature Not Verified construction of Delhi Doordarshan Bhawan, Mandi House, Phase-II, New Delhi. The work was scheduled to commence on 12th April, 1990 and reach completion on 11th April, 1991; however, it suffered a delay of roughly 42½ months and was finally completed on 30th October, 1994. Disputes and differences emerged between the parties owing to such delay, which were subsequently referred to an Arbitrator (“Arbitrator”, hereafter) for resolution.

4. The trajectory of the case, leading to the present stage, is set out hereunder: a) Arbitration proceedings having been initiated, the Arbitrator vide award dated 11th February, 1999 (“First Award”, hereafter) decided various claims and counter-claims filed by the parties.

Claim Nos. 10, 11, and 12 were collectively addressed under section 73 of the Indian Contract Act, 1872 (“Contract Act”), as they all centred around the issue of delay and the resultant losses.

Vide Claim No. 10, the appellant claimed a sum of Rs. 50,00,000.00 (Rupees fifty lakh) owing to the marked escalation in prices/rates for the work executed beyond the stipulated contract period. Vide Claim No. 11, the appellant implored the Arbitrator to award Rs. 41,00,000.00 (Rupees forty-one lakh) to cover substantial expenses associated with the establishment, machinery, centring/shuttering, and other vital aspects of the project. Additionally, vide Claim No. 12, the appellant urged that a compensation of Rs. 2,00,00,000.00 (Rupees two crore) be granted as redress for the loss of profit endured due to the appellant’s protracted retention on the contract without any corresponding increase in monetary benefits earned. Despite the Arbitrator's rejection of Claim Nos. 10 and 11, the appellant was awarded a sum of Rs. 1,44,83,830 (Rupees one crore, forty-four lakh, eighty-three thousand, eight hundred and thirty) towards Claim No. 12, along with an interest of 18% per annum under Claim No. 13 from 12th May, 1997 to the date of actual payment. The Arbitrator supported this award based on the undisputed fact that the delay in completing the work beyond the stipulated contract period was caused by the respondent and against the stipulated contract period of 12 months, the appellant was retained by the respondent for the execution of the work for an additional period of 3½ years leading to loss of the appellant’s profit earning capacity during the said extended period. The loss of profit was worked out based on a profit allowance of 7½% per year, which the Arbitrator held to be reasonable in a civil works contract. Applying Hudson’s formula, the Arbitrator arrived at the final compensati




            Click Here to Read the rest of this document
            1
            2
            3
            4
            5
            6
            7
            8
            9
            10
            11
            SupremeToday Portrait Ad
            supreme today icon
            logo-black

            An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

            Please visit our Training & Support
            Center or Contact Us for assistance

            qr

            Scan Me!

            India’s Legal research and Law Firm App, Download now!

            For Daily Legal Updates, Join us on :

            whatsapp-icon Back to top