SUPREME COURT OF INDIA
L. NAGESWARA RAO, J
M/S. INOX WIND LTD. – Appellant
Versus
M/S THERMOCABLES LTD. – Respondent
CIVIL APPEAL No . 19 of 2018 | SLP (Civil) No.31049 of 2016



Advocates:
For the Appellants/Petitioners: Not mentioned
For the Respondents: Not mentioned

General reference to a standard form is sufficient for incorporation of an arbitration clause in a contract.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Appeal against the dismissal of application for appointment of arbitrator - The purchase order contained arbitration clause incorporated by reference to standard terms - General reference to standard form is sufficient for incorporation of an arbitration clause. (Paras 19, 20)

(B) Incorporation of Arbitration Clause - The court clarified that while a general reference to an earlier contract is not sufficient to incorporate an arbitration clause, a general reference to a standard form contract of one party suffices. (Paras 18-19)

Table of Content
1. introduction and background of appeal (Para 1 , 2)
2. details of purchase order and dispute (Para 3 , 4)
3. high court dismissal basis (Para 5 , 6)
4. discussion of relevant case law (Para 7 , 8 , 9)
5. final judgment and appointment of arbitrator (Para 19 , 20 , 21)

JUDGMENT

L. NAGESWARA RAO, J.

Leave granted.

2. This appeal is directed against the judgment of the High Court of Judicature at Allahabad dismissing the application filed by the Appellant under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’).

3. The Appellant is a manufacturer of wind turbine generators (WTGs).

The Respondent is engaged in the business of manufacture of wind power cables and other types of cables. Two purchase orders dated 13.12.2012 and 02.02.2013 were issued by the Appellant to the Respondent for supply of cables for their WTGs. According to the Purchase Order, the supply was to be according to the terms mentioned in the order and the Standard Terms and Conditions that were attached thereto. Apart from the other conditions, the Standard Terms and Conditions contain a clause pertaining to dispute resolution. The said clause provides for a dispute to be resolved by a sole arbitrator in accordance with the provisions of the Arbitration and Conciliation Act, 1996 . The material on record indicates that the Respondent accepted all the terms and conditions mentioned in the Purchase Order except the delivery period as is evident from a letter dated 15.12.2012.

4. The Respondent, pursuant to the Purchase Order, supplied wind power cables to the Appellant. While laying the cables supplied by the Respondent-company, the Appellant discovered that the outer sheaths of the cables of 150 sq. mm. were cracked. This forced them to stop the WTGs so as to avert damage to expensive equipment. According to the Appellant, the Respondent-company did not replace the cables. The Appellant, therefore, was constrained to issue a notice dated 30.10.2014 proposing the name of a sole arbitrator in terms of the Standard Terms and Conditions. In the absence of any response, the Appellant moved the High Court of Judicature at Allahabad by filing an application under Section 11 (6) of the Act.

5. The High Court dismissed the said application by holding that an arbitrator cannot be appointed as the Appellant did not prove the existence of an arbitration agreement. The High Court relied upon the judgment of this Court in M.R. Engineers and Contractors Private Limited v. Som Datt Builders Limited , (2009) 7 SCC 696 to hold that there is no special reference to the arbitration clause in the standard terms and conditions, so the arbitration clause cannot be said to have been incorporated into the purchase order.

6. We have heard the counsel for the Appellant and Respondent. The judgment of this Court in M.R. Engineers’ case (supra) was relied upon by both the parties. Before proceeding further, it would be necessary to appreciate the ratio of the said judgment. A few facts necessary to understand the dispute in the said case are that the Appellant therein was a sub-contractor of the Respondent. The Appellant was entrusted a part of the work by the Respondent-contractor which pertained to ‘construction of project directorate building’. It was mentioned in the sub-contract that it shall be carried out as per the terms and conditions applicable to the main contract. A dispute arose between the parties which made the Appellant therein to approach the High Court for appointment of an arbitrator under Section 11 (6) of the Arbitration and Conciliation Act, 1996 . The High Court of Kerala rejected the application on the ground that the arbitration clause in the main contract was not incorporated by reference in the contract between the Appellant and Respondent therein. In the appeal before this Court, the Appellant submitted that his case was squarely covered by Section 7 (5) of the Act and that the arbitration clause from

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top