SUPREME COURT OF INDIA
T. AROKIADOSS – Appellant
Versus
P. JOHN PHILIP – Respondent
SLP(C) No.-022011 - 2022



ITEM NO.7 COURT NO.14 SECTION XII S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS Petition(s) for Special Leave to Appeal (C) No. 22011/2022 [Arising out of impugned final judgment and order dated 27-04-2022 in SA No. 74/2019 passed by the High Court of Judicature at Madras]

T. AROKIADOSS Petitioner(s)

VERSUS P. JOHN PHILIP & ORS. Respondent(s)

IA No. 164649/2022 - EXEMPTION FROM FILING O.T.

Date : 21-01-2025 This matter was called on for hearing today.

CORAM : HON'BLE MR. JUSTICE J.B. PARDIWALA HON'BLE MR. JUSTICE R. MAHADEVAN For Petitioner(s) :Mr. S. Nagamuthu, Sr. Adv.

Mr. M.P. Parthiban, AOR Mr. Bilal Mansoor, Adv.

Mr. Shreyas Kaushal, Adv.

Mr. S. Geyolin Selvam, Adv.

Mr. Alagiri K, Adv.

Mr. P.v.k. Deivendran, Adv.

For Respondent(s) :Mr. R.Prabhakaran, Adv.

Mr. G.sivabalamurugan, AOR Mr. Selvaraj Mahendran, Adv.

Mr. S.b.kamalanathan, Adv.

Mr. C.adhikesavan, Adv.

Mr. Harikrishnan P.v, Adv.

Mr. C.kavin Ananth, Adv.

Signature Not Verified Digitally signed by CHANDRESH 1 Date: 2025.01.23 Reason:

UPON hearing the counsel the Court made the following

O R D E R

1. This petition arises from the judgement and order passed by the High Court of judicature at Madras dated 27 April, 2022 in Second Appeal No. 74 of 2019, by which the second appeal filed by the appellant herein (original plaintiff) came to be dismissed thereby affirming the judgment and order passed by the First Appellate Court.

2. We take notice of the fact that the plaintiff herein instituted a civil suit for specific performance of contract based on an agreement of sale dated 21.04.2008. The agreement of sale entered into was in respect of land ad-measuring 3.18 acres. At the time of agreement of sale, an amount of Rs. 3 lakh was paid by the plaintiff to the defendants, as against the total sale consideration of Rs. 5,10,000/- fixed in the agreement.

3. As disputes cropped up between the parties, the plaintiff instituted a suit for specific performance which came to be allowed. The defendants being dissatisfied with the judgment and decree granting specific performance preferred first ap- peal before the District Court. The First Appellate Court al-

lowed the appeal and reversed the judgment and decree passed by the trial court.

4. The plaintiff being dissatisfied with the judgment and order passed by the Appellate court went before the High Court by way of second appeal. The second appeal came to be dis-

missed.

5. In such circumstances, referred to above, the petitioner (original- plaintiff) is here before this court with the present petition.

6. We have heard Mr. M.P. Parthiban, the learned counsel appearing for the petitioner (original-plaintiff) and Mr. R. Prabhakaran, the learned counsel appearing for the respondents (original defendants).

7. It appears that the First Appellate Court as well as the High Court doubted the very credibility of the sale agree- ment. The High Court in Para 24 of its impugned judgment has observed thus:-

“24.It is found from the evidence produced that Ex.A1 sale agreement could have been executed only for the purpose of a loan transaction. The circumstances sur- rounding, the execution of Ex.A1 sale agreement, dis- cussed above confirms that Ex.A1 sale agreement could have been executed only for the purpose of loan trans- action and not really intended to be a sale agreement. Ordinary rules is that specific performance should be granted. When there are evidences to support the case of the respondent that Ex.A1 sale agreement was not executed intending to sell the property, but executed in connection with the loan transaction, the settled proposition is that specific performance relief cannot be granted. When the sale price was only Rs.5,10,000/- and a sum of Rs.3,00,000/- was paid even on the date of sale agreement on 21.04.2008 to the defendants 2 to 4, there is a genuine question arises, why instead of executing a sale agreement, further part payments were made on 20.05.2008 and on 11.07.2008. The time fixed for completion of sale is one month fro