| 1. court makes directives for the execution of a conveyance deed. (Para 1 , 2) |
| 2. court confirms documents must be available for execution. (Para 3 , 4) |
| 3. court orders timely registration of the conveyance deed. (Para 5 , 6 , 7) |
UPON hearing the counsel the Court made the following
O R D E R
1. The parties are required to execute the Conveyance Deed in accordance with the judgment dated 23.09.2022 in Civil Appeal No. 2741 of 2009.
2. Learned counsel for the respondents submits that though the respondents have approached the Registering Authorities, i.e., (i) Sub-Registrar, Bidarahalli (ii) The District Registrar, Shivajinagar (iii) The Panchayat Development Officer (PDO), Mandur Panchayath (iv) The Tehsildar, K.R.Puram (v) Bangalore North Assistant Commissioner and (vi) Bangalore Urban Deputy Commissioner, the Conveyance Deed could not be executed on account of the non-availability of certain documents.
3. We see no reason for the Registering Authorities to withhold the execution of the Conveyance Deed, inasmuch the area, which is to be handed over to the petitioners, has been identified by this Court vide its order dated 07.11.2023 in the present proceedings..
4. It is also not in dispute that vide order dated 21.04.2025, this Court noted that the Assistant Director of the Land Records, Bengaluru East Taluk, Bengaluru has carried out demarcation as per the order dated 07.11.2023 passed by this Court. Accordingly, this Court directed that on receipt of the report of the Assistant Director of Land Records, respondent Nos. 2 and 3 shall execute Conveyance Deed in favour of the petitioner within a period of eight weeks.
5. In that view of the matter, we direct the abovestated Registering Authorities to ensure that the Conveyance Deed is duly registered within a period of two weeks from today.
6. The parties shall remain present before the Registering Authorities on 27.10.2025 for execution of the Conveyance Deed.
7. List this matter after two weeks for compliance.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.