SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(Online)(SC) 624

SUPREME COURT
*T. S. Thakur, C. J., R. Banumathi, J.
Northern Coalfield Ltd. – Appellant
Versus
Heavy Energy Corporation Ltd. – Respondent
Civil Suit No. 1709 of 2000 | Appeal No. 64 of 1999 | Appeal No. 67 of 1998 | RFA (OS) No.50 of 2007



Advocates:
For the Appellants/Petitioners: Mr. P.S. Patwalia
For the Respondents: Mr. Ranjit Kumar

The Supreme Court ruled that the absence of clearance from the Committee on Disputes does not invalidate the right to file a suit, and that disputes between government corporations should be adjudicated according to statutory provisions, not administrative mechanisms.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Permanent Machinery of Arbitration - Dispute between two Government corporations regarding contracts for a Coal Handling Plant - The High Court ruled that the absence of clearance from the Committee on Disputes precluded the filing of a suit, leading to the rejection of the plaint. The Supreme Court found that the High Court misinterpreted the legal requirement and that litigation was permitted to save limitation. The Supreme Court emphasized that a proper adjudication of the disputes is necessary as the awards under the special procedure lacked enforceability under existing arbitration laws. (Paras 1-28)

(B) Clearances and Legal Entitlements - The mechanism for inter-governmental disputes should ensure adequate resolution without judicial stagnation; the previous requirement of clearance from the Committee on Disputes was abrogated, allowing for renewed arbitration under statutory regulation. (Paras 18-28)

(C) Administrative Actions vs. Legal Remedies - Debates surrounding the enforceability of awards created via administrative frameworks necessitate recourse to established judicial mechanisms regardless of the parties involved. (Paras 19-26)

Facts of the case:
The appellant contracted the respondent to construct a Coal Handling Plant with disputes arising concerning contract fulfillment and subsequent awards favoring the parties. The High Court intervened due to claims of breach.

Findings of Court:
The Supreme Court found the High Court's interpretation flawed, underscoring the lack of legal impediments to filing claims under existing arbitration law.

Issues: Whether the absence of clearance from the Committee on Disputes invalidated the suit and if the arbitral awards could be challenged or must be enforced administratively.

Ratio Decidendi: The Court held that a suit could not be rejected solely for lack of Committee clearance and that the permanent arbitration mechanism was not a substitute for statutory arbitration.

Result: Appeal allowed; disputes referred to arbitration.

1. Leave granted.

2. This is yet another case that brings to fore a sad state of affairs when it comes to resolving disputes between two Government owned corporations. What adds to the enigma of apathy towards realism in official circles is the fact that the respondent - corporation has with considerable tenacity opposed the move aimed at a quick and effective resolution of the conflict and resultant quietus to the controversy by a reference of the disputes to arbitration in terms of the Arbitration and Conciliation Act , 1996.

3. The Facts:
Appellant - Northern Coalfield Ltd. issued a tender for construction of a Coal Handling Plant at Bina sometime in May, 1984. The construction work was meant to be carried out under two contracts: viz. (1) a Contract for works and services and (2) a Contract for equipment and spares. Both these contracts were awarded to the respondent - Heavy Energy Corporation Ltd. which is also a Government of India company. The contracts contained a Clause that provided for adjudication of disputes between the parties by way of arbitration. Disputes having actually arisen in relation to the two contracts, the same were referred for resolution in terms of the "permanent in - house administrative machinery" set up by the Government. Claims and counter claims were made by the two corporations against each other which finally culminated in the making of two awards both dated 28.02.1997 under which respondent No.1 was held entitled to a sum of Rs.16,87,61,981.11/-, while the appellant was awarded Rs.56,05,000/-. Both the parties were, however, dissatisfied with the awards which they challenged in appeals filed before the Law Secretary, Department of Legal Affairs, Ministry of Law and Justice in terms of the in - house mechanism provided by the Government. While Appeal No. 67 of 1998 filed before the Law Secretary pertained to the contract for supply of equipment, Appeal No. 64 of 1999 pertained to the contract for execution of works and services.

4. During the pendency of the appeals aforementioned respondent No. 2 - M/s. Rampur Engineering Company Ltd. filed Suit No. 450 of 1999 before the High Court of Delhi against the two corporations in which the said respondent prayed for an injunction restraining respondent No.1 from settling the disputes with the appellant. The appellant's case is that it came to know about the role of Respondent No.2 in the execution of contracts only after the filing of the said suit in which by an interim order, the High Court restrained the parties from implementing any award made by the appellate authority. The appellant's further case is that respondent No.1 had, contrary to Clause 3 of the Terms of Contracts executed with the appellant, sublet the contracts in favour of respondent No.2 without prior consent of the former and that the said arrangement was of no legal consequence nor did it create any legal relationship between the appellant and the sub-contractor.

5. Appeal No. 64 of 1999, arising out of the contract for works and services came to be disposed of first, wherein the appellate authority made an award on 13.11.1999 holding that a sum of Rs.15,84,50,000/- apart from Rs.3.73 crores due as interest was recoverable from the appellant. Appeal No. 67 of 1998 filed by the first respondent was disposed of by the appellate authority on 01.12.1999 remanding the matter back to the Arbitrator for reconsideration. Aggrieved by the awards made by the Arbitrator and the appellate authority, the appellant - herein filed Civil Suit No. 1709 of 2000 before the High Court of Delhi in which it claimed a declaration to the effect that respondent No.1 had committed a breach of Clause 3 of the terms of the Contracts executed between the two Corporations by sub-letting the contract to respondent No. 2 thereby rendering the contracts between the appellants and the first respondents null and void. The appellant further prayed for a declaration to the effect that respondent No.1 was not entitled

























































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top