REPORTABLE
2026 INSC 228 IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS. OF 2026 (Arising out of SLP (C) Nos. 23846-47 OF 2025)
MUNICIPAL CORPORATION OF GREATER MUMBAI …APPELLANT VERSUS M/S R.V. ANDERSON ASSOCIATES LIMITED …RESPONDENT
JUDGMENT
J.K. MAHESHWARI, J.
1. Leave granted.
2. The instant appeal(s) are directed against the judgment dated 04.07.2025 of the High Court of Bombay (hereinafter referred to as “High Court”) in Arbitration Appeal (L) No. 4339 of 2024 with Interim Application (L) No. 7312 of 2024.
3. By the impugned judgement, the High Court dismissed the appeal of the Appellant – Municipal Corporation of Greater Mumbai (hereinafter referred to as “MCGM”) under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred toas “1996 Act”) and confirmed the judgment and order dated 19th and 20th of October, 2022 of the learned Single Judge in Arbitration Petition No. 84 of 2012 dismissing the application filed under Section 34 of the 1996 Act by MCGM for setting aside the award dated 05.06.2010 of a three-member Arbitral Tribunal.
4. The challenge made in the proceedings of Section 34 was threefold - improper constitution of the tribunal, limitation and interest. However, before us, the Appellant has confined their arguments only to the question of lack of jurisdiction due to improper constitution of the tribunal. As such, our examination of the facts of the case is confined to the question of validity of constitution of the tribunal.
FACTS
5. The facts shorn of unnecessary details are that the MCGM had floated a tender and invited proposals for ‘Consultancy Services to Upgrade Sewerage Operations & Maintenance Services’. The scope of work of the contract was for providing consultancy in upgrading the sewage and sewerage handling facilities, operations and routine maintenance protocols. This was a World Bank funded project and the Respondent turned out to be the successful bidder in association with PHE Consultants, Mumbai. Pursuant thereto, an agreement dated 18.09.1995 (hereinafter referred to as the “Agreement”) was entered into between the MCGM and M/s R.V. Anderson Associates Ltd., which is an engineering firm based out of Canada.
6. The stipulated duration for completion of the work under the Agreement was 72 months and the contract was designed to be implemented in stages. The work under the contract was completed on 20.06.2001 and a final report was submitted by the Respondent to the MCGM. At that stage, a dispute arose in respect of payment of outstanding dues. A meeting was held on 24.10.2002 where the Respondent’s claims were discussed and rejected by MCGM except to make partial payments on 17.02.2004.
7. When things stood as thus, on 09.08.2005, the Respondent invoked the arbitration clause as contained in the Agreement. Vide communication dated 09.08.2005, received by the MCGM on 14.09.2005, the Respondent invoked the arbitration clause, particularly clause 8.3(b) of the Agreement and appointed Hon’ble Mr. Justice S.M. Jhunjhunwala (Retd.) as their nominee arbitrator. On 07.10.2005, the MCGM appointed Mr. Sharad Upasani, former IAS officer as their nominee arbitrator.
8. On 04.11.2005, a meeting was held between the Appellant and the Respondent, where the parties discussed about exploring a possibility of conciliation or mediation. In reference to the said meeting, another letter dated 08.11.2005 was sent by the Respondent to MCGM, seeking to explore non-binding conciliation or mediation and in the meanwhile, on confirmation by the MCGM, the arbitration proceedings be put in abeyance. The said letter dated 08.11.2005 was also marked to Justice Jhunjhunwala (Retd.) and Mr. Upasani. The MCGM, by writing letter dated 07.01.2006 acknowledged the intention of the Respondent to keep arbitration proceedings in abeyance and to start conciliation proceedings.
9. After a while, the Respondent wrote letters dated 12.02.2006 and 27.02.2006 to the MCGM, requesting to participate in the conciliation. It appears from the record that steps were not taken by the parties to explore the possibility of settlement and nothing was materialized. On 15.12.2006, MCGM addressed a letter to Mr. Upasani, informing him that there was no conciliation pur
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.