2026 Supreme(Online)(SC) 1940
IN THE SUPREME COURT OF INDIA
2026 INSC 1036
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. OF 2026
(@ SPECIAL LEAVE PETITION (CIVIL) NO. 24803 OF 2025)
North Eastern Electric Power Corporation Limited (NEEPCO) … Appellant
Versus
Astra Construction Private Limited … Respondent
Alok Aradhe, J.
SEPTEMBER 22, 2026
……………..……………………………….J.
[PAMIDIGHANTAM SRI NARASIMHA]
………………………………………………J.
[ALOK ARADHE]
NEW DELHI;
SEPTEMBER 22, 2026.
NON-REPORTABLE
J U D G M E N T
Alok Aradhe, J.
1. Leave granted.
2. This appeal calls in question the judgment dated 19.06.2025 rendered by the High Court, Digitally signed by, whereby the appeal preferred by the respondent under Section 37 of the Arbitration and Conciliation Act, 1996 (1996 Act) was allowed and the grant of pre-reference interest by the Arbitral Tribunal, earlier disallowed by the Commercial Court, was restored. The controversy, though narrow in compass, bears materially upon public works contracts generally, and turns upon the true meaning of Clause 54 of the SignatureG Not Veerifniederal Conditions of Contract (GCC) governing the parties' KAPIL TANDON Date: 2026.09.22 Reason:1 High Court of Meghalaya at Shillong
agreement, and upon whether the said clause corresponds, in substance, to the clause construed by a three-Judge Bench of this Court in State of U.P. v. Harish Chandra and Co., (1999) 1 SCC 63 or, instead, to the clauses considered in the later line of authority commencing with Sayeed Ahmed & Company v. State of U.P. & Ors., (2009) 12 SCC 26.
FACTS
3. The facts, shorn of unnecessary detail, may be briefly noticed. On 12.06.1995, the appellant invited tenders for the civil works of the main plant and auxiliary building of a Gas Turbine Power Project at Ram Chandra Nagar, Tripura. The respondent's tender was accepted, and a formal agreement was executed between the parties on 23.05.1996. The estimated value of the work under the contract was Rs. 17,09,26,913/- (Rupees Seventeen Crore Nine Lakhs Twenty-Six Thousand Nine Hundred and Thirteen only), and the work was stipulated to be completed by 26.03.1997.
4. Disputes having arisen between the parties, the matter was referred to arbitration. The Arbitral Tribunal, by its award dated 05.06.2015, held that the delay in execution of the project was attributable to the appellant. Four claims preferred by the respondent were allowed, and a principal sum of Rs. 3.30 crores was awarded. The Tribunal further awarded pre-reference interest at the rate of 12% per annum on each of the claims, together with pendente lite and future interest at the rate of 9% per annum.
5. The appellant assailed the award before the Commercial Court under Section 34 of the Act. The Commercial Court, by its judgment dated 15.02.2024, placed reliance on the decision of this Court in Sayeed Ahmed (supra), and held that Clause 54 of the GCC bars the grant of interest, whether pre-reference or pendente lite. The award was modified accordingly, and the grant of pre-suit and pendente lite interest on claim nos. 2, 3, 4 and 5 was set aside as being contrary to Clause 54 of the GCC read with Section 31(7) of the Act, the award being otherwise upheld.
6. Aggrieved, the respondent preferred an appeal under Section 37 of the 1996 Act. The High Court, by the impugned judgment, relying upon Harish Chandra (supra), held that the clause considered therein was identical to Clause 54 of the GCC; that the bar under Clause 54 was confined to interest claimed on money or balances held up owing to a dispute; and that it did not extend to interest on any other head of claim, including interest upon an award itself. The High Court accordingly restored the award of the Arbitral Tribunal in its entirety.
SUBMISSIONS
7. Mr. Tushar Mehta, learned Solicitor General and Mr. Raghavendra P. Shankar, learned Additional Solicitor General, appearing for the appellant at the outset confined the challenge to that part of the impugned judgment which restores the grant of interest for the pre-reference period. He submitted that the plea that Clause 54 bars interest for the pre-reference and pendente lite period was specifically raised before the Arbitral Tribunal, and that the High Court erred in relying upon Harish Chandra (supra), a decision rendered under the Arbitration Act, 1940 (1940 Act), without appreciating that the question stood authoritatively settled, in the context of the 1996 Act, in Sayeed Ahmed (supra) an