2025 Supreme(Online)(SCDRC) 3409

STATE CONSUMER DISPUTES REDRESSAL COMMISSION
RAJ SHEKHAR ATTRI, PRESIDENT, MR. PREETINDER SINGH, MEMBER
RESHMA RANI – Appellant
Versus
ROHTAS GOEL – Respondent
CONSUMER COMPLAINT NO. SC/4/CC/90/2024



Advocates:
For the Complainant: Col. Shamsher Singh (Retd.)
For the Respondents: Sh. Tajeshwar Singh

Contractual obligations must be fulfilled regardless of external circumstances like force majeure, especially when delays existed prior.

Headnote:(A) Consumer Protection Act, 2019 - Definition of Consumer - Delay in possession of unit purchased by complainant under subvention scheme, on account of unfair trade practices.

(B) Forces of Nature - Claims of force majeure by builder rejected as delay occurred before COVID-19 lockdown.

Facts of the case:
The complainant, who purchased an apartment, alleged significant delays in possession despite substantial payments made. The opposite parties cited various defenses but were unable to justify the failures in service delivery.

Findings of Court:
The complainant was found to be a consumer under the 2019 Act despite ownership of other units; opposition's defenses surrounding exemption from consumer status were dismissed.

Issues: The court addressed whether the delay could be justified by claiming force majeure and the interpretation of consumer status.

Ratio Decidendi: The court asserted that the possession's delay was unjustifiable despite the cited circumstances, affirming that contractual timelines are to be honored in consumer agreements.

Result: Complaint partly accepted with directives for possession, compensation, and penalties for delays.

Table of Content
1. consumer complaint for delay in possession and compensation. (Para 1 , 2)
2. opposite parties' justification for delay discussed and rejected. (Para 3 , 4)
3. court's consideration of contractual obligation and fairness. (Para 10 , 12)
4. final order on possession and compensation. (Para 19)

PER JUSTICE RAJ SHEKHAR ATTRI

This complaint has been filed by the complainant, seeking possession of the unit purchased by her alongwith compensation for the period of delay etc., as she is aggrieved of delay and laches; deficiency in providing service, negligence and adoption of unfair trade practice on the part of opposite parties no.1 to 4. It has been alleged by the complainant in this complaint that despite the fact that she has made payment of substantial sale consideration of Rs.94,42,846.24, for the period from 01.06.2015 to 02.12.2023, yet, the opposite parties no.1 to 4 have not offered possession of the unit for want of development and construction at the project site. Details with regard to the project in dispute; unit purchased by the complainant; payments made by her etc. is given below:-

Project“The Lake”, Omaxe New Chandigarh, District SAS Nagar, Mohali, Punjab
Booked on11.06.2015 on making payment of Rs.5 lacs
Apartment No.TLC/EMERALD-A/FIRST/104
Area of the unit1850 square feet
Total cost91,16,140.00
Amount paid94,42,846.24.00 01.06.2015 to 13.12.2023
Payment planConstruction linked/Subvention Plan
Allotment Letter/ Agreement26.08.2015 (Ann.C-5)
Due date of possession25.02.2019 (42 months i.e. 36 months plus 6 months grace period from the date of execution of agreement, as per clause 40 (a) thereof)
Possession offered or notNot offered
Delay in yearsMore than 6 years which is continuing

It has been stated that for making payment towards price of the said unit, under subvention scheme, the complainant has obtained housing loan from PNB Housing Finance Limited/opposite party no.5 for which the parties entered into tripartite agreement dated 22.09.2015, Annexure C-7 and as such, the opposite parties no.1 to 4 were liable to pay Pre-EMI interest for a fixed period of 34 months i.e. upto delivery of possession of the unit in question. The said subvention period stood extended by the opposite parties no.1 to 4, on account of delay in delivery of possession of the unit. It has been further stated that due to delay in making payment of Pre-EMIs to the PNB Housing Finance Limited the CIBIL score of the complainant has been spoiled and also the actual period of payment of EMIs to be paid by the complainant has been increased from 168 installments to 218 months. Legal notice dated 06.05.2024, Annexure C-29 served upon the opposite parties no.1 to 4 in the matter also did not yield any results. Hence this complaint.

2. Though opposite parties no.1 to 4 appeared through their counsel, yet, written reply was filed only on behalf of opposite parties no.2 to 4, wherein, while admitting the factual matrix of the case with regard to sale of the unit in question to the complainant; execution of allotment letter/agreement etc. took various objections/pleas as under:-

i. the complainant being investor did not fall within the definition of consumer, as she and her husband owned multiple properties;

ii. that the subvention period was initially for 34 months which got extended on mutual understanding that she will not claim delayed compensation for the period of delay;

iii. that the complainant defaulted in making payment toward the unit in question and she had made payment from her own pocket to the tune of Rs.22,64,894.71 only and the remaining amount of Rs.47,02,935/- has been received from opposite party no.5 under subvention scheme

iv. that the opposite parties no.1 to 4 had paid an amount of Rs.38,66,339.45 towards Pre-EMI to opposite party no.5 and are paying the same till date;

v. that an amount of Rs.16,58,813.01 has been adjusted in cost of the unit, towards subvention interest;

vi. that as per clause 40 (a) it was also clearly brought to

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top