STATE CONSUMER DISPUTES REDRESSAL COMMISSION
JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT, MR. PREETINDER SINGH, MEMBER
RESHMA RANI – Appellant
Versus
ROHTAS GOEL, M/S OMAXE CHANDIGARH EXTN DEVELOPERS PVT LTD, PNB HOUSING FINANCE LIMITED – Respondent
CONSUMER COMPLAINT NO. SC/4/CC/90/2024
| Table of Content |
|---|
| 1. complaint filed for possession and compensation due to delays. (Para 1) |
| 2. arguments from both sides regarding delay and consumer rights discussed. (Para 2 , 3 , 11 , 12 , 13) |
| 3. exploration of obligations and responses from both parties in breach situations. (Para 4 , 5) |
| 4. existing delays accountability is outlined with contractual commitments. (Para 9 , 10) |
| 5. final rulings issued covering possession, compensation, and appeals. (Para 19 , 20) |
PER JUSTICE RAJ SHEKHAR ATTRI
This complaint has been filed by the complainant, seeking possession of the unit purchased by her alongwith compensation for the period of delay etc., as she is aggrieved of delay and laches; deficiency in providing service, negligence and adoption of unfair trade practice on the part of opposite parties no.1 to 4. It has been alleged by the complainant in this complaint that despite the fact that she has made payment of substantial sale consideration of Rs.94,42,846.24, for the period from 01.06.2015 to 02.12.2023, yet, the opposite parties no.1 to 4 have not offered possession of the unit for want of development and construction at the project site. Details with regard to the project in dispute; unit purchased by the complainant; payments made by her etc. is given below:-
| Project | “The Lake”, Omaxe New Chandigarh, District SAS Nagar, Mohali, Punjab |
| Booked on | 11.06.2015 on making payment of Rs.5 lacs |
| Apartment No. | TLC/EMERALD-A/FIRST/104 |
| Area of the unit | 1850 square feet |
| Total cost | 91,16,140.00 |
| Amount paid | 94,42,846.24.00 01.06.2015 to 13.12.2023 |
| Payment plan | Construction linked/Subvention Plan |
| Allotment Letter/ Agreement | 26.08.2015 (Ann.C-5) |
| Due date of possession | 25.02.2019 (42 months i.e. 36 months plus 6 months grace period from the date of execution of agreement, as per clause 40 (a) thereof) |
| Possession offered or not | Not offered |
| Delay in years | More than 6 years which is continuing |
It has been stated that for making payment towards price of the said unit, under subvention scheme, the complainant has obtained housing loan from PNB Housing Finance Limited/opposite party no.5 for which the parties entered into tripartite agreement dated 22.09.2015, Annexure C-7 and as such, the opposite parties no.1 to 4 were liable to pay Pre-EMI interest for a fixed period of 34 months i.e. upto delivery of possession of the unit in question. The said subvention period stood extended by the opposite parties no.1 to 4, on account of delay in delivery of possession of the unit. It has been further stated that due to delay in making payment of Pre-EMIs to the PNB Housing Finance Limited the CIBIL score of the complainant has been spoiled and also the actual period of payment of EMIs to be paid by the complainant has been increased from 168 installments to 218 months. Legal notice dated 06.05.2024, Annexure C-29 served upon the opposite parties no.1 to 4 in the matter also did not yield any results. Hence this complaint.
2. Though opposite parties no.1 to 4 appeared through their counsel, yet, written reply was filed only on behalf of opposite parties no.2 to 4, wherein, while admitting the factual matrix of the case with regard to sale of the unit in question to the complainant; execution of allotment letter/agreement etc. took various objections/pleas as under:-
i. the complainant being investor did not fall within the definition of consumer, as she and her husband owned multiple properties;
ii. that the subvention period was initially for 34 months which got extended on mutual understanding that she will not claim delayed compensation for the period of delay;
iii. that the complainant defaulted in making payment toward the unit in question and she had made payment from her own pocket to the tune of Rs.22,64,894.71 only and the remaining amount of Rs.47,02,935/- has been received from opposite party no.5 under subvention scheme
iv. that the opposite parties no.1 to 4 had paid an amount of Rs.38,66,339.45 towards Pre-EMI to opposite party no.5 and are paying the same till date;
v. that
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.