STATE CONSUMER DISPUTES REDRESSAL COMMISSION, ODISHA,C UTTACK FIRST APPEAL NO. 126 OF 2020 (From an order dated 09.9,2020 p M a a s l s k e a d n gi b r y ii n t C h . e C . D N is o tr .1 ic 4 t o C f o 2 n 0 s 2 u 0 m ) e r Disputes Redressal Commission, Sub-Divisional Officer, TPSODL, Malkangiri Electrical Division, At/Po/Ps/Dist- Malkangiri Appellant Vrs.
Prafulla Kumar Swain, aged about 71 years, SloL ate Bharat Swain, Resident of Durgagudi Sahi, Jagannath Temple Street, At/Po/Ps/Dist- Malkangiri Respondent M/s P.K.Tripathy andA ssociates For the appellant For the respondent None PRESENT:
OFFICIATING PRESIDENT, THE HON'BLE SHRI D.K.MOHAPATRA, AND MISS S.L.PATTNAIK, MEMBER DATED THE 12th APRIL, 2024 ORDER SRI D.K.MOHAPATRA,OFFICIATING PRESIDENT is Learned counsel for the appellant is present. Respondents absent on call.
Since the matter 0s of the year 2020, we dispose of the appeal on the basis of materials available on record.
The case of the complainant is that the complainant is consumer
2.
He was No.713101030116.
under the Opp..Party vide Consumer paying the energy charges regularly. Complainant deposited the electricity bill tillA ugust, 2014 and in the month of September, 2014 the meter became defective as such the electricity company issued a provisional bill which was paid by him. It is further stated that on 20.12.2014 some unknown persons identifying themselves as staffs of Southco inspected the meter and took his signature in a blank form. On 22.12.2014 complainant received as how cause notice from the OP mentioning to submit his reply within seven days as to why he shall not pay Rs.45,020/-. The complainant submitted his reply on 23.12.2014 to OPs. Being mentally harassed, the complainant filed the Consumer Complainwt ith prayer to direct the Opp.Party to waive out allt he illegal dues and to pay Rs.50,000/- towards compensation for mental agony and Rs.10,000/- towards litigation expenses.
3. On being noticed, OP filed written version. stating that they had visited the premises of the complainant on 20.12.2014 and found the electricity supply was without any meter for which they issued provisional assessment order U/s 126 of Electricity Act, 2003 and after receipt of objection from complainant final assessment order passed for Rs.13,601/- on 20.1.2017.
4. After hearing the learned District Commission passed the impugned order directing the OP to waive out the arrear amount of Rs.13,601/- being demanded at a belated stage and the complainant was directed to pay the monthly electricity charges regularly.
5. Challenging the impugned order, the appellant- Opp.Party has filed the present appeal.
6 During course of hearing learned counsel for the appellant submitted that on 20.12.2014 inspection was made by the Officers of the Electricity Department. Thereafter on 20.12.2014 provisional assessment order was issued asking the complainant to file his objection. Complainant filed the objection, thereafter final assessment order was passed on 20.1.2017 demanding Rs.13,601/- after a period of two years. Learned counsel for the appellant submitted that the complainant has filed the C.C.No. 202 of 2014 challenging the provisional assessment order, before learned District Commission, which was dismissed by learned District Commission holding that as the dispute relates to the provision Uls 126 of the Indian Electricity Act, 2003 the forum hasno jurisdiction for adjudication. After dismissal of CC No. 202 of 2014 the electricity department issued the bill, as the complainant not paid the electricity dues disconnection notice was sent the to complainant. Challenging the said action of OPs/appellant, complainant has filed the present consumer complaint No. 14 of 2020 in which the learned District Commission has directed to waive out of the final assessment amount which was passed u/s 126 of the Ihdian Electricity Act, 2003. Counsel of appellant submitted that although the learned District Commission has dismissed the C.C.No. 202 of 2014 o