IN THE DELHI STATE CONSUMER DISPUTES REDRESSAL COMMISSION Date of Institution: 19.08.2013 Date of hearing: 28.03.2022 Date of Decision: 18.04.2022 COMPLAINT CASE NO.- 473/2013 IN THE MATTER OF
1. SH. JAIKESH KUMAR, S/o Shri. H.K. Shrivastava
2. SH. HARENDRA KUMAR SHRIVASTAVA, S/o Shri Madan Pd. Verma Both R/o Plot No. 151, Bari Co-operative Colony, P.O Siwandih, Bokaro Steel City, Jharkhand.
(Through: Mr. Kaushal Kishor Mishra, Advocate)
…Complainants VERSUS
1. M/S GARDENIA INDIA LTD., R/o 3rd Floor, Near Shakarpur, Lakshmi Nagar, Delhi- 110092
2. PROPERTY GURU PVT. LTD., C-40, Sector-58, Noida- 201301 (Through: Mr. Pratyush Kumar Yadav Advocate)
… Opposite Parties CORAM:
HON’BLE DR. JUSTICE SANGITA DHINGRA SEHGAL (PRESIDENT)
HON’BLE SH. RAJAN SHARMA, MEMBER (JUDICIAL)
Present: None for the Parties.
PER: HON’BLE DR. JUSTICE SANGITA DHINGRA SEHGAL, PRESIDENT JUDGMENT
1. The present Consumer Complaint has been filed before this Commission under Section 17 of the Consumer Protection Act, 1986, seeking the following reliefs:-
“It is therefore most respectfully prayed that in the interest of justice, equity and fair play and for the reasons mentioned in the present Complaint petition, this Hon'ble commission may be most graciously be pleased to the respondents to restore the flat of the complainants cancelled by the respondents on the previous terms and conditions. Any other relief which this Hon'ble Commission may deem fit may also be passed in favour of the complainants and against the respondents.”
2. Brief facts necessary for adjudication of the present complaint are that the Complainants booked a Dwelling unit in the project of the Opposite Parties namely “Gardenia Gateway” situated at Plot No. 9, Sector-75, Noida (U.P.) and made an initial payment of Rs. 1,00,000/- to Opposite Parties. Thereafter, a payment of Rs. 2,44,250/- vide cheque dated 02.02.2011 was made by the Complainants to Opposite Parties. To fulfill the further demands of Opposite Parties, complainants had enquired about home loan from different banks and the approval was given by the bank (LICHFL) after providing some pre-requisite documents. For the approval of the said loan, Complainant needs to submit the approval code of the said project in the bank, which was provided by the Opposite Party no. 1 on 18.04.2012. Thereafter, the bank asked the complainants to submit the Allotment Letter and Builder Buyer Agreement for the sanctioning of loan. In response of which, an unsigned Allotment Letter and Builder Buyer Agreement were issued by the Opposite Parties to the complainants.
3. While reviewing the Allotment Letter and Builder Buyer Agreement, the Complainants found some prima facie errors in it and intimated the Opposite Parties about those errors and requested to rectify these before executing the same. However, the opposite party no. 1 failed to do the said rectifications. Therefore, the Complainants had sent a legal notice dated 01.08.2012 to the Opposite Parties demanding them to amend the allotment letter but was of no avail.
4. The complainants further stated that despite the numerous requests to rectify the errors in the allotment letter, the Opposite Parties had cancelled their allotted unit unilaterally.
5. Thus, left with no other option, alleging deficiency of service and unfair trade practice on the part of Opposite Parties, the Complainants approached this Commission.
6. The Opposite Party no. 1 has contested the present case and has raised some preliminary objections as to the maintainability of the complaint case. The counsel for the Opposite Party no. 1 submitted that the Complainants are not consumer within the provisions of the Consumer Protection Act, 1986 as the plot was purchased for investment i.e. for commercial purposes. The counsel for Opposite Party no. 1 further submitted that the present complaint is not maintainable because it is beyond the Territorial Jurisdiction of this Commission.
7. The counsel for Opposite Party no. 1 further submitted in w