1. Sri Naren Rama Krishnan – Appellant
Versus
1. M/s.Aparna Shelters Private Ltd. – Respondent
SC/36/CC/86/2016



BEFORE THE TELANGANA STATE cONSUMER DISPUTES REDRESSAL COMMISSION:HYDERABAD (ADDITIONALB ENCH)

C.C.86/2016 Between:

1.Sri Naren Ramakrishnan, S/o.Sri N.Ramakrishnan, Aged about 37 years, Occ: Service, R/o.E-25, Aparna Kanopy Lotus, Kompally, Hyderabad 500 014.

2. Smt. Arunasree Swapna, W/o.Sri Naren Ramakrishnan, Aged about 35 years, Occ: Service, R/o.E-25, Aparna Kanopy Lotus, ..Complainants Kompally, Hyderabad 500 014.

And

1.M/s.Aparna Shelters Private Limited, A company registered under Companies Act, 1956, Having its registered office at # 802, Astral Heights, D.No.6-3-352/2 & 3, Road No. 1, Banjara Hills, Hyderabad, Represented by its Director Bommi Reddy Venu Gopal Reddy.

2. D.S.Prasad , Former Director of M/s.Aparna Shelters Pvt. Ltd., Aparna Shelters Pvt. Ltd.,# 802, Astral Heights, D.No.6-3-352/2 & 3, Road No. 1, Banjara Hills, Hyderabad.

3. P.V.R.Prasad, Manager, Aparna Maintenance Services, # 802, Astral Heights, D.No.6-3-352/2 & 3, Road No. 1, Banjara Hills, Hyderabad.

M/s.P. Vikram.

Counsel for the Complainants Counsel for the Opposite Parties: M/s.M.V.Durga Prasad.

Hon'ble Sri V.V.Seshubabu, Member (J), CORAM And Hon'ble Smt.R.S.Rajeshree, Member (NJ).

TUESDAY, THE ELEVENTH DAY OF OCTOBER, TWO THOUSAND TWENTY TWO.

Order (Per Hon'ble Sri V.V.Seshubabu, Member (J), ****

01) The complaint is filed u/s.17(1)(a)(i) of the Consumer Protection Act,1986 seeking the reliefs of directing the opposite parties to repay Rs.2,58,000/ with interest 24% p.a. with joint and several liability from the date of handing over of the property till realization, to pay Rs.50 lakhs for the damages for devaluation of the property, mental agony and undue hardship sustained by the complainants and to award costs.

02). The brief averments of the complaint are that the complainants 1 & 2 are the husband and wife and opposite party no.2 is the Dircctor and opposite party no.3 is the Maintenance Service Manager under opposite party no. 1; that the complainants having impressed with the brochure and other details of the project styled as Aparna Kanopy Lotus with a total of 92 plots to be constructed in an extent of land admeasuring 50,011.79 sq. Mtrs. purchased plot no.25 admeasuring 200.28 sq.yards; that prior to Agreement dt.29.11.2013, they have paid Rs.13,81,120/-

by way of two cheques; that the total cost of the villa was at Rs.69,05,600/- and as per the Agreement of Sale they have to pay balance amount of Rs.55,24,480/- as per the schedule; that as per the Schedule-D of the Agreement of Sale, the opposite party no.1 promised to provide Club House and amenities nine in number like 1). Gymnasium, 2). Health Club, 3) Library and ATM Arca, 4). Multi purpose hall, 5). Indoor Games/sports , 6). Yoga/Aerobics area and that under head Club House and Amenities like 1). Swimming Pool, 2) Snooker/Billiards, and 3). Play Area for children; that on 12.3.2014, the opposite party no.1 executed registered Sale Deed in favour of the complainants; that on the same day both sides have entered into an Agreement of Construction, as per the same, the villa as described in schedule B shall be constructed; that on 22.7.2014 the opposite party no.1 declared that the villa has been completed in all respects as per the terms and conditions and specifications and delivered possession; that the total consideration was paid by that day; that the opposite party no.1 not handed over the possession as agreed upon in the Agreement of Sale, Sale Deed or the Construction Agreement for which the opposite party no.1 is liable to pay the rent amount at Rs.5/- per sq.ft. till possession was delivered; that the complainants after taking delivery of possession and having lived in Villa for a considerable time of 10 months raised the querries regarding the maintenance, infrastructure, Club House and amenities, vide E-mail dt.22.5.2015 for which a reply E-mail was sent on 1.6.2015 stating that they are sorting out the querries, that the correspondence wenton between both sides as referred under A