2025 Supreme(Online)(SCDRC) 32437
STATE CONSUMER DISPUTES REDRESSAL COMMISSION, PUNJAB, CHANDIGARH.
Date of institution : 16.01.2024 Reserved On : 18.08.2025 Date of decision : 01.09.2025
United India Insurance Company Limited, Railway Station Road, Sangrur, 148001, through its Divisional Manager.
Now through Manager, United India Insurance Company Limited, Surya Tower-108, 3rd Floor, The Mall Road, near Fountain Chowk, Ludhiana-141001.
….Appellant/Opposite Party Versus BTC Stone Supplier, Village Burj, Tehsil Malerkotla, District Sangrur, through its Proprietor, Nirbhai Singh son of Balbir Singh resident of Village Burj, Tehsil Malerkotla, District Sangrur, now Malerkotla.
….Respondent/Complainant
First Appeal under Section 41 of the Consumer Protection Act, 2019 against the order dated 08.08.2023 passed by the District Consumer Disputes Redressal Commission, Malerkotla.
Quorum:-
Hon’ble Mrs. Justice Daya Chaudhary, President
Mr. Vishav Kant Garg, Member
(JUSTICE DAYA CHAUDHARY)
PRESIDENT
(VISHAV KANT GARG)
MEMBER
September 01, 2025.
(Gurmeet S)
1) Whether Reporters of the Newspapers may be allowed to see the Judgment? Yes/No
2) To be referred to the Reporters or not? Yes/No
3) Whether Judgment should be reported in the Digest? Yes/No Present:-
For the Appellant : Sh. Ram Avtar, Advocate
For the Respondent : Sh. Barjinder Singh, Advocate
(Through VC)
JUSTICE DAYA CHAUDHARY, PRESIDENT
Appellant/OP i.e. United India Insurance Company Limited through its Divisional Manager has filed the present Appeal under Section 41 of the Consumer Protection Act, 2019 to challenge the order dated 08.08.2023 passed by the District Consumer Disputes Redressal Commission, Malerkotla (in short, “the District Commission”), whereby the Complaint filed by the Respondent/Complainant had been partly allowed.
2. It would be apposite to mention here that hereinafter the parties will be referred, as had been arrayed before the District Commission.
3. Briefly, the facts of the case, which are necessary for disposal of the present Appeal are that the Respondent/Complainant filed the Complaint before the District Commission with the following prayer:
i) The OP be directed to pay the claim amount of ₹4,33,027/- along with interest at the rate of 18% from the date of accident till its realization;
ii) To pay compensation of ₹30,000/- for causing mental agony and harassment; and iii) To pay ₹11,000/- towards litigation expenses.
4. Upon issuance of notice in the said Complaint, the OP had appeared before the District Commission through Counsel and filed the written reply, wherein certain preliminary objections were raised. All other averments as made in the Complaint were denied. It was prayed that the Complaint be dismissed.
5. By considering the contents of the Complaint and reply thereof filed by the OP and after going through the evidence available on the file, the Complaint was partly allowed by the District Commission vide impugned order dated 08.08.2023. The relevant portion of said order as mentioned in Para-11 & 12 is reproduced as under:
“11. In view of above said discussion, Complaint of the Complainant is partly allowed to the effect that he is entitled to 75% of Rs.4,12,357/-, which is assessed by the surveyor, whereas Complainant demanded Rs.4,33,027/- as repair amount but the report of the surveyor is not challenged by the Complainant. Therefore, net loss amount assessed by the surveyor is final.
12. So, OP is directed to pay 75% of the assessed amount i.e. Rs.4,12,357/- within 45 days after receiving the certified copy of this order failing which they are liable to pay interest at the rate of 6% from the date of order till realization.
Further, OP is directed to pay Rs.20,000/- lump-sum as mental tension and litigation expenses, as genuine claim of the Complainant is repudiated by the OP which the Complainant is unnecessary dragged into unwanted litigation. Free certified copy of this order be sent to the parties, as per rules. The file be indexed & consigned to the Record Room.”
6. Said order dated 08.08.2023 passed by the District Commission has been challenged by the Appellant/OP by way of filing the present Appeal by raising a number of arguments.
7. There was a delay of 79 days in filing of the Appeal. Misc. Application No.121 of 2024 was filed for condonation of delay, which was supported by an affidavit. Said application was allowed vide order dated 19.03.2024 and the delay in filing of the Appeal was condoned subject to cost of ₹3,000/- to be deposited in the Consumer Legal Aid Account of this Commission before the date fixed.
8. Mr. Ram Avtar, learned Counsel for the Appellant/OP has submitted that the order passed by the District Commission is contrary to facts and record as well the documentary evidence available on the record. Learned Counsel has also submitted that the District Commission had failed to appreciate the material fact that the truck was being used in violation of the terms and conditions of the insurance policy, as there was no valid Route Permit at the