##PAGE1##

STATE CONSUMER DISPUTES REDRESSAL COMMISSION KERALA REVISION PETITION NO. SC/32/RP/54/2025 (Against the Order dated 4th June 2025 in Appeal DC/566/CC/24/798 of the District Consumer Disputes Redressal Commission Trissur)

WITH SC/32/IA/712/2025 (FOR GRANT OF STAY)

CALETAL REALTY PVT LTD BUSINESS ADDRESS - REP BY ITS MANAGING DIRECTOR AKASH ANANDAYYANTHOLE , THRISSUR,KERALA.

AKASH ANAND S/o. SADANADAN PRESENT ADDRESS - KOTTIYATTIL HOUSE , THRISSUR , AYYANTHOLE.P.O , THRISSUR,KERALA.

.......Petitioner(s)

Versus MADHU V.N PERMANENT ADDRESS - A-204, KESAV SRUSHTI C.H.S, NEW LINK ROAD, CHINCHOLBHANDARA,MAHARASHTRA.

LEKHA MADHU NAIR PERMANENT ADDRESS - A-204, KESAV SRUSHTI C.H.S, NEW LINK ROAD, CHINCHOLBHANDARA,MAHARASHTRA.

DEEPAK MADHU NAIR PERMANENT ADDRESS - A-204, KESAV SRUSHTI C.H.S, NEW LINK ROAD, CHINCHOLBHANDARA,MAHARASHTRA.

.......Respondent(s)

BEFORE:

HON'BLE MR. JUSTICE SRI.B.SUDHEENDRA KUMAR , PRESIDENT HON'BLE MR. SRI.AJITH KUMAR.D , JUDICIAL MEMBER SRI.RADHAKRISHNAN.K.R , MEMBER FOR THE PETITIONER:

NEMO FOR THE RESPONDENT:

NEMO DATED: 25/11/2025

ORDER

KERALA STATE CONSUMER DISPUTES REDRESSAL COMMISSION VAZHUTHACAUD, THIRUVANANTHAPURAM REVISION PETITION No.54/2025 ORDER DATED: 25.11.2025 (Against the Order in I.A.No.296/2025 in C.C.No.798/2024 on the files of DCDRC, Thrissur)

##PAGE2##

PRESENT:

HON’BLE JUSTICE SRI. B. SUDHEENDRA : PRESIDENT KUMAR SRI. AJITH KUMAR D. : JUDICIAL MEMBER SRI. K.R. RADHAKRISHNAN : MEMBER REVISION PETITIONERS:

1. Caletal Realty Pvt. Ltd. represented by its Managing Director, Akash Anand, Kottiyattil House, Ayyanthole P.O., Thrissur – 680 003

2. Akash Anand, Kottiyattil House, Ayyanthole P.O., Thrissur – 680 003 (by Adv. Sandeep T. George)

Vs.

RESPONDENTS:

##PAGE3##

1. Madhu V.N., A-204, Kesav Srushti C.H.S., New Link Road, Chincholi, Malad Dely, Mumbai, Maharashtra – 400 064

2. Lekha Madhu Nair, A-204, Kesav Srushti C.H.S., New Link Road, Chincholi, Malad Dely, Mumbai, Maharashtra – 400 064

3. Deepak Madhu Nair, A-204, Kesav Srushti C.H.S., New Link Road, Chincholi, Malad Dely, Mumbai, Maharashtra – 400 064 (by Adv. V.R. Swaminathan)

O R D E R

HON’BLE JUSTICE B. SUDHEENDRA KUMAR : PRESIDENT The revision petitioners are the opposite parties in C.C.No.798/2024 on the files of the District Consumer Disputes Redressal Commission, Thrissur (for short, ‘the District Commission’).

2. The complainants filed a complaint before the District Commission alleging deficiency in service and unfair trade practice against the opposite parties in connection with the construction of a villa. During the pendency of the complaint before the District Commission, the complainants filed I.A.No.296/2025, praying for permitting the complainants to complete the construction. The District Commission, as per order dated 04.06.2025, allowed I.A.No.296/2025, against which this revision petition has been filed.

##PAGE4##

3. Heard both sides. Perused the records.

4. It is not disputed that the construction is not yet complete. The complainants have prayed for permitting them to complete the construction of the villa. The opposite parties alleged that the construction was not completed as the payment was not made by the complainants. To show the present situation of the villa, including the extent of construction, there is a report submitted by the expert appointed by the District Commission on the request of the complainants.

5. The only contention raised by the learned counsel for the revision petitioners before this Commission is that if the construction is permitted to be completed, some of the materials kept in the premises of the complainants will be utilised by the complainants for the construction. However, no such contention was taken by the revision petitioners in the counter filed by the revision petitioners before the District Commission. In the said circumstances, we are not inclined to issue any direction to that effect. However, since the construction is not complete, there is no harm in permitting the complainants to complet