2026 Supreme(Online)(SCDRC) 1845

STATE CONSUMER DISPUTES REDRESSAL COMMISSION
Joyeeta Mondal – Appellant
Versus
Maa Durga Construction & Others – Respondent
SC/19/CC/667/2019



Petitioner Advocates:Mr. Dipankar Naskar, Mr. T.Chatterjee ,Respondent Advocate: Mr. Shamim Ahmed, Ms. Asha Ghosh, Mrs. Paramita Adhikary,Mrs. Paramita Adhikary, Ms. Asha Ghosh,Mr. Shamim Ahmed, Ms. Asha Ghosh,Ms. Sanhita Shaoo.

STATE CONSUMER DISPUTES REDRESSAL COMMISSION WEST BENGAL CONSUMER COMPLAINT NO. SC/19/CC/667/2019 Joyeeta Mondal PRESENT ADDRESS - W/o Biswajit Mondal, Kanjial Para Rathtala, P.O. & P.S. - Rajarhat, Dist.

North 24 Pgs., Kolkata - 700 135.,WEST BENGAL.

.......Complainant(s)

Versus Maa Durga Construction & Others PRESENT ADDRESS - Vill. - Reckjoani, P.O. & P.S. - Rajarhat, Dist. North 24 Pgs., Kolkata - 700

135.,WEST BENGAL. Pradip Narayan Bose PRESENT ADDRESS - S/o Lt. Surendra Narayan Bose, Vill. - Bhatenda, P.O. & P.S. - Rajarhat, Dist. North 24 Pgs., Kolkata - 700 135.,WEST BENGAL.

Soma Bairagya PRESENT ADDRESS - W/o Kaushik Bairagya, Vill. - Reckjoani, P.O. & P.S. - Rajarhat, Dist.

North 24 Pgs., Kolkata - 700 135.,WEST BENGAL.

Mukul Sen Gupta PRESENT ADDRESS - S/o Lt. Manotosh Sen Gupta, Kanjial Para, P.O. & P.S. - Rajarhat, Dist.

North 24 Pgs., Kolkata - 700 135.,WEST BENGAL.

Smt. Srabani Dasgupta PRESENT ADDRESS - W/o Lt. Gopal Dasgupta, Kanjial Para, P.O. & P.S. - Rajarhat, Dist. North

24 Pgs., Kolkata - 700 135.,WEST BENGAL.

.......Opposite Party(s)

BEFORE:

HON'BLE MR. AJEYA MATILAL , JUDICIAL MEMBER HON'BLE MRS. SAMIKSHA BHATTACHARYA , MEMBER FOR THE COMPLAINANT:

Joyeeta Mondal, Mr. Dipankar Naskar, Mr. T.Chatterjee (Advocate)

FOR THE OPPOSITE PARTY:

Maa Durga Construction & Others, Mr. Shamim Ahmed, Ms. Asha Ghosh, Mrs. Paramita Adhikary (Advocate) DATED: 10/03/2026

ORDER

Samiksha Bhattacharya, Member The instant complaint has been filed under Section 17(1)(a)(i) of C.P Act of 1986 (wrongly written as under Section 12 read with Section 13)

alleging deficiency in service against the OPs.

The case of the complainant, in brief, is that the OP No. 1 is a partnership firm and OP No.2 is the partner of OP NO.1 and OP No. 3 is the another partner in the setup of OP no.1. OP Nos. 4 and 5 are the land owners of the premises in question as per Joint Venture Agreement entered by and between the OP Nos. 1, 2 & 3 and OP Nos. 4 & 5.The Complainant was in search of residencial flats for their joint family and accordingly OP Nos. 2 and 3 approached the Complainant and her husband for taking flats in their project namely ‘CHAR ADHAY” upon the land comprising about 5 cottah 14 chittack land area in New Town area as well as in Rajarhat Bishnupur 1 no. GRAM PANCHAYET, 1, Mouja – Rekjuani, J.L No. – 13, HAL TOUJI NO. 10 in Government of west Bengal through District Collectorate of North 24 Parganas in L.R Dag No. 218.

The complainant entered in to agreements for sale on 20.11.2016 and 13.02.17 with the OPs. The Complainant had earlier been authorized by 2 other persons and / or near relatives for entering in to two other agreements in issue with these OPs. Out of these three flats the Complainant is entitled to get one flat i.e ‘ 1A’ On the first floor of the subject premises and other two relatives were subjected for two other flats. The consideration of the flat number being 1A has been settled at Rs. 20,05,000/-. The consideration of flat No. 2B was settled at Rs. 20,05,000/- and the consideration of flat being number 3C was settled at Rs. 19,20,000/-. Out of total consideration of Rs.59,30,000/- the Complainant paid Rs. 16,00,000/- to the OPs as an advance consideration and rest amount of Rs. 43,30,000/- was due as rest consideration.

As per agreement for sale it was agreed upon that the flats would be delivered within two (2) years from the date of execution of each agreement upon receipt of rest consideration money. However, the time has expired in respect of two agreements in November 2018 and in respect of other agreement in February 2019. The Complainant was / is keen to render rest consideration amount and repeatedly approached the OP Nos. 2 and 3 verbally and also in writing for receiving the rest consideration by the OP Nos. 1,2 &3 and to handover the necessary possession and to execute the deed conveyance. But, no positive reply has come to the complainant. Upon expiry of agreed scheduled time the complainant sent two letters in April 2018 and

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top