SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(SCDRC) 2722

STATE CONSUMER DISPUTES REDRESSAL COMMISSION
Padma Pandey, Presiding Member, Rajesh K. Arya, Member
Parminder Singh Bakshi – Appellant
Versus
WTC Noida Development Company – Respondent
Complaint case No. 102 of 2025



Advocates:
For the Appellants/Petitioners: Gurnoor Singh
For the Respondents: Ishtneet S. Bhatia

Statutory authorities controlling housing projects are 'service providers' under consumer law when their actions impact purchaser investments. Furthermore, one-sided agreement clauses placing the entire burden of delay or default on the consumer while insulating the developer constitute unfair trade practices and are unenforceable.

Headnote:(A) Consumer Protection Act, 2019 - Deficiency in service - Unfair trade practice - Refund of deposit - Developer failed to deliver possession within stipulated period and failed to provide mandatory approvals, while collecting majority of sale consideration - Such actions constitute deficiency in service and unfair trade practice. (Paras 8, 10, 25, 28)

(B) Consumer Protection Act, 2019 - Statutory Development Authority - Liability - While the authority is a public body exercising statutory powers, its actions (resumption of project site and forfeiture of funds after receiving project assets) involve the interests of the consumer - The authority cannot claim a lack of privity of contract to escape accountability when it assumes control over assets funded by consumers - Violation of principles of natural justice by failing to provide notice to affected consumers before resuming project land. (Paras 14, 15, 17, 19)

(C) Contract Law - Unfair terms - Clauses in a developer-buyer agreement that impose penal interest on the allottee for defaults while providing no corresponding compensation for the developer’s default/delay are one-sided, arbitrary, and constitute an unfair trade practice, rendering such terms non-binding. (Paras 27, 28)

Facts of the case:
The complainant booked a commercial unit in a development project, paying 95% of the total consideration. The developer failed to initiate construction or obtain requisite statutory approvals. The site was subsequently cancelled and resumed by a public development authority due to the developer's default in payment of dues. The complainant sought a refund of the deposited amount along with interest and compensation, citing the developer's failure to deliver and the authority’s unilateral action regarding the project site.

Findings of Court:
The commission found that the developer provided no evidence of construction or compliance, justifying an adverse inference. Further, the public development authority’s plea of lack of contract was rejected, as its statutory actions directly impacted the consumers' investments. It was held that clauses burdening only the consumer are unconscionable and invalid. The complainant is entitled to a refund with interest from the date of deposit.

Issues: Whether the developer committed a deficiency in service by failing to deliver the unit and whether the public authority is liable to the complainant despite the lack of direct privity of contract.

Ratio Decidendi: Statutory authorities are service providers under consumer law when their actions, such as resuming a site developed with public funds, directly affect consumer rights. Unilateral or one-sided contract terms are inherently unfair, and refund claims must be restitutionary, covering the loss of investment opportunities and price escalation.

Result: Complaint partly allowed. The opposite parties are directed to refund the principal amount with interest at 9% per annum from the date of deposit, plus compensation for mental agony and litigation costs.

PER MRS. PADMA PANDEY, PRESIDING MEMBER

The facts, in brief, are that allured by the tall claims and representations of the Opposite Parties, the complainant, booked a unit (Office Space) i.e. Unit No.830, 8th Floor in Tower-C having super area measuring 500 sq. feet in the year 2016 in the WTC Chandigarh Aerocity, Mohali project for a total consideration of ₹33,69,680/-, out of which he paid ₹31,61,828/- (about 95%) as per ledger/payment detailed (Exhibit C-2). It has been stated that the complainant, being a retiree from a repudiated private Bank, had booked the said unit for the purpose of earning his livelihood by means of self-employment as retirement plan. The opposite parties executed a Developer-Buyer Agreement dated 27.04.2016, Exhibit C-1. As per Clause 4.5 of the Developer-Buyer Agreement, the possession of the unit in question was to be offered within a period of 48 months from the date of execution of the said agreement plus additional grace period of 6 (six) months. After payment of substantial amount, the complainant kept on visiting the Mohali office site of the opposite parties No.1 to 4 to monitor on ground situation but to his disappointment, at every visit, he could not see any construction work being initiated and on enquiring about the current status, the opposite parties time and again promised that things are under control and on track, thereby giving assurance of the completion of the project within the guaranteed time period as per the agreement. In December 2020, the complainant met with the opposite parties at Mohali site office and expressed his dismay since the project had not witnessed any development at all, however, he was assured that things would be on track by March 2021. The complainant consistently sought details of mandatory approvals including RERA extensions, GMADA dues, building plans and other sanctions but the opposite parties failed to provide any such documents indicating that no approvals existed at the time of booking. In the month of April 2023, the complainant discovered that GMADA had cancelled the entire site for non-payment of dues by the opposite parties and that even the opposite parties’ writ petition (CWP No. 21141/2023) had been dismissed by the Hon’ble High Court. Audit reports further revealed siphoning of funds exceeding ₹77 crores by the opposite parties to other projects. Despite repeated requests, neither possession was offered nor refund has been provided, causing severe mental, physical and financial harassment to the complainant. It has been averred that the opposite parties’ conduct of collecting money without approvals, misrepresenting project status, violating RERA mandates, failing to update statutory information and delaying construction, constitutes grave “deficiency in service” and “unfair trade practice,” as recognized in precedents such as Kamal Sood vs. DLF Universal Ltd. and Emaar MGF Land Ltd. vs. Karnail Singh. Hence, this complaint has been filed by the complainant seeking directions to the opposite parties to refund the amount of ₹31,61,828/- along with interest @18% per annum from the respective dates of deposits till realization; to pay compensation of ₹5,00,000/- for causing financial loss as also the escalation in prices to the complainant, for causing mental and physical harassment and agony to the complainant on account of delay in allotment and possession and for selling the Unit without obtaining any approval/sanctions for the development of the project and deficiency of service on the part of Opposite parties in not delivering possession of the Unit till date inspite of receiving more than 95% of the total sale consideration; to pay litigation expenses to the tune of ₹2,00,000/- and any other relief which this Hon'ble State Commission may deem fit be also granted to the complainant.

2] It is pertinent to mention here that at the time of admission hearing, Counsel for the complainant submitted that various clauses of the agreement dated 2

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top