SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(SCDRC) 3099

STATE CONSUMER DISPUTES REDRESSAL COMMISSION
Sangita Dhingra Sehgal, President, Bimla Kumari, Member
H.M. Vyas – Appellant
Versus
Imperial Housing Ventures Pvt. Ltd. – Respondent
COMPLAINT NO. 26/2019



Advocates:
For the Appellants/Petitioners: Ravi Prabha
For the Respondents: Anirudh Jamwal, Vikas Gupta

Failure to handover possession of a property within the contractually stipulated period constitutes a continuous deficiency in service, granting the purchaser a recurring cause of action for compensation. The burden of proving a transaction is for a commercial purpose lies solely with the service provider.

Headnote:(A) Consumer Protection Act, 1986 - Sections 17(2), 24A, 2(1)(g) and (o) - Deficiency of service - Real estate - Delay in delivery of possession - Limitation period - The failure to deliver possession within the stipulated contractual period creates a recurring cause of action, hence a complaint is not barred by limitation (Paras 18, 19).

(B) Consumer - Determination of status - Commercial purpose - The onus of proof lies on the developer to establish that the purchaser is involved in the business of buying and selling properties for profit; mere ownership of more than one property does not render the purchase commercial (Paras 21-24).

(C) Territorial Jurisdiction - The presence of a registered office within the jurisdiction of the commission confers the necessary authority to entertain the complaint under Section 17(2)(a) (Paras 28, 29).

(D) Compensation - Measure - Where a developer fails to deliver possession within the agreed timeframe, the purchaser is entitled to interest as a measure of restitution for the delay, coupled with compensation for mental agony and harassment (Paras 31, 32, 41).

Facts of the case:
The complainants entered into an agreement for the purchase of an apartment, payment for which was largely completed under a construction-linked plan. The developer failed to handover possession within the contractually stipulated time, despite receiving approximately 90% of the sale consideration. The developer later raised demands for interest on delayed payments, increased area charges, and taxes, which the complainants contested as illegal.

Findings of Court:
The court held that the delay in providing possession constituted a continuing deficiency in service. The developer failed to substantiate any force majeure event. The claims for interest on delayed payments and maintenance charges prior to the actual delivery of possession were deemed unsubstantiated and unjust.

Issues: Whether the complaint was time-barred; whether the purchase was for a commercial purpose; whether the commission had territorial jurisdiction; and whether the developer was deficient in service due to construction delays.

Ratio Decidendi: The court maintained that failure to handover possession is a continuous wrong. Furthermore, once an agreement for sale is signed, the stipulated timelines are binding. If the developer fails to meet these, they are liable for compensation for the delay, as this breach of contract significantly impacts the legitimate expectations of the purchaser.

Result: Complaint allowed with directions for compensation, interest payments, and execution of title deeds.

Table of Content
1. failure to deliver flat possession within contractually agreed timeframe constitutes default. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. respondent may raise maintainability objections regarding limitation and jurisdiction. (Para 7 , 8)
3. failure to provide possession is a continuous, recurrent cause of action. (Para 16 , 17 , 18 , 19)
4. onus of proof for commercial purpose rests on the developer. (Para 20 , 21 , 22 , 23 , 24)
5. location of registered office establishes territorial jurisdiction for consumer complaints. (Para 25 , 26 , 27 , 28 , 29)
6. developer is liable for deficiency if possession is delayed without valid force majeure justification. (Para 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38)
7. court grants interest-based compensation for delayed possession and litigant costs. (Para 39 , 40 , 41 , 42 , 43 , 44 , 45)

PER: HON’BLE JUSTICE SANGITA DHINGRA SEHGAL, PRESIDENT

JUDGMENT

1. The present Complaint has been filed by the Complainants under Section 17 of the Consumer Protection Act, 1986 before this Commission alleging deficiency of service and unfair trade practices on the part of the Opposite Parties and have prayed for the following relief :-

i. Direct the OP No. 1 to deliver the possession of the fully furnished Unit No. ST-01-22-18 complete in all respects to the complainants immediately alongwith the designated parking with all fixtures therein as assured at the time of booking and execute all the accessory and required title documents in respect of the said Flat in favor of complainants for which Complainants are ready and willing to pay the balance amount of sale consideration agreed at the time of booking of the flat.

ii. Direct the OP No. 1 to withdraw the demand letters dated 20.06.18 & issue revised demand letter in terms of above prayer clause (a) a excluding the demand of interest, deducting the PLC already levied, CGST/SGST, maintenance charges demand for increased area of the unit and other illegal demands

iii. Direct the OP No. 1 to pay interest @18% per annum on Rs. 15,45,441/- being the amount deposited by the complainants with the OP No. 1 from the date when the OP No. 1 was required to hand over the possession as per law i.e. 28.07.13 till the actual date of handover of possession of the flat complete in all respect by the OP No. 1 to the complainants.

iv. Direct the OP-1 to provide & place on record all the documents since the date of booking of the flat by the complainants including the sanction of the building plan of the tower for “T” shape; revised sanction of the plan enhancing the number of floors and changing the shape of the tower from “T” to “I” causing the change in the location of the flat of the complainants & reducing the proportional share in the land underneath the tower and the entire correspondence for getting the revision of the plan; copy of the form “C” & “D” and the objections raised for occupancy certificate raised by the concerned authorities; copy of the occupancy certificate; and the details of FAR of the project including the Tower under reference,

v. Pass an award of Rs. 5,00,000/- by way of compensation for deficiency in services & adopting unfair trade practice causing permanent loss to the complainants on account of poor quality of material & workmanship, change of location of the unit from park facing to other, increasing the number of floors thereby reducing the complainants’ proportionate share in the land title underneath the tower.

vi. Pass an award of Rs. 4,00,000/- by way of compensation for causing mental agony and harassment caused to the complainants by the OP No. 1.

vii. Award cost of the present complaint in favor of the complainants and against the OP No. 1

viii. Any other relief which this Hon’ble Commission deems fit/appropriate in the facts & circumstances.

2. The brief facts necessary for the adjudication of the present complaint are that the Complainants vide application form dated 02.07.2010, applied for the allotment of a studio apartment

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top