2026 Supreme(Online)(SCDRC) 4617
STATE CONSUMER DISPUTES REDRESSAL COMMISSION
Rajes Guha Ray, Judicial Member, Santanu Saha, Member
MR. KAMAL KISHOR CHOWDHURY – Appellant
Versus
M/s. Soumita Projects Pvt. Ltd. & Others – Respondent
CONSUMER COMPLAINT NO. SC/19/CC/1053/2019
Important Points
Subject
Consumer Protection - Real Estate / Housing
Act Referred
Headnote
(B) Parties - Non-joinder - Financial institutions or marketing agents not necessary parties where the primary obligation of construction and delivery lies with the developer. (Para 6)
(C) Contractual obligations - Waiver of timelines - Acceptance of delayed payments by developer without termination of contract acts as a waiver of strict timelines and precludes late reliance on such clauses. (Para 6)
Facts of the case:
Complainant booked a residential flat in July 2014, paid approximately 95% of the consideration, but the developer failed to hand over possession within the 36-month period plus six months grace period as specified in the Agreement for Sale. The developer cited payment irregularities, while the complainant highlighted severe financial hardship and lack of possession despite full payment.
Findings of Court:
The commission found the developer guilty of deficiency in service and unfair trade practices. It held that the complainant is a consumer and the developer cannot cite minor payment delays as a reason to withhold possession after accepting subsequent payments.
Issues: Whether the complainant is a consumer, whether the complaint is bad for non-joinder of parties, and whether the developer is liable for compensatory damages for delay in possession.
Ratio Decidendi: A developer cannot indefinitely withhold possession of a flat while continuing to accept payments from the allottee and then retrospectively claim breach of contract. Failure to deliver possession within the promised period constitutes a deficiency in service warranting compensation.
Result: Complaint allowed in part; developer directed to deliver possession, execute conveyance, and pay interest on delayed compensation along with litigation costs.
For the Appellants/Petitioners: Kamal Kishor Chowdhury, Binota Roy, Abhijit Mazumder, Mousumi Sarkar
For the Respondents: Prasanta Banerjee
| Table of Content |
|---|
| 1. overview of complaint, parties involved, and the background of the disputed real estate transaction. (Para 1 , 2) |
| 2. arguments regarding payment defaults, delivery timelines, and the developer's contractual defenses. (Para 3 , 4) |
| 3. legal analysis on consumer status, non-joinder, and deficiency in service for delayed property possession. (Para 5 , 6) |
| 4. final orders mandate possession, registration, compensation, and litigation costs. (Para 7) |
ORDER
Hon’ble Mr. Santanu Saha, Member
1. Genesis of the Case
This complaint under Section 17 of the Consumer Protection Act, 1986 has been instituted by the complainant alleging deficiency in service and unfair trade practice on the part of Opposite Party No. 1, the developer of a residential housing project, in failing to hand over possession of a residential flat booked by the complainant within the contractually stipulated time and in failing to compensate the complainant for the prolonged delay.
The complaint was originally filed against OP No. 1 (Developer), OP Nos. 2 to 7 (owners/vendors of the land), and OP Nos. 8 to 23 (confirming parties). During the course of proceedings, the matter proceeded ex parte against OP Nos. 2 to 23. Contest has been made only by OP No. 1.
We have heard the learned Advocates appearing for the complainant and OP No. 1, perused the pleadings, evidence on affidavit, documentary annexures, written versions, written notes of argument and the records.
2. Facts in Brief
The complainant applied for allotment of a flat on 21.07.2014 and paid booking/application money of Rs.1,04,121/- on 28.07.2014. Thereafter, a provisional allotment letter dated 28.07.2014 was issued in respect of a flat on the first floor of Block-J in the concerned housing complex.
Subsequently, on 04.09.2014, the parties executed an Agreement for Sale in respect of the said flat together with an independent garage, for a total consideration of Rs.35,06,000/- excluding taxes and other charges. To finance the purchase, the complainant availed housing loan of Rs.20 lakh from IDBI Bank.
Under Clause 9.5 of the Agreement for Sale, possession was to be delivered within 36 months from the date of agreement, with a further extension of six months at the option of the developer. Thus, even on the most liberal construction, possession ought to have been delivered by end of March, 2018.
The complainant states that from time to time he paid substantial instalments, and in aggregate paid approximately Rs.35,13,391/-, amounting to nearly 95% of the total consideration, but possession was not handed over. Repeated requests and communications allegedly yielded only assurances.
By communication dated 07.03.2018, the complainant demanded compensation/interest for delay. OP No. 1 relied on Clause 11.3 and stated that compensation, if any, would be considered only at the time of possession.
The complainant further alleges that even in November 2019 construction was incomplete. Legal notice dated 27.11.2019 was issued demanding refund with interest. On failure of redressal, the present complaint was filed on 15.12.2019.
3. Submissions on behalf of the Complainant
The complainant’s case, in substance, is that he entered into the transaction bona fide for acquisition of a residential dwelling for personal use, arranged substantial finances including institutional housing finance, and faithfully performed his contractual obligations by paying almost the entire consideration amount. In spite thereof, the developer failed to discharge the corresponding and principal obligation of handing over possession of the flat within the agreed time and thereby committed grave deficiency in service.
According to the complainant, Clause 9.5 of the Agreement for Sale obligated the developer to deliver possession within 36 months from the date of execution of the agreement, with a further extension of six months at the option of the developer. Even after expiry of the outer contractual limit, possession was not off