Sangita Dhingra Sehgal, President, Pinki, Judicial Member
Raj Kishore – Appellant
Versus
TDI Infrastructure Ltd. – Respondent
CONSUMER COMPLAINT NO.-1010/2015



Important Points

The jurisdiction of Consumer Fora is not ousted by an arbitration clause, as the Act provides an additional, statutory remedy for grievances. Claims regarding deficiencies in property-related charges or area calculations require compelling evidence and cannot be decided based on mere assertions.

Subject

Consumer Law - Real Estate / Housing

Act Referred

Headnote

(A) Consumer Protection Act, 1986 - Section 2(1)(d) and Section 3 - Complaint against builder - Alleged unfair trade practice and deficiency in service - Maintainability of complaint - Consumer status of complainant - Whether existence of arbitration clause bars jurisdiction of Consumer Fora. (Paras 19, 31, 37, 38, 39, 43, 47)

(B) Builder Buyer Agreement - Super area variation - Demand for additional charges - Burden of proof to establish illegality - Failure of complainant to produce expert evidence to challenge builder's calculation - Effect of accepting possession without protest regarding specific charges. (Paras 49, 50, 51, 53, 54)

(C) Compensation - Delay in possession - Proof of loss - Claim for interest and rent - Failure to provide documentary evidence - Requirement of proving actual loss. (Paras 56, 58, 59, 60)

Facts of the case:
Complainant booked a flat in a project developed by the opposite party. Alleging excess charges for increased super area, illegal levies, and delay in possession beyond the stipulated 30-month period, the complainant sought a refund of excess amounts, compensation for delay, and registration of the conveyance deed. The builder defended the complaint, alleging it was for commercial investment purposes and barred by the arbitration clause.

Findings of Court:
The Court held that the complainant qualifies as a consumer and that the arbitration clause does not oust the jurisdiction of consumer forums. However, on merits, the Court found that the complainant failed to substantiate allegations regarding the super area measurement or the illegality of additional charges by producing credible expert evidence. Furthermore, claims for rental expenses and interest were found to be unsubstantiated and lacking proof of actual loss.

Issues: Whether the complainant is a consumer; whether the arbitration clause bars the complaint; and whether the builder was deficient in service regarding super area calculations and possession delays.

Ratio Decidendi: The legal remedy under the Consumer Protection Act is an additional statutory remedy that cannot be barred by an arbitration clause. However, where a complainant fails to provide expert or independent evidence to challenge the technical calculations or the justification of charges made by a developer, allegations of deficiency in service remain unsubstantiated and cannot be granted.

Result: Complaint dismissed.

Advocates:
For the Appellants/Petitioners: Mr. A.B. Pandey
For the Respondents: Ms. Kanika Agnihotri, Mr. Vaibhav Agnihotri

Table of Content
1. complaint against builder for deficiency in service and unfair trade practices. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29)
2. determination of consumer status under the act. (Para 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38)
3. impact of arbitration clauses on consumer jurisdiction. (Para 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47)
4. proof requirements for challenges to super area and charges. (Para 48 , 49 , 50 , 51 , 52 , 53 , 54)
5. compensation claims require substantiation of actual loss. (Para 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64)

PER : HON’BLE MS. PINKI, MEMBER (JUDICIAL)

JUDGMENT

1. The present complaint has been filed by the Complainant against the TDI Infrastructure Ltd. (hereinafter referred to as the ‘Opposite Party) alleging unfair trade practices and deficiency in service on the part of the Opposite Party. The Complainant has prayed for the following reliefs:

(a) Refund the excess amount of Rs.8,06,300/- (Rupees Eight Lakhs, Six Thousand and Three Hundred only) charged from the complainant, alongwith interest @ 21% per annum (the rate at which interest was charged by the respondent on all delayed payment, even when the installment have been deposited within time) payable with effect from 18th April, 2014 till realization.

(b) Pay to the complainant in compensation for the delay in delivery of possession amounting to Rs.42,292/- and the aggregate rental paid by the complainant for residence elsewhere amounting to Rs.88,000/-, alongwith interest @ 21% per annum payable with effect from 18th April 2014 till realization.

(c) Take step for registration of necessary conveyance deed in favour of the complainant.

(d) An amount of Rs.51,000/- (Rupees Sixty five thousand only) towards the aggregate legal expenses incurred and being incurred by the complainant.

Such other order/s as may be deemed fit in the circumstances, may also be passed.

2. Brief facts necessary for the adjudication of the present complaint, as stated by the Complainant, are that the Opposite Party had publicized and advertised its real estate project titled'Tuscan Floors, Tuscan City' (hereinafter referred to as 'the Project') situated at Kundli, Sonepat, Haryana, through advertisements in various forms of media, including in Delhi.

Copies of such advertisements are filed on record as Annexure C-1 at page No.13-14 of the complaint.

3. The Complainant applied for a flat in the project on 23.04.2010. Copies of the invitation for allotment dated 24.11.2010 and the allotment letter dated 03.12.2010 issued by the Opposite Party in favour of the Complainant are filed on record as annexure C-2 at page no.15-16 of the Complaint.

4. It is further case of the complainant that on the basis of the Complainant's application and payment of the requisite registration amount, Flat No. T-65, III Floor, comprising 3 bedrooms, a drawing/dining room, a kitchen, 2 toilets, and balconies, having a tentative super area of 108.14 square meters (1,164 square feet), was allotted to the Complainant in the Project for an initial total sale price of Rs.25,44,426/- under a Construction-Linked Payment Plan. The said sale price was payable in installments: 15% at registration, 15% at allotment, six installments of 10% each at various stages of construction, and the final balance of 10% at the time of possession. Copies of the confirmation of allotment, the execution of the Independent Floor/Apartment Buyer's Agreement dated 10.03.2011, and the said agreement itself are filed on record as annexure C-3 at page No.17-37 of this Complaint.

5. It is further submitted that the Complainant obtained a housing loan from a bank for the purpose of purchasing the said flat. A copy of the sanction letter dated 30.05.2011 issued by the Complainant's bank is filed on record as annexure C-5 at page No.64-65 of this Complaint. The Complainant thereafter regularly made all installments