2026 Supreme(Online)(SCDRC) 12066
STATE CONSUMER DISPUTES REDRESSAL COMMISSION
CHAITI BHATTACHARJEE D/o. LATE RATANANANDA BHATTACHARJEE – Appellant
Versus
ABHISHEK CHOWDHURY S/o. BIPUL CHODHURY – Respondent
SC/19/FA/46/2025
##PAGE1##
STATE CONSUMER DISPUTES REDRESSAL COMMISSION WEST BENGAL FIRST APPEAL NO. SC/19/FA/46/2025 (Against the Order dated 17th February 2025 in Complaint No. DC/AB1/303/CC/315/2024 of the District Consumer Disputes Redressal Commission Rajarhat)
CHAITI BHATTACHARJEE D/o. LATE RATANANANDA .......Appellant(s)
BHATTACHARJEE PRESENT ADDRESS - 271 SHYAMNAGAR ROAD GOURINATH SASTRI SARANI , 24 PARAGANAS NORTH,WEST BENGAL.
JABA BHATTACHAREE W/o. Late Ratanananda Bhattacharjee PRESENT ADDRESS - RESIDING AT 271 SHYAMNAGAR ROAD GOURINATH SASTRI SARANI , 24 PARAGANAS NORTH,WEST BENGAL.
Versus ABHISHEK CHOWDHURY S/o. BIPUL CHODHURY .......Respondent(s)
PRESENT ADDRESS - 232/1NAGENDRANATH ROAD , 24 PARAGANAS NORTH,WEST BENGAL.
SRI BIPUL CHOWDHURY S/o.
PRESENT ADDRESS - 232/1 NAGENDRA NATH ROAD NATUN PALLY
24 PARAGANAS NORTH,WEST BENGAL.
BEFORE:
HON'BLE MR. JUSTICE BIBHAS RANJAN DE , PRESIDENT HON'BLE MRS. MRIDULA ROY , MEMBER FOR THE APPELLANT: Adv Akshay Bhattacharya, Adv Partha Sarathi Bhadra (Advocate)
FOR THE RESPONDENT: ABHISHEK CHOWDHURY S/o. BIPUL CHODHURYSRI BIPUL CHOWDHURY S/o.
DATED: 01/09/2026
ORDER
HON'BLE MR. JUSTICE BIBHAS RANJAN DE, PRESIDENT
##PAGE2##LEAD-IN
1. This appellate invocation stands directed against the ultimate determination dated 17.02.2025, pronounced in Consumer Complaint No.315 of 2024, under whose canopy the Ld. District Consumer Disputes Redressal Commission, Rajarhat New Town (hereinafter referred to as Ld. DCDRC), in its wisdom, non-suited the complainant and dismissed the underlying application at the admission stage, with the following explicit mandates :
Dated : 17.02.2025 “
Order No.03 Record is taken up for hearing of admission of the case.
Heard the Ld. Advocate of the Complainant in details.
Perused the materials on record, contents of the Complaint Petition.
Complainant have filed the instant Complaint case against the Ops under Section 35 of the C.P. Act, 2019 for refund of earnest money to the Ops and other reliefs for not provided the documents (Porcha and Conversion Certificate) on the part of the Ops inspite of repeated requests. According to the Complainant cause of action arose on and from 14.03.2024 when agreement for sale was executed by and between the Complainant and the OPs and thereafter on several occasions inspite of receipt legal notice, the OP failed to provide the said two documents as noted above. The documents dt.11.07.2024 sent by the Senior Bank Manager, PNB Dum Dum reflects that without Porcha and Conversion Certificate of the land, Bank is unable to sanction the loan to the Complainant as per their proposal and ultimately the Bank rejected the load application of the Complainant due to non-filing of Porcha and Conversion Certificate of the land in question. The letter dt.05.07.2024 against the Advocate notice, sent by the Complainant the Ld. Advocate on behalf of the Ops sent reply as stated in para 2, in which they replied that the OP has already having a loan on the aforesaid property from IDBI Bank, which states the marketability of the said property. In para 6 it has been stated that ‘as the requirement of these documents are not binding as per the agreement, my client shall require timeline as per the requirement of the BLRO office to complete the procedures and procure the L.R. Parcha, which shall be provided to yourselves as and when received by my client from the BLRO office.’ Thus, reply sent by the Ld. Advocate of the Ops against the Advocate’s letter of the Complainant clearly shows that the alleged documents (Porcha and Conversion Certificate) as demanded by the Complainant is not within the knot of the OP, rather under the control of the Government i.e., BLRO. In this circumstance, we are not inclined to hold that there was latches on the part of the Ops to supply the Porcha and Conversion Certificate to the Complainant and thus it cannot be hold that there was deficiency of service on the part of the Ops and negligence regarding the cancellation of the Bank Loan Amount of