2015 Supreme(Online)(TDSAT) 37
TELECOM DISPUTES SETTLEMENT AND APPELLATE TRIBUNAL
Aftab Alam, CJ, Kuldip Singh, J, Bipin Bihari Srivastava, J
M/s Bharti Airtel Ltd. – Appellant
Versus
Bharat Sanchar Nigam Ltd. – Respondent
Petition No. 190 of 2014
For the Appellants/Petitioners:Mr. Gopal Jain, Sr. Advocate, Ms. Chinmayee Chandra, Advocate
For the Respondents:Ms. Maneesha Dhir, Advocate, Mr. Abhishek Kumar, Advocate, Mr. Prashant Jain, Advocate, Ms. Neha Singh, Advocate
The demand for rental after acceptance of line surrender is illegal as it novated the original agreement.
Headnote:(A) Telecom Disputes Settlement and Appellate Tribunal - Demand for payment of rental for leased lines - The Tribunal holds the demand of rent for three years as illegal due to prior acceptance of surrender of leased lines by BSNL's Dy. GM in the letter dated 6 January 2004, thus novating the original agreement which required retention of leased lines for a minimum of five years. The Bharti petition demonstrates the principle of novation in contractual obligations. (Paras 17, 23, 25)
(B) Legal Inevitable on payment adjustment - The Tribunal found that the security deposit could not legally support the ongoing demand after the premature surrender of services. The original commitment was altered by BSNL's acceptance of Bharti's request for surrender. The Tribunal categorized the demand as unjustifiable and beyond the remit of BSNL. (Paras 12, 15, 30)
Facts of the case:
Bharti Airtel challenged the demand for Rs.9,09,88,497/- for three-year rent for leased lines after BSNL had accepted the surrender of the lines as detailed in correspondence from 2004. (Paras 1-5)
Findings of Court:
The Tribunal set aside BSNL's demand on the grounds of its illegality arising from the premature surrender consent. (Paras 11-15)
Issues: Whether the termination of service following acceptance of line surrender invalidates continued rental demand and if the adjustment of rental payments is permissible according to original contract terms. (Paras 10, 21)
Ratio Decidendi: The demand for rental payments post-termination of the agreement is illegal; the acceptance of premature surrender constitutes a novation of the original lease contract. (Paras 19, 23)
Result: The petition is allowed, and BSNL is directed to refund the security deposit with interest.
| Table of Content |
|---|
| 1. facts surrounding bharti's leased lines and demand. (Para 1 , 2 , 3) |
ORDER
By Aftab Alam, Chairperson –
The Petitioner, Bharti Airtel Limited (Bharti, hereinafter) has filed this petition challenging the demand of Rs.9,09,88,497/- by the respondent, Bharat Sanchar Nigam Limited (BSNL, hereinafter) as three years’ rent for 36 leased lines, laid out by BSNL for the dedicated use by Bharti and given it on lease. The demand is contained in the letter dated 15 January 2014 which was followed by letter dated 26 March 2014 containing the threat that all the Bharti POIs,
The facts of the case are quite simple and may be stated thus. On Bharti’s request, BSNL leased out to it 74 dedicated lines of 2 Mbps each under agreement dated 2 May 2002. The terms and conditions stipulated in the agreement are as under:
“1. The licensee shall submit a commitment letter to BSNL to keep all the leased lines for a minimum period of 5 years.
2. BSNL while collecting the required leased line charges as per the existing guidelines of BSNL Corporate Office, New Delhi shall raise demand note for 2 years charges and the licensee shall pay the amount.
3. The charges collected by BSNL towards the second year will be kept as Security Deposit and this Deposit shall not carry any interest.
4. The licensee is required to renew the leased lines every year and for making the renewal payment by the licensee, the terms and conditions stipulated under chapter 7(Interconnect billing system) of the Interconnect agreement shall hold good.
5. In case the licensee fails to renew the leased lines or fails to make the renewal payment, the security deposit paid under clause 3 above shall be forfeited and this shall be without prejudice to any other action that shall be taken against the failure indicated above by BSNL.”
Clause 1 of the agreement terms required Bharti to submit a commitment letter to keep all the leased lines for a minimum period of five years which Bharti duly submitted. Clause 5 provided that in case Bharti failed to renew the leased lines or to make the renewal payment, the security deposit under clause 3 would be forfeited. It needs to be clarified here that leased lines had fixed annual rental, payable every year in advance. At the time of commissioning, BSNL raised demand notes in advance and Bharti paid the rental for two years. The annual rent for the second year was kept by BSNL as security. At the beginning of the second year, BSNL issued demand note for annual rent for the second year and the security deposit was kept as security for the rent for the third year, and so on. However, within two years of the commissioning of the leased lines in question, Bharti was able to up- grade it’s inter -connect device in the Synchronous Digital Hierarchy by entering into an arrangement with BSNL to set up an STM-1,
“We would therefore like to shift the entire interconnectivity at the various POI locations from a combination of leased lines ( 33 E1s at 12 POI locations