IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
THE HONOURABLE SMT JUSTICE K. SUJANA
B.SATHI REDDY SAHEBNAGAR R.R.DT – Appellant
Versus
HEMALATHA OSMANGUNJ HYD – Respondent
AS 1217/2002



HONOURABLE SMT JUSTICE K. SUJANA APPEAL SUIT No.1217 OF 2002

JUDGMENT:

This Appeal Suit is filed challenging the judgment dated

26.03.2002 made in O.S.No.416 of 1994 on the file of the Principal Senior Civil Judge, Ranga Reddy District.

2. The appellant herein is plaintiff, and respondent herein is defendant, in O.S.No.416 of 1994. For the sake of convenience, the parties herein are referred to as arrayed in suit.

3. The brief facts of the case are that the plaintiff instituted O.S.No.416 of 1994 seeking specific performance of an Agreement of Sale dated 08.12.1993 executed by the defendant, concerning one acre of agricultural land located in Survey Nos.218/1 and 221/1 of Sahebnagar Kalan Village, Hayathnagar Mandal. The total sale consideration was Rs.2,50,000/- of which Rs.50,000/- was paid at the time of agreement and the remaining Rs.2,00,000/- was to be paid in four scheduled installments. Clause 7 of the agreement emphasized that time was of the essence, and Clause 8 imposed an obligation on the defendant to clear any disputes affecting ownership before execution of the sale deed.

4. At the time of agreement, litigation was already pending against the defendant, including Inam Appeal No.B3/7774/93 filed by Kongara Ramulu and others challenging the grant of occupancy rights in her favor under the A.P. (Telangana Area) Abolition of Inams Act, 1955 (for short ‘the Act’). The plaintiff and his brothers also initiated Case No.A/1118/94 under Section 32 claiming protected tenancy over the same land. The plaintiff asserted that despite being ready and willing to pay the remaining consideration, the defendant failed to resolve these disputes and attempted to alienate the land elsewhere, while demanding a higher price citing escalation in market value.

5. In the written statement, the defendant admitted execution of the agreement and receipt of the initial Rs.50,000/- but denied that the litigation was pending, contending that the appeal had already been dismissed and that the patta continued in her name. She contended that the plaintiff had full knowledge of the litigation and had even participated in earlier revenue proceedings. She also denied the plaintiff's claim of willingness, alleging failure to pay the balance consideration within the contractual time frame. However, she stated that she was still willing to execute the sale deed, provided the plaintiff paid the remaining Rs.2,00,000/- with interest at 24% per annum.

6. Upon hearing both sides, the trial Court framed the following issues:

i. Whether the plaintiff was entitled to specific performance of the agreement dated 08.12.1993;

ii. Whether the plaintiff was not ready and willing to perform his part of the contract;

iii. Whether the defendant was entitled to the balance consideration with 24%

interest;

iv. To what relief was the plaintiff entitled.

7. During trial, the plaintiff got himself examined as PW1 and marked Exs.A1 to A7 including the agreement, payment receipts, legal notices, and order of this Court. It was stated that Ex.A7 receipt was introduced only during cross-examination and bore unexplained overwriting and substitutions of names, parentage, and locality. It was filed belatedly on 14.02.2002 i.e., the day the defendant was cross- examined. The trial Court found this document manipulated and inadmissible, viewing it as an attempt to falsely establish part performance during litigation.

8. The trial Court noted contradictions between pleadings and oral testimony, especially regarding the plaintiff’s readiness and willingness, and held that the plaintiff, having entered into the agreement with full knowledge of litigation, could not rely on Clause 8 to justify non-payment, and that his failure to honor the installment schedule and fabrication of Ex. A7 undermined his claim. The trial Court rejected the relief of specific performance, emphasizing that such relief is discretionary and grounded in equity. However, invoking Section 22 of the Specific Relief Act and co