2025 Supreme(Online)(Tel) 50692
IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
THE HONOURABLE SMT JUSTICE RENUKA YARA,THE HONOURABLE THE ACTING CHIEF JUSTICE SUJOY PAUL
National Highways Authority of India – Appellant
Versus
The State of Telangana – Respondent
WA 544/2025
THE HON’BLE THE ACTING CHIEF JUSTICE SUJOY PAUL AND THE HON’BLE SMT. JUSTICE RENUKA YARA WRIT APPEAL No.544 OF 2025 JUDGMENT: (Per Hon’ble Smt. Justice Renuka Yara)
Heard Sri M. Ramu, learned Standing Counsel for National Highways Authority of India, for the appellant and Sri Bhukya Mangilal Naik, learned Government Pleader for Endowments for the respondents. Perused the record.
2. Heard the Writ Appeal with consent of both counsels. Both counsels agreed that the Writ Appeal be disposed off in terms of the order passed by this Division Bench in W.P.No.10964 of 2022, dated
08.09.2022.
3. This is an intra-court appeal preferred by the appellant/petitioner aggrieved by the order passed by the learned Single Judge in W.P.No.34373 of 2024, dated 03.02.2025, wherein, the relief sought for grant of permission to acquire the land in Sy.No.73 to an extent of Ac.2.05 gts., situated at Irigipally Village, Sangareddy District and in Sy.No.313 to an extent of Ac.0.21 gts., situated at Tadlapalle Village, Sangareddy Mandal and District, belonging to respondent Nos.1 to 3 for the purpose of laying National Highway connecting from Girmapur Village (on NH65 at Chainage Km. 492 + 200) in Sangareddy District to Choutuppal (on NH 65 Chainage Km 55 + 400) in Yadadri Bhuvanagiri District via Medak and Siddipet Districts, has been declined.
4. The appellant filed writ petition seeking permission to acquire lands from Endowments Department for the purpose of laying National Highway between Sangareddy District and Yadadri Bhuvanagiri District as described. The learned Single Judge was apprised of the order of a Division Bench of this Court in W.P.No10964 of 2022, dated 08.09.2022 as well as the order in W.P.M.P.No.13204 of 2006 in W.P.No.10547 of 2006, dated 30.05.2006. This Court after taking stock of the manner in which temple lands were sold has given the following order in W.P.M.P.No.13204 of 2006 in W.P.No.10547 of 2006 on 30.05.2006:
“that there will be stay of all further proceedings in relation to the acquisition of the lands belongs to the temples all over the state, at whatever stage they are and any deviation, in this regard, would be treated as contempt of court”.
5. Subsequently, a Division Bench of this Court in W.P.No.10964 of 2022 dated 08.09.2022 in similar facts situation has passed the following order:
“4. It is submitted that before filing the present writ petition, petitioner had approached the Endowments Department for initiation of land acquisition proceedings to which the said Department has given ‘no objection’ to approach the Court in terms of the order dated 30.05.2006.
5. Having regard to the above, we grant permission to the petitioner for passing an award in terms of the provisions of the Right to Fair Compensation and Transparency in Land Acquisition and Rehabilitation and Resettlement Act (Act 30 of 2013) as amended by the State of Telangana by Act 21 of 2017. Petitioner shall ensure that due compensation in terms of the aforesaid Act is paid to respondent No.5, which shall be deposited in the account of respondent No.5. Thereafter, it would be open for respondent No.5 to keep the said amount in an interest bearing Fixed Deposit.”
6. On the basis of the above, similar orders were also passed in W.P.Nos.1767 of 2021, 26755 of 2021, 10964 of 2022, 29676 of 2021, 42198 of 2022, 22257 of 2022 and 10332 of 2024. All the orders were placed before the learned Single Judge for his perusal. In the aforementioned writ petitions, this Court had granted permission to acquire land by the Government for various purposes.
7. In the instant case, the land in question which was required for laying National Highway belongs to respondent Nos.1 to 3 i.e. Endowment Department. When the appellant sought no objection to acquire the land, the respondent Nos.1 to 3 have given no objection for said acquisition subject to payment of fair compensation as contemplated under Right to Fair Compensation and Transparency in Land Acquisition and Rehabilitation an