SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Tel) 11391

IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
Nagesh Bheemapaka, J
B. Sridhar Reddy – Appellant
Versus
Union of India – Respondent
WRIT PETITION No. 28152 of 2025



Advocates:
For the Appellants/Petitioners: Not listed
For the Respondents: Not listed

The High Court will not grant relief in land acquisition matters for national infrastructure projects where a specific statutory arbitration mechanism exists to resolve disputes over compensation, provided there is no manifest illegality or violation of natural justice in the acquisition process.

Headnote:(A) National Highways Act, 1956 - Sections 3A, 3C, 3D, 3G, 3H and 3E - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 26 to 30 - Land acquisition for national highway - Challenge to award and acquisition proceedings - Availability of statutory remedy - Writ jurisdiction - Exercise of. (Paras 1, 2.1, 10.2, 22)

(B) Writ Petition - Maintainability - Existence of alternative remedy - Held, that if an effective and efficacious remedy is available, the High Court would not normally exercise its jurisdiction - Statutory mechanism under the Act for redressal of disputes relating to compensation cannot be bypassed - The Court cannot nullify the acquisition of land unless it is found to be ex facie contrary to the mandate of law or tainted due to mala fides. (Paras 13, 15, 17, 21)

(C) Land Acquisition - Public purpose - Infrastructure project - The project involving construction of new highways is vital for development of infrastructure - The Court is not equipped to decide upon the viability and feasibility of a particular project or alignment - Scope of judicial review is very limited. (Paras 12, 13, 14)

Facts of the case:
The petitioner challenged the land acquisition proceedings for a highway project, alleging that the notifications were defective, environmental clearance was delayed, and compensation was improperly determined without accounting for structures, trees, or rehabilitation and resettlement benefits. The petitioner sought an order to stall the acquisition and re-evaluate the compensation.

Findings of Court:
The court noted that the project is a national infrastructure priority and that the acquisition process was conducted in accordance with the prescribed statutory framework. It observed that the petitioner failed to show any violation of fundamental rights or principles of natural justice and that a vast majority of other landowners had accepted the settled compensation. The court found that the statutory framework provides clear mechanisms for challenging compensation awards and determining entitlements.

Issues: Whether the writ petition is maintainable when there is an alternative statutory remedy for compensation disputes and whether the court should interfere with a national infrastructure project.

Ratio Decidendi: The court ruled that when a special enactment contains an inbuilt mechanism for adjudicating disputes regarding compensation and acquisition, the extraordinary jurisdiction of the High Court should not be invoked unless there are exceptional circumstances. The petitioner must exhaust the statutory arbitration process for the determination of compensation and potential grievances regarding resettlement before seeking further judicial recourse under arbitration laws.

Result: Writ petition disposed of, relegating the petitioner to statutory remedy; interim order vacated.

Table of Content
1. petitioner challenges land acquisition procedure and compensation adequacy. (Para 1)
2. respondents defend acquisition as compliant with nh act provisions. (Para 2 , 3)
3. parties reiterate procedural arguments and statutory remedy availability. (Para 4 , 5 , 6 , 8 , 9 , 10)
4. counsel cites precedents regarding property rights and procedural safeguards. (Para 7)
5. court directs aggrieved parties to statutory arbitration mechanism. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22)

ORDER:

The case of the petitioner, precisely, as per the writ affidavit is that the initial land acquisition notification issued under Section 3A of the National Highways Act, 1956, published in Gazette No.1102(E) dated 10.03.2021 and subsequently published in newspapers on 25.03.2021. This notification proposed the acquisition of lands across approximately ten villages in Parkal, Shayampet, and Damera mandals, including portions of the petitioner’s land, for construction of a new four-lane green highway. The petitioner asserts that the notification lacked adequate landowner-wise details and merely specified survey numbers and extents, making it difficult for affected persons to clearly identify their holdings. He further states that the notification claimed maps and plans were available with the competent authority, but in reality no such documents were accessible. Believing the project unnecessary given the existence of nearby National and State Highways that were allegedly underutilized, the petitioner and other affected farmers submitted general objections to the authorities. During the environmental impact assessment stage, a public hearing was conducted in which several landowners, including affected persons from the region, raised objections to the project.

1.1. For nearly a year thereafter, the petitioner claims there was no communication regarding the progress of the acquisition or environmental clearance. The situation changed when a public notice dated 04.02.2023 was issued under Section 3G of the National Highways Act, and published in newspapers on 15.02.2023, directing landowners to appear before the competent authority on various dates between 23.02.2023 and 09.03.2023 to submit their compensation claims. Through this notice, the petitioner states he first learned that a declaration under Section 3D had already been issued through Gazette No.1017 dated 08.03.2022, which effectively finalized the acquisition of the land. He asserts that this declaration was neither published locally nor circulated in newspapers with local readership, thereby depriving affected landowners of proper notice. In response, the petitioner and others submitted representations to the authorities requesting that the acquisition process be halted.

1.2. Subsequently, the petitioner and several other affected landowners approached this Court by filing W.P. No.5187 of 2023, challenging both the Section 3D declaration dated 08.03.2022 and the Section 3G award enquiry notice dated 04.02.2023. Their principal contention was that the acquisition process had advanced prior to obtaining environmental clearance, which they argued was impermissible under law. This Court initially granted stay of further proceedings for more than six months, but during the pendency of the writ petition the environmental clearance was obtained. As a result, the Court dismissed the petition in October 2023. The petitioner and others then filed Writ Appeal No.1190 of 2023, which was admitted and remains pending adjudication. The petitioner asserts that after the dismissal of the earlier writ petition and during the pendency of the writ appeal, the authorities resumed the acquisition process and proceeded to issue further notices and awards under Section 3G.

1.3. It is stated that in April 2024, several other landowners from Oorugonda village filed W.P. No.9909 of 2024, challenging multiple acquisition notifications including Section 3A notifications S.O.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top